wa-law.org > bill > 2023-24 > SB 5200 > Substitute Bill

SB 5200 - Capital budget

Source

Section 1

  1. A capital budget is hereby adopted and, subject to the provisions set forth in this act, the several dollar amounts hereinafter specified, or so much thereof as shall be sufficient to accomplish the purposes designated, are hereby appropriated and authorized to be incurred for capital projects during the period beginning with the effective date of this act and ending June 30, 2025, out of the several funds specified in this act.

  2. The definitions in this subsection apply throughout this act unless the context clearly requires otherwise.

    1. "Fiscal year 2024" or "FY 2024" means the period beginning July 1, 2023, and ending June 30, 2024.

    2. "Fiscal year 2025" or "FY 2025" means the period beginning July 1, 2024, and ending June 30, 2025.

    3. "Lapse" or "revert" means the amount shall return to an unappropriated status.

    4. "Provided solely" means the specified amount may be spent only for the specified purpose.

  3. Unless otherwise specifically authorized in this act, any portion of an amount provided solely for a specified purpose that is not expended subject to the specified conditions and limitations to fulfill the specified purpose shall lapse.

  4. The amounts shown under the headings "Prior Biennia," "Future Biennia," and "Total" in this act are for informational purposes only and do not constitute legislative approval of these amounts. "Prior biennia" typically refers to the immediate prior biennium for reappropriations, but may refer to multiple biennia in the case of specific projects. A "future biennia" amount is an estimate of what may be appropriated for the project or program in the 2025-2027 biennium and the following three biennia; an amount of zero does not necessarily constitute legislative intent to not provide funding for the project or program in the future.

  5. "Reappropriations" in this act are appropriations and, unless the context clearly provides otherwise, are subject to the relevant conditions and limitations applicable to appropriations. Reappropriations shall be limited to the unexpended balances remaining on June 30, 2023, from the 2021-2023 biennial appropriations for each project.

Section 1001

FOR THE OFFICE OF THE SECRETARY OF STATE

The appropriation in this section is subject to the following conditions and limitations: $5,000,000 of the Washington state library-archives building account—state appropriation is provided solely for costs associated with the design, permitting, and conservation plan development of the library-archives building. No later than December 1, 2023, the secretary of state shall present to the governor and the capital committees of the legislature funding options and a proposed construction schedule for construction of the library-archives building using anticipated revenue from a certificate of participation and no more than $30,000,000 in state building construction bonds over the 2023-2025 and 2025-2027 fiscal biennia.

Section 1002

FOR THE OFFICE OF THE SECRETARY OF STATE

Section 1003

FOR THE DEPARTMENT OF COMMERCE

The appropriation in this section is subject to the following conditions and limitations:

  1. The appropriation is subject to the provisions of RCW 43.63A.125.

  2. The department may not expend the appropriation in this section unless and until the nonstate share of project costs have been either expended or firmly committed, or both, in an amount sufficient to complete the project or a distinct phase of the project that is useable to the public for the purpose intended by this appropriation. This requirement does not apply to projects where a share of the appropriation is for design costs only.

  3. The appropriation is provided solely for the following list of projects:

American Legion Veteran Housing and Resource

Center$493,000

Asia Pacific Cultural Center Renovation$1,082,000

Behavioral Health Clinic$250,000

Benston Hall$247,000

Capital Expansion for Job Skills, Training,

Support, and More$100,000

Carl Maxey Center Remodel - Phase 3$350,000

Cham Community Center$2,050,000

Childcare and Development Center Phase II$200,000

CLR Certified Community Behavioral Health Center$2,446,000

Community Meal Program$672,000

Culinary Training Academy and Community Event

Space at HopeWorks$635,000

CYS Marina View Building Renovation$100,000

Eloise's Cooking Pot Food Bank Capital Remodel

Project$243,000

Energy Retrofit Project$135,000

Eritrean Community Center Expansion Project$312,000

Expanding Capacity for Workforce Development$99,000

Expansion of and Updates to GLOW Children ELC

Space$185,000

Expansion of public food business incubator$100,000

Food Bank Renovation$425,000

Food Pantry Renovation in Kittitas County$473,000

Global Neighborhood Building Expansion: Enhancing

Services$229,000

HVAC replacement for ECEAP Classrooms$188,000

Lake Stevens Food Bank Building$675,000

Landing Youth Service Center$297,000

Latino Arts and Culture Community Center$90,000

Makah Community Gymnasium$160,000

New Family Resource Center Construction$325,000

NEW Health Newport Capital Expansion$823,000

Nisqually Health and Wellness Center Project$6,000,000

North Seattle Family Support Center$1,090,000

Puyallup Food Bank Facilities$558,000

RAI Maker Space and Cultural Center$778,000

ReCyclery Infrastructure, Bathroom and Shop

Improvement Project$144,000

S. Everett/Mulkilteo Building Communities$100,000

Scott and Sis Names Family YMCA$3,000,000

Sea Mar CHC - Concrete$186,000

Sea Mar CHC - Elma$187,000

Sedro-Woolley Club Renovation$100,000

SEYFS Renovations$187,000

Snohomish Family Center Improvements$206,000

Step By Step Early Learning Center$2,622,000

Teen Center Building Renovation$318,000

UHeights Community Kitchen, Safety, and

Accessibility Project$250,000

Unbridled Spirit: Outdoor Program Space$68,000

United Learning Center$100,000

William Grose Innovation Center$250,000

Yelm Boys & Girls Club Remodel$100,000

YWCA Clark County Community Office Repairs and

Renovation$101,000

  1. $850,000 of the appropriation in this section is provided solely for the department to provide technical assistance to organizations interested in applying for the building communities fund grants.

Section 1004

FOR THE DEPARTMENT OF COMMERCE

The appropriation in this section is subject to the following conditions and limitations:

  1. The appropriation is subject to the provisions of RCW 43.63A.750.

  2. Except as directed otherwise prior to the effective date of this section, the department may not expend the appropriation in this section unless and until the nonstate share of project costs have been either expended, or firmly committed, or both, in an amount sufficient to complete the project or a distinct phase of the project that is useable to the public for the purpose intended by this appropriation. This requirement does not apply to projects where a share of the appropriation is for design costs only.

  3. The appropriation is provided solely for the following list of projects:

7th Street Theatre$145,000

Arté Noir$750,000

Cascade Public Media$1,000,000

Cornish College of the Arts$350,000

Experience Learning Community$200,000

Fire Mountain Arts Council$217,000

Friends of Gladish$600,000

Ghostlight Productions$200,000

Grand Tacoma Cinema Club DBA The Grand Cinema$500,000

Highland Park Improvement Club$400,000

Imagine Children's Museum$75,000

Lincoln Theatre Center Foundation Green$350,000

Magenta Theater$7,000

Orcas Center$350,000

Pacific Public Media$800,000

Pickford Film Center$550,000

Port Angeles Waterfront Center dba Field Arts &

Events Hall$2,000,000

Richland Players Inc$350,000

Sahak Khemararam Buddhist Association$500,000

Sea Mar Community Health Centers$350,000

Seattle Children's Theatre$750,000

Seattle Repertory Theatre Seattle Rep Renovations

for Accessibility$1,200,000

Seattle Symphony Orchestra$250,000

Seattle Theatre Group$491,000

Sequim City Band$401,000

SIFF$500,000

Spokane Valley Summer Theatre$1,849,000

Tacoma Arts Live Tacoma Armory Performance Venue

Renovation$2,000,000

The 5th Avenue Theatre Association$550,000

The Clymer Foundation$100,000

Theatre33$100,000

Vashon Allied Arts, Inc.$115,000

Section 1005

FOR THE DEPARTMENT OF COMMERCE

Section 1006

FOR THE DEPARTMENT OF COMMERCE

Section 1007

FOR THE DEPARTMENT OF COMMERCE

The appropriation in this section is subject to the following conditions and limitations:

  1. $5,000,000 of the appropriation in this section is provided solely for grants to local governments, public higher education institutions, school districts, tribal governments, and state agencies for improvements to facilities and related projects that result in energy and operational cost savings.

    1. At least 20 percent of each competitive grant round is designated for award to eligible projects in small cities or towns with a population of 5,000 or fewer residents.

