School districts shall select their architectural and engineering consultants in accordance with chapter 39.80 RCW. As required by RCW 39.80.050, the district shall negotiate a contract with the most qualified consultants at a price which the school district determines is fair and reasonable. In making its determination, the district must take into account the estimated value of the services to be rendered based upon the scope and complexity of the project.
The state maximum allowable cost for architectural and engineering services must be based on the latest edition of the American institute of architect's handbook of professional practice and calculated by the percentage of construction cost in relation to the square foot area of construction and project type, as set forth in this subsection.
Square Feet of
Construction
Percent of
Construction Cost
0
3,699
5.0
3,700
7,349
4.5
7,350
10,999
4.375
11,000
14,649
4.25
14,650
18,299
4.125
18,300
25,699
4.0
25,700
36,699
3.875
36,700
54,999
3.75
55,000
73,399
3.625
73,400
100,999
3.5
101,000
128,449
3.375
128,450
155,999
3.25
156,000
183,499
3.125
183,500
& above
3.0
b. For modernization projects the limits of state funding assistance is 1.5 times the amount calculated for new construction.