Unless the context clearly requires otherwise, the definitions in this section apply throughout this chapter.

  1. "Closed record appeal" means an administrative appeal on the record to a local government body or officer, including the legislative body, following an open record hearing on a project permit application when the appeal is on the record with no or limited new evidence or information allowed to be submitted and only appeal argument allowed.

  2. "Local government" means a county, city, or town.

  3. "Open record hearing" means a hearing, conducted by a single hearing body or officer authorized by the local government to conduct such hearings, that creates the local government's record through testimony and submission of evidence and information, under procedures prescribed by the local government by ordinance or resolution. An open record hearing may be held prior to a local government's decision on a project permit to be known as an "open record predecision hearing." An open record hearing may be held on an appeal, to be known as an "open record appeal hearing," if no open record predecision hearing has been held on the project permit.

  4. [Empty]

    1. "Project permit" or "project permit application" means any land use or environmental permit or license required from a local government for a project action, including but not limited to subdivisions, binding site plans, planned unit developments, conditional uses, shoreline substantial development permits, site plan review, permits or approvals required by critical area ordinances, site-specific rezones which do not require a comprehensive plan amendment, but excluding the adoption or amendment of a comprehensive plan, subarea plan, or development regulations except as otherwise specifically included in this subsection.

    2. "Project permit" or "project permit application" does not include building permits.

  5. "Public meeting" means an informal meeting, hearing, workshop, or other public gathering of people to obtain comments from the public or other agencies on a proposed project permit prior to the local government's decision. A public meeting may include, but is not limited to, a design review or architectural control board meeting, a special review district or community council meeting, or a scoping meeting on a draft environmental impact statement. A public meeting does not include an open record hearing. The proceedings at a public meeting may be recorded and a report or recommendation may be included in the local government's project permit application file.

Section 2

  1. A local government by ordinance or resolution may exclude the following project permits from the provisions of RCW 36.70B.060 through 36.70B.080 and 36.70B.110 through 36.70B.130: Landmark designations, street vacations, or other approvals relating to the use of public areas or facilities, or other project permits, whether administrative or quasi-judicial, that the local government by ordinance or resolution has determined present special circumstances that warrant a review process or time periods for approval which are different from that provided in RCW 36.70B.060 through 36.70B.080 and 36.70B.110 through 36.70B.130.

  2. A local government by ordinance or resolution also may exclude the following project permits from the provisions of RCW 36.70B.060 and 36.70B.110 through 36.70B.130: Lot line or boundary adjustments and other construction permits, or similar administrative approvals, categorically exempt from environmental review under chapter 43.21C RCW, or for which environmental review has been completed in connection with other project permits.

  3. A local government must exclude project permits for interior alterations from site plan review, provided that the interior alterations do not result in the following:

    1. Additional sleeping quarters or bedrooms;

    2. Nonconformity with federal emergency management agency substantial improvement thresholds; or

    3. Increase the total square footage or valuation of the structure thereby requiring upgraded fire access or fire suppression systems.

  4. Nothing in this section exempts interior alterations from otherwise applicable building, plumbing, mechanical, or electrical codes.

  5. For purposes of this section, "interior alterations" include construction activities that do not modify the existing site layout or its current use and involve no exterior work adding to the building footprint.