    2. In each competitive round, a higher energy savings to investment ratio must result in a higher project ranking. Priority consideration must be given to applicants that have not received grant awards for this purpose in prior biennia.

    3. The department must determine a minimum match ratio to maximize the leverage of nonstate funds.

  2. [Empty]

    1. $2,000,000 of the appropriation in this section is provided solely for grants to be awarded in competitive rounds to local governments, public higher education institutions, school districts, tribal governments, and state agencies for projects that involve the purchase and installation of solar energy systems, including solar modules and inverters, with a preference for products manufactured in Washington.

    2. At least 20 percent of each competitive grant round is designated for award to eligible projects in small cities or towns with a population of 5,000 or fewer residents.

    3. In each competitive round, a higher energy savings to investment ratio must result in a higher project ranking. Priority consideration must be given to applicants that have not received grant awards for this purpose in prior biennia.

    4. The department must determine a minimum match ratio to maximize the leverage of nonstate funds.

  3. $3,000,000 of the appropriation in this section is provided solely for the energy efficiency and environmental performance improvements to minor works, stand-alone, and emergency projects at facilities owned by agencies that repair or replace existing building systems and reduce greenhouse gas emissions from state operations, including, but not limited to, HVAC, lighting, insulation, windows, and other mechanical systems. Eligibility for this funding is dependent on an analysis using the office of financial management's life-cycle cost tool that compares project design alternatives for initial and long-term cost-effectiveness.

  4. The department shall develop metrics that indicate the performance of energy efficiency efforts.

  5. If a grant is provided in subsection (1) or (3) of this section to purchase heating devices or systems, the agency must, whenever possible and most cost effective, select devices and systems that do not use fossil fuels.

  6. Grants provided in subsections (1), (2), and (3) of this section to state agencies are exempt from the match requirements in this section.

Section 1008

FOR THE DEPARTMENT OF COMMERCE

Section 1009

FOR THE DEPARTMENT OF COMMERCE

The appropriation in this section is subject to the following conditions and limitations: The appropriation in this section is provided solely for the following list of projects:

Bethel School District$1,080,000

Highline School District$809,000

Issaquah School District$1,057,000

Orondo School District$1,080,000

South Bend School District$300,000

Toppenish School District$1,080,000

Section 1010

FOR THE DEPARTMENT OF COMMERCE

The appropriation in this section is subject to the following conditions and limitations:

  1. The appropriation in this section is provided solely for a local library capital improvement grant program for the following list of projects:

City of Longview$750,000

City of Port Townsend$173,000

City of Shelton$70,000

City of South Bend$673,000

City of Walla Walla$2,000,000

Stevens County Rural Library District$615,000

Tacoma Public Library$2,000,000

  1. The department must establish a competitive process to solicit proposals for and prioritize projects whose primary objective is to assist libraries operated by governmental units, as defined in RCW 27.12.010, in acquiring, constructing, repairing, or rehabilitating facilities.

  2. The department must establish a committee to develop the grant program criteria established under subsection (2) of this section and review proposals. The committee must be composed of five members as provided in this subsection. The committee must include: (a) A representative from the department of commerce; (b) a representative from the department of archaeology and historic preservation; (c) the state librarian; (d) a representative from a library district; and (e) a representative from a municipal library.

  3. The department must conduct a statewide solicitation of project applications. The department must evaluate and rank applications in consultation with the committee established in subsection (3) of this section, using objective criteria. The ranking of projects must prioritize library district facilities listed on a local, state, or federal register of historic places and those located in distressed or rural counties. The evaluation and ranking process must also include an examination of existing assets that applicants propose to apply to projects. Grant assistance under this section may not exceed 50 percent of the total cost of the project. The nonstate portion of the total project cost may include cash, the value of real property when acquired solely for the purpose of the project, and in-kind contributions.

  4. The department must submit a prioritized list of recommended projects to the governor and the legislature by October 1, 2024, for inclusion in the department of commerce's 2025-2027 biennial capital budget request. The list must include a description of each project, the amount of recommended state funding, and documentation of nonstate funds to be used for the project. Individual grants may not exceed $2,000,000. The total amount of recommended state funding for the projects on a biennial project list may not exceed $10,000,000.

  5. In contracts for grants authorized under this section, the department must include provisions that require that capital improvements be held by the grantee for a specified period of time appropriate to the amount of the grant and that facilities be used for the express purpose of the grant. If the grantee is found to be out of compliance with provisions of the contract, the grantee must repay to the state general fund the principal amount of the grant plus interest calculated at the rate of interest on state of Washington general obligation bonds issued on the date most close in time to the date of authorization of the grant.

  6. The department must assist grant recipients under this section to apply for applicable competitive federal grant funding and, upon receipt of any such funding, an equal amount of the state building construction account—state appropriation must be placed in unallotted status.

Section 1011

FOR THE DEPARTMENT OF COMMERCE

Section 1012

FOR THE DEPARTMENT OF COMMERCE

Section 1013

FOR THE DEPARTMENT OF COMMERCE

The appropriation in this section is subject to the following conditions and limitations: $50,000,000 of the appropriation in this section is provided solely as match for grant funding received by the department for the broadband equity, access, and deployment state grants program in section 60102 of P.L. 117-58 (infrastructure investment and jobs act). Expenditure of the amount in this subsection is contingent on the receipt of this grant funding.

Section 1014

FOR THE DEPARTMENT OF COMMERCE

The appropriations in this section are subject to the following conditions and limitations:

  1. $5,000,000 of the state building construction account—state appropriation in this section is provided solely for grants for the Washington State University energy extension community energy efficiency program (CEEP) to support homeowners, tenants, and small business owners in making sound energy efficiency investments by providing consumer education and marketing, workforce support through training and lead generation, and direct consumer incentives for upgrades to existing homes and small commercial buildings. This is the maximum amount the department may expend for this purpose.

  2. The department must, to the extent practicable, implement the recommendations in the weatherization plus health 2022 report.

  3. If funding from these appropriations are used to purchase heating devices or systems, the agency shall, whenever possible and most cost effective, select devices and systems that do not use fossil fuels.

  4. The department must:

    1. Recruit community energy efficiency program sponsors that are community-based organizations located in geographic areas of the state that have not received funding for low-income weatherization programs, targeting hard to reach market segments;

    2. Leverage funding from community energy efficiency program sponsors in an amount greater than or equal to the amount provided by the state through the weatherization program;

    3. Ensure that community energy efficiency program utility sponsors work with nonprofit community-based organizations to deliver community energy efficiency program services; and

    4. Identify community energy efficiency program sponsors that support the conversion of space and water heating from fossil fuels to electricity, as part of a set of energy efficiency investments.

Section 1015

FOR THE DEPARTMENT OF COMMERCE

The appropriation in this section is subject to the following conditions and limitations:

  1. The appropriation is subject to the provisions of RCW 43.63A.135.

  2. Except as directed otherwise prior to the effective date of this section, the department may not expend the appropriation in this section unless and until the nonstate share of project costs have been either expended or firmly committed, or both, in an amount sufficient to complete the project or a distinct phase of the project that is useable to the public for the purpose intended by this appropriation. This requirement does not apply to projects where a share of the appropriation is for design costs only.

  3. The appropriation is provided solely for the following list of projects:

Camp Kilworth Lodges Renovation and Activation$500,000

Coupeville Boys & Girls Club Construction Project$391,000

Dylan Jude Harrell Community Center Gymnasium$384,000

Evergreen Pool Updates$75,000

EYFO Youth Enrichment Center$1,200,000

GHHS Safe Learning Spaces$254,000

Multicultural Youth Recreation Facility$226,000

OIC Excel Youth Center$1,054,000

Performing Arts Center Spokane Valley$1,176,000

The Auburn Valley YMCA Health Kids Campus$1,200,000

The Lummi Nation BGC Facility Improvement Project$340,000

University Family YMCA$1,200,000

Section 1016

FOR THE DEPARTMENT OF COMMERCE

Section 1017

FOR THE DEPARTMENT OF COMMERCE

The appropriations in this section are subject to the following conditions and limitations:

  1. Except as provided in subsection (2) of this section, the appropriations in this section are subject to the following conditions and limitations: The appropriations in this section are provided solely for planning and predesign work, project predevelopment work, and development of clean energy projects that contribute to achieving the state's greenhouse gas emissions limits and related policies.

    1. As part of the planning activities under this section, the department must convene a work group to:

      1. Analyze the financial investments required for owners of tier 1 covered buildings to comply with the state energy performance standard under RCW 19.27A.210; and

      2. Make recommendations to the legislature to assist building owners in attaining compliance, which must include, but are not limited to:

(A) Identifying energy efficiency investments or other strategies and related timelines for increasing energy efficiency in the buildings sector;

(B) Providing a cost-benefit analysis of options, including energy efficiency, to meet the goal of reducing greenhouse gas emissions from the buildings sector; and

(C) Recommendations to balance financial investments while maximizing clean energy benefits for the state, including statutory changes that may be necessary for this purpose.

b. The work group membership convened under this section must include, but is not limited to: One representative of the office of the superintendent of public instruction; one representative of a K-12 maintenance and operation administrators association; one representative of each of the state's public four-year institutions of higher education; one representative of the state board for community and technical colleges; one representative of the department of social and health services; one representative of the department of corrections; one representative of the department of enterprise services; one representative of a health care organization; one representative from a local government; one representative from an organization representing privately owned tier 1 covered buildings; and two representatives of a national association for industrial and office parks.

The department must submit to the appropriate committees of the legislature:

    i. Analysis of financial investments as required by this section by December 15, 2023; and

    ii. A final report with recommendations as required by this section by September 1, 2024.
  1. $7,500,000 of the climate commitment account—state appropriation is provided solely for a regional energy analytics capability at Pacific Northwest national laboratory.

Section 1018

FOR THE DEPARTMENT OF COMMERCE

The appropriations in this section are subject to the following conditions and limitations:

  1. $168,871,000 of the state taxable building construction account—state appropriation and $3,000,000 of the capital community assistance account—state appropriation are provided solely for the new construction of affordable housing projects that serve and benefit low-income and special needs populations including, but not limited to, people with chronic mental illness or behavioral health conditions, farmworkers, people who are homeless, and people in need of permanent supportive housing. The department shall strive to invest at least 20 percent of the appropriation provided under this subsection with by and for organizations, as defined by the office of equity.

  2. $25,000,000 of the state taxable building construction account—state appropriation is provided solely for affordable housing projects that serve and benefit low-income people with developmental or intellectual disabilities. The department must coordinate with the department of social and health services regarding any needed supportive services and make efforts to enact the recommendations of the housing needs study for individuals with intellectual and developmental disabilities, as provided in section 1068(6), chapter 332, Laws of 2021.

  3. $70,000,000 of the state taxable building construction account—state appropriation is provided solely for the apple health and homes rapid permanent supportive housing program created in chapter 216, Laws of 2022.

  4. [Empty]

    1. $40,000,000 of the state taxable building construction account—state appropriation is provided solely for awards to organizations eligible under RCW 43.185A.040 for the development of homeownership projects affordable to first-time low-income households throughout the state. Homebuyers whose income is up to 100 percent of the area median income, adjusted for household size, for the county where the property is located are eligible to apply. Eligible activities include, but are not limited to, down payment assistance, closing costs, acquisition, rehabilitation costs, and new construction. Eligible organizations may include those that plan to provide housing to socially disadvantaged communities as defined in 13 C.F.R. Sec. 124.103. The department shall provide outreach and technical assistance to by and for organizations, as defined by the office of equity, with the intent of increasing the percentage of by and for organizations that participate and are successful in obtaining funding under this section, strive to invest at least 50 percent of these funds with by and for organizations, and make efforts to enact the recommendations of the homeownership disparities work group created in section 128(100), chapter 297, Laws of 2022.

    2. In addition to the definition in RCW 43.185A.010, for the purposes of awarding funds to homeownership projects during the 2023-2025 fiscal biennium, "first-time home buyer" also includes:

      1. A single parent who has only owned a home with a former spouse while married;

      2. An individual who is a displaced homemaker as defined in 24 C.F.R. Sec. 93.2 as it existed on the effective date of this section, or such subsequent date as may be provided by the department by rule, consistent with the purposes of this section, and who has only owned a home with a spouse;

      3. An individual who has only owned a principal residence not permanently affixed to a permanent foundation in accordance with applicable regulations; or

      4. An individual who has only owned a property that is discerned by a licensed building inspector as being uninhabitable.

  5. $40,000,000 of the state building construction account—state appropriation is provided solely for affordable housing preservation projects, which may include, but are not limited to:

    1. Projects preserving and extending the affordability commitment period for projects in the housing trust fund portfolio. The funds may be provided for major building improvements, preservation, and system replacements, necessary for the existing housing trust fund portfolio to maintain long-term viability. The department must require a capital needs assessment be provided prior to contract execution. Funds may not be used to add or expand the capacity of the property. When allocating funds, the department must prioritize buildings that are older than 15 years and that serve very low-income and extremely low-income populations.

    2. Projects preserving affordable multifamily housing at risk of losing its affordability due to expiration of use restrictions that otherwise require affordability including, but not limited to, United States department of agriculture funded multifamily housing. The department must prioritize projects that satisfy the goal of long-term preservation of Washington's affordable multifamily housing stock, particularly in rural areas of the state. Funds may be used for acquisition or for acquisition and rehabilitation of properties to preserve the affordable housing units beyond their existing use restrictions and keep them in Washington's housing portfolio for a minimum of 40 years. If a capital needs assessment is required, the department must work with the applicant to ensure that this does not create an unnecessary impediment to rapidly accessing these funds.

    3. The funding provided under this subsection (5) is not subject to the 90-day application periods in RCW 43.185.070 or 43.185A.050.

    4. The amount awarded under this subsection (5) may not be calculated in award limitations for other housing trust fund awards.

  6. $6,000,000 of the state taxable building construction account—state appropriation is provided solely for awards to organizations eligible under RCW 43.185A.040 and organizations defined as mobile home park cooperatives and manufactured housing cooperatives under RCW 59.20.030 for the acquisition and preservation of mobile or manufactured home communities. Funds provided under this subsection can be used to acquire mobile or manufactured home communities for the purpose of avoiding household displacement due to sale or other transactions and ensuring preservation of housing affordability for low-income households for a minimum of 40 years.

  7. $47,129,000 of the state taxable building construction account—state appropriation is provided solely for the following list of projects:

African Diaspora Cultural Anchor Village (SeaTac)$4,000,000

Bridge Meadows Tacoma (Tacoma)$515,000

Kenmore Supportive Housing (Kenmore)$5,100,000

Lewis County Homeless Shelter (Chehalis)$2,500,000

Lincoln District Family Housing (Tacoma)$5,050,000

Mary's Place Shelter Replacement (Burien)$6,000,000

Mills Crossing Affordable Housing Project

(Bremerton)$2,000,000

Mount Zion Housing (Seattle)$1,000,000

Multicultural Village Design (Kent)$550,000

New Beginnings Home (Puyallup)$427,000

New Hope Family Housing (Seattle)$325,000

Peninsula Community Health Housing (Bremerton)$412,000

Tacoma/Pierce County Habitat Affordable Housing (Pierce

County)$14,000,000

Rural Resources Community Action Central Colville

Apts (Colville)$50,000

Shelton Young Adult Transitional Housing (Shelton)$1,200,000

Shiloh Baptist Church New Life Housing (Tacoma)$1,000,000

Skyway Affordable Housing (Skyway)$3,000,000

  1. In evaluating projects in this section, the department must give preference for applications based on some or all of the criteria in RCW 43.185.070(5).

  2. The appropriations in this section are subject to the following reporting requirements:

    1. The department must report on its website the following for every previous funding cycle: The number of homeownership and multifamily rental projects funded by housing trust fund moneys; the percentage of housing trust fund investments made to homeownership and multifamily rental projects; and the total number of households being served at up to 80 percent of the area median income, up to 50 percent of the area median income, and up to 30 percent of the area median income, for both homeownership and multifamily rental projects.

    2. By November 1, 2023, and November 1, 2024, the department must provide the legislature and the governor with a report of its final cost data for each project under this section. Such cost data must, at a minimum, include total development cost per unit for each project completed within the past year, descriptive statistics such as average and median per unit costs, regional cost variation, and other costs that the department deems necessary to improve cost controls and enhance understanding of development costs. The department must coordinate with the housing finance commission to identify relevant development costs data and ensure that the measures are consistent across relevant agencies.

  3. The department shall strive to allocate at least 30 percent of the funds provided in this section to projects located in rural areas of the state, as defined by the department.

  4. The department must strive to allocate all of the amounts appropriated in this section within the 2023-2025 fiscal biennium in the manner prescribed in each subsection of this section. However, if upon review of applications the department determines there are not adequate suitable projects in a category, the department may allocate funds to other affordable housing projects serving other low-income and special needs populations, provided those projects are located in an area with an identified need for the type of housing proposed.

Section 1019

FOR THE DEPARTMENT OF COMMERCE

The appropriation in this section is subject to the following conditions and limitations:

  1. The appropriation in this section is provided solely for grants to local governments and public utility districts for system development charges, impact fees, and utility improvements for new affordable housing projects that serve and benefit low-income households. Where applicable, the extension must be consistent with the approved comprehensive plans under the growth management act and must be within the established boundaries of the urban growth area.

  2. $18,000,000 of the state building construction account—state appropriation in this section is provided solely for grants to local governments or public utilities located within a jurisdiction that impose a sales and use tax under RCW 82.14.530(1)(a)(ii), 82.14.530(1)(b)(i)(B), 82.14.540, or 84.52.105.

  3. $2,000,000 of the state building construction account—state appropriation in this section is provided solely for the aviva crossing sanitary sewer upgrades (Tacoma) project.

  4. To be eligible for funding under subsection (2) of this section, an applicant must demonstrate, at minimum:

    1. That affordable housing development will begin construction within 24 months of the grant award; and

    2. A strong probability of serving the original target group or income level for a period of at least 25 years.

  5. For purposes of this section, the following definitions apply.

    1. "Affordable housing" has the same meaning as in RCW 43.185A.010.

    2. "Impact fees" means fees that are collected under chapter 82.02 RCW and waived under RCW 82.02.060(4), including the remaining fees when a full waiver is granted under RCW 82.02.060(4).

    3. "Low-income household" has the same meaning as in RCW 43.185A.010.

    4. "System development charges" means charges for new drinking water, wastewater, or stormwater connections when a local government or public utility has waived standard fees normally applied to developers for connection charges on affordable housing projects.

    5. "Utility improvements" means drinking water, wastewater, or stormwater utility improvements.

Section 1020

FOR THE DEPARTMENT OF COMMERCE

The appropriations in this section are subject to the following conditions and limitations: The appropriations in this section are provided solely as match to private investment for grants to for-profit and nonprofit housing developers and public entities to carry out projects designed to increase the supply and affordability of transit-oriented housing development. The department shall work with the department of transportation to develop and administer a competitive grant program to assist in the financing of housing projects within rapid transit corridors created in section 3, chapter . . ., Laws of 2023 (Engrossed Substitute Senate Bill No. 5466). If Engrossed Substitute Senate Bill No. 5466 is not enacted by June 30, 2023, the department shall implement the program pursuant to the following eligibility criteria and definitions:

  1. Entities eligible to receive grant awards are state agencies, local governments, and nonprofit or for-profit housing developers. Eligible uses of grant awards include project capital costs and infrastructure costs and addressing gaps in project financing that would prevent ongoing or complete project construction.

  2. [Empty]

    1. Except as provided in (b) of this subsection, eligible housing projects must meet the following requirements:

      1. Be within one-quarter mile of a rapid transit corridor. For purposes of this section, "rapid transit corridor" includes light rail, commuter rail, bus rapid transit, and bus stops that meet certain high-use thresholds as defined in rule;

      2. Comply with floor area ratio or net density minimums as defined in rule;

      3. Produce at least 100 units of housing; and

      4. Include a covenant on the property requiring at least 20 percent of units remain affordable for households with incomes at or below 80 percent of area median income for at least 99 years.

    2. No more than five percent of grant funds may be awarded to housing projects within rapid transit corridors that meet the requirements under (a) of this subsection, except for requirements under (a)(i) or (iii) of this subsection.

  3. The department must prioritize eligible projects by occupancy date, with a target occupancy date of December 31, 2025. The department must also consider the following criteria when prioritizing projects:

    1. Are comprised of the largest percentage of affordable units;

    2. Have a high concentration of units affordable to households with incomes at or below 50 percent area median income;

    3. Do not include costs related to land acquisition;

    4. Include land acquired at a reduced price or without cost;

    5. Abide by antidisplacement measures, if appropriate;

    6. Submitted by community-based housing developers;

    7. Include units with additional bedrooms or intended for occupancy by families with multiple dependents; or

    8. Have acquired all necessary permits.

  4. The department may adopt any necessary rules to implement the competitive grant program under this section, including any additional project eligibility criteria and prioritization criteria.

Section 1021

FOR THE DEPARTMENT OF COMMERCE

The appropriation in this section is subject to the following conditions and limitations:

  1. The appropriation in this section is provided solely for the department to issue grants to community hospitals or other community providers to expand and establish new capacity for behavioral health services in communities. The department must consult an advisory group consisting of representatives from the department of social and health services, the health care authority, one representative from a managed care organization, one representative from an accountable care organization, and one representative from the association of county human services. Amounts provided in this section may be used for construction and equipment costs associated with establishment of the facilities. The department may approve funding for the acquisition of a facility if the project will result in increased behavioral health capacity. Amounts provided in this section may not be used for operating costs associated with the treatment of patients using these services.

  2. The department must establish criteria for the issuance of the grants, which must include:

    1. Evidence that the application was developed in collaboration with one or more regional behavioral health entities that administer the purchasing of services;

    2. Evidence that the applicant has assessed and would meet gaps in geographical behavioral health services needs in their region;

    3. Evidence that the applicant is able to meet applicable licensing and certification requirements in the facility that will be used to provide services;

    4. A commitment by applicants to serve persons who are publicly funded and persons detained for involuntary commitment under chapter 71.05 RCW;

    5. A commitment by the applicant to maintain and operate the beds or facility for a time period commensurate to the state investment, but for at least a 15-year period;

    6. The date upon which structural modifications or construction would begin and the anticipated date of completion of the project;

    7. A detailed estimate of the costs associated with opening the beds;

    8. A financial plan demonstrating the ability to maintain and operate the facility; and

    9. The applicant's commitment to work with local courts and prosecutors to ensure that prosecutors and courts in the area served by the hospital or facility will be available to conduct involuntary commitment hearings and proceedings under chapter 71.05 RCW.

  3. In awarding funding for projects in subsection (5) of this section, the department, in consultation with the advisory group established in subsection (1) of this section, must strive for geographic distribution and allocate funding based on population and service needs of an area. The department must consider current services available, anticipated services available based on projects underway, and the service delivery needs of an area.

  4. The department must prioritize projects that increase capacity in unserved and underserved areas of the state.

  5. [Empty]

    1. $15,000,000 of the state building construction account—state appropriation in this section is provided solely for the department to provide grants to community hospitals, freestanding evaluation and treatment providers, or freestanding psychiatric hospitals to develop capacity for beds to serve individuals on 90-day or 180-day civil commitments as an alternative to treatment in the state hospitals. In awarding this funding, the department must coordinate with the department of social and health services, the health care authority, and the department of health and must only select facilities that meet the following conditions:

      1. The funding must be used to increase capacity related to serving individuals who will be transitioned from or diverted from the state hospitals;

      2. The facility is not subject to federal funding restrictions that apply to institutions of mental diseases;

      3. The provider has submitted a proposal for operating the facility to the health care authority;

      4. The provider has demonstrated to the department of health and the health care authority that it is able to meet the applicable licensing and certification requirements for the facility that will be used to provide services; and

    2. The health care authority has confirmed that it intends to contract with the facility for operating costs within funds provided in the operating budget for these purposes.

    3. $19,253,000 of the state building construction account—state appropriation in this section is provided solely for competitive community behavioral health grants to address regional needs. When distributing funding under this subsection (5)(b), the department of commerce shall prioritize projects for secure withdrawal management and stabilization treatment beds not subject to federal funding restrictions that apply to institutions of mental disease.

    4. $15,000,000 of the state building construction account—state appropriation in this section is provided solely for intensive behavioral health treatment facilities for long-term placement of behavioral health patients with complex needs and that are not subject to federal funding restrictions that apply to institutions of mental diseases.

    5. $10,000,000 of the state building construction account—state appropriation in this section is provided solely for grants to community providers to increase behavioral health services and capacity for children and minor youth including, but not limited to, services for youth crisis walk-in intervention, substance use disorder treatment, sexual assault and traumatic stress, anxiety, or depression, children with behavioral health and intellectual or developmental disability needs, and interventions for children exhibiting aggressive or depressive behaviors in facilities that are not subject to federal funding restrictions. Consideration must be given to programs that incorporate outreach and treatment for youth dealing with behavioral health or social isolation issues.

    6. $82,192,000 of the state building construction account—state appropriation in this section is provided solely for the following list of projects:

Aristo Healthcare Services (Renton)$2,000,000

Compass Health Broadway Behavioral Health

Services (Everett)$18,700,000

Jamestown S'Klallam Behavior Health

Center (Sequim)$25,745,000

Lummi Nation Substance Abuse Treatment

(Bellingham)$8,147,000

Nisqually Tribe Healing Village (Olympia)$12,000,000

Recovery Innovations Crisis Stabilization

(Federal Way)$1,600,000

SHC Medical Center - Astria/Toppenish Hospital

(Toppenish)$2,500,000

Spokane Treatment and Recovery Service (Spokane)$4,000,000

Three Rivers Behavioral Health Center (Kennewick)$5,000,000

Tubman Center for Health and Freedom (Seattle)$2,500,000

  1. The department shall notify all applicants that they may be required to have a construction review performed by the department of health.

  2. To accommodate the emergent need for behavioral health services, the department and the department of health, in collaboration with the health care authority and the department of social and health services, must establish a concurrent and expedited process to assist grant applicants in meeting any applicable regulatory requirements necessary to operate inpatient psychiatric beds, freestanding evaluation and treatment facilities, enhanced services facilities, triage facilities, crisis stabilization facilities, or secure detoxification/secure withdrawal management and stabilization facilities.

  3. The department must strive to allocate all of the amounts appropriated within subsection (5) of this section in the manner prescribed. However, if upon review of applications, the department determines, in consultation with the advisory group established in subsection (1) of this section, that there are not adequate suitable projects in a category of projects under subsection (5) of this section, the department may allocate funds to other behavioral health capacity project categories within subsection (5) of this section, prioritizing projects that support serving individuals who will be transitioned from or diverted from the state hospitals or that are under subsections (5)(b) and (d) of this section. Underserved areas of the state may also be considered.

  4. The department must provide a progress report by September 1, 2024. The report must include:

    1. The total number of applications and amount of funding requested;

    2. A list and description of the projects approved for funding including state funding, total project cost, services anticipated to be provided, bed capacity, and anticipated completion date;

    3. A statewide map of new capacity since 2018, including projected bed capacity and opening dates; and

    4. A status report of projects that received funding in prior funding rounds, including details about the project completion and the date the facility began providing services.

  5. The department must coordinate with the health care authority to request capital budget funding for behavioral health community capacity grants for the 2025-2027 biennial budget by the due date established by the office of financial management. Associated operating costs must also be identified.

Section 1022

FOR THE DEPARTMENT OF COMMERCE

The appropriations in this section are subject to the following conditions and limitations:

  1. $7,500,000 of the state building construction account—state appropriation in this section is provided solely for minor renovation grants.

  2. $25,050,000 of the Ruth Lecocq Kagi early learning facilities development account—state appropriation in this section is provided solely for the early learning facility grant and loan program, subject to the provisions of RCW 43.31.573 through 43.31.583 and 43.84.092, to provide state assistance for designing, constructing, purchasing, expanding, or modernizing public or private early learning education facilities for eligible organizations. Up to four percent of the funding in this subsection may be used by the department of children, youth, and families to provide technical assistance to early learning providers interested in applying for the early learning facility grant or loan program.

  3. $21,000,000 of the state building construction account—state appropriation in this section is provided solely for the following list of projects:

Eastside Early Childhood Center (Bellevue)$1,100,000

Oak Harbor Early Learning Center (Oak Harbor)$13,900,000

Rainier Valley Early Learning Center (Seattle)$6,000,000

  1. $350,000 of the state building construction account—state appropriation in this section is provided solely for the early learning facilities capital readiness pilot program. The department, in partnership with the department of children, youth, and families, shall administer the program as part of the early learning facilities program. The early learning facilities capital readiness pilot program must support no more than 10 licensed early learning providers that will serve children through working connections child care or through the early childhood education and assistance program to study the feasibility of expanding, remodeling, purchasing, or constructing early learning facilities and classrooms. Participants must receive small grants and project support to conduct capital feasibility studies that cover financing, architectural design, construction, business operations, and other relevant topics. Participants must also have access to professional consultation related to financing, architectural design, construction, and business operations.

  2. The department of children, youth, and families must develop methodology to identify, at the school district boundary level, the geographic locations of where early childhood education and assistance program slots are needed to meet the entitlement specified in RCW 43.216.556. This methodology must be linked to the caseload forecast produced by the caseload forecast council and must include estimates of the number of slots needed at each school district. This methodology must inform any early learning facilities needs assessment conducted by the department and the department of children, youth, and families. This methodology must be included as part of the budget submittal documentation required by RCW 43.88.030.

  3. When prioritizing areas with the highest unmet need for early childhood education and assistance program slots, the committee of early learning experts convened by the department pursuant to RCW 43.31.581 must first consider those areas at risk of not meeting the entitlement specified in RCW 43.216.556.

  4. The department must track the number of slots being renovated separately from the number of slots being constructed and, within these categories, must track the number of slots separately by program for the working connections child care program and the early childhood education and assistance program.

  5. When prioritizing applications for projects pursuant to RCW 43.31.581, the department must award priority points to applications from a rural county or from extreme child care deserts as defined by the department of children, youth, and families.

Section 1023

FOR THE DEPARTMENT OF COMMERCE

The appropriation in this section is subject to the following conditions and limitations:

  1. The department shall not expend the appropriation in this section unless and until the nonstate share of project costs have been either expended or firmly committed, or both, in an amount sufficient to complete the project or a distinct phase of the project that is useable to the public for the purpose intended by the legislature. This requirement does not apply to projects where a share of the appropriation is for design costs only.

  2. Prior to receiving funds, project recipients must demonstrate that the project site is under control for a minimum of 10 years, either through ownership or a long-term lease. This requirement does not apply to appropriations for preconstruction activities or appropriations in which the sole purpose is to purchase real property that does not include a construction or renovation component.

  3. Projects funded in this section may be required to comply with Washington's high performance building standards under chapter 39.35D RCW.

  4. Project funds are available on a reimbursement basis only and may not be advanced under any circumstances.

  5. In contracts for grants authorized under this section, the department shall include provisions that require that capital improvements be held by the grantee for a specified period of time appropriate to the amount of the grant and that facilities be used for the express purpose of the grant. If the grantee is found to be out of compliance with provisions of the contract, the grantee shall repay to the state general fund the principal amount of the grant plus interest calculated at the rate of interest on state of Washington general obligation bonds issued most closely to the date of authorization of the grant.

  6. Projects funded in this section, including those that are owned and operated by nonprofit organizations, are generally required to pay state prevailing wages.

  7. The appropriation is provided solely for the following list of projects:

57th Ave Sewer Project (University Place)$200,000

ACT Historic Landmark Roof Restoration (Seattle)$539,000

ADA For Northwest Center Janitorial (Spokane

Valley)$19,000

Admiral Theatre Facility Improvements (Bremerton)$165,000

Affordable Housing Land Acquisition (Tacoma)$1,500,000

Afterschool Program Expansion (Walla Walla)$45,000

Airway Heights Public Safety (Airway Heights)$500,000

American Indian Community Center (Spokane)$500,000

American Legion Post 79 Roof Replacement

(Snoqualmie)$49,000

Anderson Island Multipurpose Building (Anderson

Island)$258,000

Ashley House (Spokane)$515,000

Asia Pacific Cultural Center (Tacoma)$1,000,000

ASUW Shell House (Seattle)$3,000,000

Athletic Field Lights For Ridgefield Outdoor

(Ridgefield)$250,000

Auburn Avenue Theater Rebuild (Auburn)$500,000

Avista Stadium Improvements (Spokane Valley)$543,000

B5 Community Learning Center (Kennewick)$750,000

Ball Field at Historic Petes (Enumclaw)$439,000

Ballard Boys & Girls Clubs Flooring Replacement

(Seattle)$49,000

Behavioral Health Wellbeing Clinic (Spokane)$1,571,000

Bonney Lake Senior Center Rehab Project (Bonney

Lake)$650,000

Boys & Girls Club Parking Lot Renovation (Federal

Way)$168,000

Boys & Girls Club Seismic Upgrade & Roof

Replacement (Vancouver)$412,000

Brewster Boys and Girls Club Facility (Brewster)$300,000

Building What Matters (Wenatchee)$400,000

Cannery Parking Lot & Sidewalk Rehab (Anacortes)$110,000

Capitol Land Trust Public Access Preconstruction

(Olympia)$77,000

Cathlamet Waterfront Park (Cathlamet)$86,000

Celebration Park Synthetic Turf Upgrade (Federal

Way)$822,000

Chehalis River Raw Water (Chehalis)$250,000

Children's Therapy Center (University Place)$500,000

City of Othello Lions Park (Othello)$600,000

City of Sequim Park Acquisition (Sequim)$375,000

Cloney Inclusive Playground (Longview)$1,000,000

Colfax Pool (Colfax)$706,000

Columbia Play Project Children's Museum

(Vancouver)$515,000

Commercial Pumpouts to Save Puget Sound

(Anacortes)$800,000

Community Homes Renovations (Woodinville)$67,000

Community Homes Renovations 41st LD (Bellevue)$106,000

Community Homes Renovations 48th LD (Bellevue)$243,000

Community Homes Upgrades 1st LD (Bothell)$104,000

Conconully Service Complex/Fire Hall (Conconully)$1,600,000

Cross Kirkland Corridor 132nd Avenue NE

Improvements (Kirkland)$515,000

Day Island Bridge Design Project (University

Place)$200,000

Des Moines Marina Steps (Des Moines)$1,000,000

Diking District 7 Fish Passage and Levee

(Stanwood)$750,000

Dishman Hills Conservancy Education Ctr Site

Planning (Spokane)$46,000

Double Culvert Replacement (Castle Rock)$500,000

East Hill North Community Park Phase 1 (Kent)$250,000

Eaton Urban Pathway Project (Battle Ground)$1,000,000

Ebey Waterfront Trail Phase 4 (Marysville)$1,030,000

Edmonds Boys & Girls Clubs Capital Project

(Edmonds)$1,385,000

Ejidos Community Farm (Everson)$824,000

Electron Way & Contra Costa Ave Intersection

Improvement (Fircrest)$153,000

Emergency Operation Generator (Coupeville)$350,000

Evans Creek Relocation Project (Redmond)$1,030,000

EWAM Handicap Parking Improvement Project

(Pomeroy)$98,000

Fair Building Improvements (Graham)$77,000

Ferry County Fairgrounds (Republic)$50,000

Fife Aquatic & Community Center Improvements$1,000,000

Fire Panel Replacement & Integration (Seattle)$294,000

Forest Park Pickleball Court Installation

(Everett)$345,000

Free Clinic & Central Construction Project (Walla

Walla)$500,000

Frontier Park Horse Cover (Graham)$1,388,000

Ft Steilacoom Park Nisqually Indian Tribe

Improvements (Lakewood)$309,000

Gibson Hall Improvement Project (Issaquah)$206,000

Gravelly Lake Commons at LASA (Lakewood)$460,000

Greenwood Early Learning Playground (Seattle)$69,000

Greg Cuoio Park Accessibility Improvements (Lacey)$515,000

Harbour Point Boulevard Pathway (Mukilteo)$258,000

Harlequin Theater Renovation (Olympia)$700,000

Heritage Center at Meeker Mansion (Puyallup)$496,000

Highland Park Improvement Club Rebuild (Seattle)$400,000

HUB Sports Fields (Liberty Lake)$1,030,000

In-Patient SUD Treatment & Sobering Center

(Bellingham)$412,000

Indian American Community Services Community

Center (Kent)$794,000

Interurban Trail War Memorials (Pacific)$10,000

Issaquah Senior Ctr Veterans Memorial Consolidated

Prk (Issaquah)$721,000

Japanese American Exclusion Memorial Vis Ctr

(Bainbridge Island)$350,000

Jarstad Aquatic Center Assessment & Roof Repair

(Bremerton)$309,000

Jenkins Creek Recreation Trail (Covington)$250,000

Kennewick Kiwanis Playground (Kennewick)$250,000

King County Sheriff's Office Air Support Unit

(Seattle)$1,000,000

King Street Station Creative Youth Empowerment Hub

(Seattle)$500,000

Kirkland Boys & Girls Clubs Community Playfield

(Kirkland)$150,000

Kirkland Performance Center Safety Improvements$1,288,000

Kitsap Humane Society Veterinary Lifesaving Center

(Silverdale)$412,000

Lacamas Lake Water Improvements (Camas)$500,000

Lake Boren CrossTown Recreational Trail

(Newcastle)$824,000

Lake Stevens Community Food Bank (Lake Stevens)$450,000

Lambert House Flood Abatement & Foundation

Replacement (Seattle)$1,030,000

Latah Water System Rehabilitation Project (Latah)$180,000

Lenny Wilkens and Sue Bird Statues (Seattle)$412,000

Lester Creek Personnel to Water Intake (Pe Ell)$640,000

Lewis County Senior Centers (Chehalis)$500,000

Lincoln County Fair and Livestock (Davenport)$1,000,000

Local Grain Conveyance & Storage System (Tumwater)$255,000

Logistics Facility (Vancouver)$874,000

Lyon Creek Culvert at SR 104 (Lake Forest Park)$1,820,000

Madison Street School Sidewalk Project (South

Bend)$175,000

Marine Spills Operations Base (Friday Harbor)$210,000

Marshall Park Inclusive Community Playground

(Vancouver)$200,000

Mason PUD Water Infrastructure (Matlock)$1,000,000

Mays Pond Playground (Bothell)$650,000

Medical Lake Storm Water Mitigation (Medical Lake)$1,000,000

Medically-Tailored Meals & Groceries Expansion

(Seattle)$275,000

Memorial Stadium (Seattle)$4,000,000

Meydenbauer Center Clean Buildings Energy

Improvements (Bellevue)$500,000

MLK Jr. Park & Swimming Pool (Yakima)$1,160,000

Monroe Therapeutic Facility (Monroe)$1,100,000

Mt. Spokane Ski & Snowboard Park (Mead)$100,000

Mukilteo First Responder Wellness Center

(Mukilteo)$258,000

National Nordic Museum East Garden Capital Project

(Seattle)$258,000

Nespelem Community Longhouse (Nespelem)$1,850,000

New Tomorrow's Hope Child Development Center

(Everett)$725,000

No. County Rec. Association Youth Sports (Castle

Rock)$256,000

Nooksack Community Housing (Deming)$370,000

North Seattle Boys & Girls Clubs Flooring

Replacement (Seattle)$134,000

NW Stream Center Sustainable Infrastructure

(Everett)$273,000

Old Fort Lake Subarea Remediation & Public Access

Proj (DuPont)$215,000

Othello's Regional Water Plan (Othello)$400,000

Outdoor Fields LED Retrofit and Solar (Tukwila)$500,000

Pasco Boulevard Soccer Field (Pasco)$750,000

Pasco Clubhouse Safety Modernization (Pasco)$840,000

Peninsula Medical Respite & Housing Center

(Bremerton)$1,000,000

Peninsula Senior Activity (Ocean Park)$264,000

PenMet Parks Community Recreation Center (Gig

Harbor)$1,030,000

Pike Place Market Elevator & Stair Replacement

(Seattle)$515,000

Pond to Pines Infrastructure (Ellensburg)$518,000

Port of Vancouver Dock Demo and Removal of

Creosote (Vancouver)$3,500,000

Port Orchard Breakwater Replacement (Port Orchard)$800,000

Port Remediation (Olympia)$2,200,000

Portland Avenue Park Sprayground (Tacoma)$500,000

Poulsbo Historical Society - Nilsen-Sonju House$300,000

Prosser City Entrance Sign (Prosser)$110,000

Public Works Facility & Vehicle Storage (Sedro

Woolley)$500,000

Puyallup Elks Roof Replacement (Puyallup)$359,000

RAI Maker Space & Cultural Center (Seattle)$802,000

Redondo Fishing Pier Replacement Phase 1 (Des

Moines)$1,000,000

Refugee Welcoming & Healing Center (SeaTac)$515,000

Regional Water & Sewer Upgrades (Rochester)$250,000

Rejuvenation Community Day Center (Bremerton)$200,000

Remembrance Gallery (Puyallup)$250,000

Renton Public Square (Renton)$1,485,000

Replacement Hospital Infrastructure (Moses Lake)$1,482,000

Reservoir Capacity & Seismic (Battle Ground)$1,250,000

Ritzville Legion Hall Renovation (Ritzville)$165,000

Ritzville Rodeo Bleachers Replacement (Ritzville)$194,000

Ritzville Theater (Ritzville)$75,000

Rock Creek Horse Park (Ravensdale)$206,000

Rotary Boys & Girls Clubs HVAC Replacement

(Seattle)$309,000

Rotary Morrow Community Park (Poulsbo)$100,000

Roy Water Preliminary Design (Roy)$250,000

Scriber Place Housing for Homeless Students

(Lynnwood)$2,050,000

Search & Rescue Headquarters Feasibility Study

(Snoqualmie)$103,000

Seattle Aquarium (Seattle)$3,000,000

Seattle Public Library Holds Pick-Up Locker

(Seattle)$93,000

Security & Access Improvements (Shelton)$250,000

Sewer Pump Station 12 & Force Main (Bellevue)$1,030,000

Shelton Day Care & Building Project (Shelton)$215,000

Skagit County Voluntary Stewardship (Skagit)$1,000,000

Skagit PUD 10th District Waterlines (Skagit)$650,000

Skagit PUD 39th District Waterline Relocations

(Mt. Vernon)$600,000

Skagit PUD Headquarters Public Meeting Room (Mt.

Vernon)$206,000

Snohomish Public Safety & City Services Campus

(Snohomish)$700,000

South Hill Park and Sports (Woodland)$250,000

Southwest Boys & Girls Clubs Safety & Security

Improve (Seattle)$3,000

Spokane International Airport (Spokane)$500,000

Spokane Scale House Market (Spokane Valley)$750,000

Spring Box Replacement/Water (Concrete)$450,000

St. Mary Medical Center (Walla Walla)$75,000

Storm Upgrades Downtown Phase N2 (Puyallup)$696,000

Sultan Basin Park (Sultan)$500,000

Sumas Ave Water Pipe Replacement (Sumas)$150,000

SVYAC Barn Construction Phase 2B (North Bend)$232,000

SW WA Agricultural Business (Tenino)$250,000

Swede Hall Renovation Project (Rochester)$198,000

Take-A-Break Park Playground (Maple Valley)$412,000

Taproot Theatre Jewell Mainstage Renovation

(Seattle)$515,000

Tasveer Art Center (Bellevue)$258,000

Township Hall North & West (Spokane)$100,000

Tribal Cultural Center & Museum Restoration

(Steilacoom)$200,000

Tubman Center for Health & Freedom (Seattle)$1,690,000

Tugboat Parthia Pavilion Construction (Olympia)$148,000

Tukwila Community Center HVAC Replacement (Tukwila)$515,000

Ultrafine Particle Monitoring (SeaTac)$340,000

Van Zandt Community Hall Renovation (Deming)$502,000

Veterans Memorial Balfour Park (Spokane Valley)$207,000

VFW Post 2224 Critical Renovations (Puyallup)$200,000

Village Theatre's Francis J Gaudette HVAC

Replacement (Issaquah)$489,000

VOA Crosswalk 2.0 (Spokane)$1,000,000

Washougal Civic Campus Project (Washougal)$2,000,000

Washtucna Town Hall (Washtucna)$20,000

Wastewater Treatment Facility & Loss Project

(Carbonado)$500,000

Wastewater Treatment System Upgrades (Long Beach)$330,000

Waterfront Organic Soil Removal (Washougal)$2,000,000

What-Comm Dispatch Center (Bellingham)$100,000

Whatcom Ag Research Station (Lynden)$464,000

White Bluffs Rail/Rail Replacement (Richland)$1,250,000

White Center Community Hub (Seattle)$275,000

White Center Food Bank Renovation (Seattle)$275,000

Wilkeson Infrastructure (Wilkeson)$500,000

Yakima County Meals on Wheels (Union Gap)$1,000,000

Yakima Trolley Museum (Yakima)$25,000

YMCA Early Learning Center (Port Angeles)$1,625,000

Youth Assist Program Skills Training Center

(Tacoma)$500,000

Youth Emergency Shelter (Longview)$250,000

Section 1024

FOR THE DEPARTMENT OF COMMERCE

The appropriation in this section is subject to the following conditions and limitations:

  1. $38,250,000 of the appropriation in this section is provided solely for grants to provide tribal assistance to mitigate and adapt to the effects of climate change, including, but not limited to, supporting relocation for Indian tribes located in areas of heightened risk due to anticipated sea level rise, flooding, or other disturbances caused by climate change. In developing the grant program, the department must collaborate with tribes to determine program parameters for award amounts, distribution, and benchmarks for success. In order to meet the requirements of RCW 70A.65.230(1)(b), tribal applicants are encouraged to include a tribal resolution supporting their request with their application.

  2. $11,750,000 of the appropriation in this section is provided solely for the Quinault Indian Nation's relocation of the Taholah and Queets Villages.

Section 1025

FOR THE DEPARTMENT OF COMMERCE

The appropriation in this section is subject to the following conditions and limitations:

  1. $1,000,0000 of the state taxable building construction account—appropriation in this section is provided solely for the department to contract with the communities of concern commission for development of a list of community-led capital projects that serve underserved communities. Eligible expenses include costs incurred by the communities of concern commission in conducting outreach, developing an application process, providing technical assistance, assisting project proponents with project readiness, and assisting the department with identifying barriers faced in accessing capital grant programs. The communities of concern commission must provide a report to the house capital budget committee and the senate ways and means committee that describes the transparency of their process to develop the list and how the $1,000,000 was spent by December 1, 2023. The department may submit a list of identified projects prepared by the communities of concern commission to the governor and fiscal committees of the legislature for consideration for funding in the 2024 supplemental capital budget.

  2. $5,000,000 of the state taxable building construction account—state appropriation in this section must remain in unallotted status for possible appropriation for projects submitted for consideration for the 2024 supplemental capital budget. The legislature retains the right to review and consider all such funding as it does with other requests for project funding.

  3. $5,000,000 of the state taxable building construction account—state appropriation in this section is provided solely for the following list of projects:

Cora Whitley Family Center (Tacoma)$2,000,000

Latino Community Service Center (Lynnwood)$500,000

Rainier Court Phase V (Seattle)$750,000

Raze Development Capital Project (Spokane)$500,000

Tubman Center for Health and Freedom (Seattle)$1,250,000

Section 1026

FOR THE DEPARTMENT OF COMMERCE

The appropriation in this section is subject to the following conditions and limitations: The appropriation in this section is provided solely for state match for the Pacific Northwest hydrogen association application, supported by the department, for a United States department of energy hydrogen hub grant.

Section 1027

FOR THE DEPARTMENT OF COMMERCE

Section 1028

FOR THE DEPARTMENT OF COMMERCE

The appropriations in this section are subject to the following conditions and limitations: The appropriations in this section are provided solely for the housing finance commission land acquisition program to help developers purchase land for affordable rental or homeownership housing developments. The department must work with the housing finance commission and provide the governor and legislature with a progress report by November 1, 2024. The report must include:

  1. The total number of applications and amount of funding requested; and

  2. A list and description of the projects approved for funding, including project location.

Section 1029

FOR THE DEPARTMENT OF COMMERCE

The appropriation in this section is subject to the following conditions and limitations: The appropriation in this section is provided solely for the following list of projects:

City of Lakewood, McChord North Clear Zone

(Lakewood)$900,000

Compatible Lands Foundation, Fairchild REPI

Easement Acquisition$2,500,000

Lakewood Water District, Water Well (K-3, G-4)

(Lakewood)$3,720,000

Quincy Square Civic Improvements (Bremerton)$1,750,000

Whidbey Camano Land Trust, Keystone Preserve

(Greenbank)$1,300,000

Section 1030

FOR THE DEPARTMENT OF COMMERCE

The appropriation in this section is subject to the following conditions and limitations: The appropriation in this section is provided solely for the rising strong project to construct no fewer than 24 units of supportive transitional housing.

Section 1031

FOR THE DEPARTMENT OF COMMERCE

2023-25 Port Electrification (92001363)

The appropriation in this section is subject to the following conditions and limitations:

  1. To be eligible to receive state funds under this section, a port must first adopt a policy that requires vessels that dock at the port facility to use any shore power if such vessel is capable of using such power and when such power is available at the port facility.

  2. The appropriation in this section is provided solely for the following list of projects:

Port Electrification Competitive Grants$21,000,000

Port of Everett$5,000,000

Northwest Seaport Alliance (Seattle)$14,000,000

Section 1032

FOR THE DEPARTMENT OF COMMERCE

Public Facility Improvement Fund (92001367)

The appropriation in this section is subject to the following conditions and limitations:

  1. The appropriation in this section is provided solely for infrastructure improvements at the publicly owned facilities listed in subsection (2) of this section and must be combined with local funds. For projects that are required to meet major league baseball professional development league facility standards, state funds may only be used to fund renovations necessary to meet those standards.

  2. The appropriation is provided solely for the following list of projects:

City of Bellingham Joe Martin Stadium$700,000

City of Everett$7,400,000

City of Pasco Gesa Stadium$3,000,000

City of Port Angeles Civic Field$600,000

City of Ridgefield, Ridgefield Outdoor

Recreational Complex$450,000

City of Tacoma Cheney Stadium$3,000,000

City of Walla Walla Borleske Stadium$525,000

Lower Columbia College David Story Field

(Longview)$1,300,000

Spokane County Avista Stadium$5,800,000

Wenatchee Valley College Paul Thomas Sr. Field

(Wenatchee)$700,000

Yakima County Yakima County Stadium$525,000

Section 1033

FOR THE DEPARTMENT OF COMMERCE

2023-25 Dental Capacity Grants (92001393)

The appropriation in this section is subject to the following conditions and limitations: The appropriation in this section is provided solely for the following list of projects:

HealthPoint (Seattle)$490,000

Lake Roosevelt Community Health Center (Inchelium)$160,000

Lake Roosevelt Community Health Center (Keller)$80,000

Peninsula Community Health Services (Bremerton)$495,000

Seattle Indian Health Board (Seattle)$305,000

Section 1034

FOR THE DEPARTMENT OF COMMERCE

Dental Community Partnerships (92001399)

The appropriation in this section is subject to the following conditions and limitations: The appropriation in this section is provided solely for the following list of projects:

PNWU Dental School (Yakima)$5,000,000

Sea Mar Community Health Center (Tacoma)$3,500,000

Yakima Valley Farm Workers Clinic (Kennewick)$4,000,000

Section 1035

FOR THE DEPARTMENT OF COMMERCE

2023-25 Landlord Mitigation Account (92001419)

The appropriation in this section is subject to the following conditions and limitations: $5,000,000 of the state building construction account—state appropriation is provided solely for deposit in the landlord mitigation program account.

Section 1036

FOR THE OFFICE OF FINANCIAL MANAGEMENT

The appropriation in this section is subject to the following conditions and limitations:

  1. Emergency repair funding is provided solely to address unexpected building or grounds failures that will impact public health and safety and the day-to-day operations of the facility. To be eligible for funds from the emergency repair pool, a request letter for emergency funding signed by the affected agency director must be submitted to the office of financial management and the appropriate legislative fiscal committees. The request must include a statement describing the health and safety hazard and impacts to facility operations, the possible cause, the proposed scope of emergency repair work and related cost estimate, and identification of other funding that may be applied to the project.

  2. For emergencies occurring during a legislative session, an agency must notify the legislative fiscal committees before requesting emergency funds from the office of financial management.

  3. The office of financial management must notify the legislative evaluation and accountability program committee and the legislative fiscal committees as emergency projects are approved for funding and include what funded level was approved.

Section 1037

FOR THE DEPARTMENT OF ENTERPRISE SERVICES

The reappropriations in this section are subject to the following conditions and limitations: The reappropriations are subject to the provisions of section 1075, chapter 413, Laws of 2019.

Section 1038

FOR THE DEPARTMENT OF ENTERPRISE SERVICES

The appropriations in this section are subject to the following conditions and limitations:

  1. The reappropriations are subject to the provisions of section 6023, chapter 332, Laws of 2021.

  2. The appropriations in this section are provided solely for the following list of projects:

Campus - Duress System Replacement$120,000

Campus - Redundant Fiber Optic Pathway$376,000

Mansion - Enhancements & Security Improvements -

Guard Posts$1,660,000

Mansion - Exec Residence Enhancements - Fencing,

Gates, Bollards$510,000

Mansion - Exec Residence Enhancements - Video

Surveillance and Ext$1,000,000

Section 1039

FOR THE DEPARTMENT OF ENTERPRISE SERVICES

The appropriations in this section are subject to the following conditions and limitations:

  1. The reappropriation is subject to the provisions of section 1110, chapter 332, Laws of 2021.

  2. The appropriation in this section is provided solely for the following list of projects:

Campus - Physical Access Control (Re-Key Locksets)$200,000

Capitol Campus Access Controls - Exterior Doors$1,000,000

Section 1040

FOR THE DEPARTMENT OF ENTERPRISE SERVICES

The appropriation in this section is subject to the following conditions and limitations:

  1. The appropriation in this section is provided solely for architectural and engineering services to manage public works contracting for all state facilities pursuant to RCW 43.19.450.

  2. At the end of each fiscal biennium, the department must report to the office of financial management and the appropriate committees of the legislature on performance, including the following:

    1. The number of projects managed by each project manager by fiscal year;

    2. The number of project predesigns completed on time, reported by project and fiscal year;

    3. The number of project designs completed, reported by project and fiscal year;

    4. The number of project constructions completed on time, reported by project and fiscal year and in total;

    5. Projects that were not completed on schedule, how many days they were delayed, and the reasons for the delays;

    6. The number and cost of the change orders and the reason for each change order; and

    7. A list of the interagency agreements executed with state agencies during the 2023-2025 fiscal biennium to provide staff support to state agencies that is over and above the allocation provided in this section. The list must include the agency, the amount of dollars by fiscal year, and the rationale for the additional service.

Section 1041

FOR THE DEPARTMENT OF ENTERPRISE SERVICES

Section 1042

FOR THE DEPARTMENT OF ENTERPRISE SERVICES

Section 1043

FOR THE DEPARTMENT OF ENTERPRISE SERVICES

Section 1044

FOR THE DEPARTMENT OF ENTERPRISE SERVICES

Section 1045

FOR THE DEPARTMENT OF ENTERPRISE SERVICES

Section 1046

FOR THE DEPARTMENT OF ENTERPRISE SERVICES

Section 1047

FOR THE DEPARTMENT OF ENTERPRISE SERVICES

The appropriation in this section is subject to the following conditions and limitations:

  1. $1,000,000 of the state building construction account—state appropriation is provided solely for replacement of the roof.

  2. $100,000 of the model toxics control capital account—state appropriation is provided solely for asbestos abatement.

Section 1048

FOR THE DEPARTMENT OF ENTERPRISE SERVICES

Section 1049

FOR THE DEPARTMENT OF ENTERPRISE SERVICES

The appropriation in this section is subject to the following conditions and limitations:

  1. The appropriation in this section is provided solely for design and the beginning of construction for the restoration of the legislative skylight systems located above the chambers of the house of representatives and the senate, to include work on each bronze ceiling laylight, skylight attic, roof and skylight system, and chamber acoustics.

  2. The legislature intends to provide funds in the amount of $7,271,000 over the course of the 2023-2025, 2025-2027, and 2027-2029 fiscal biennia for construction of the legislative skylight system with completion in time for the legislative building's centennial in 2028. Pursuant to RCW 43.88.130, the department is authorized to enter into a multibiennium contract for the construction of the skylight system. Nothing in this section authorizes the agency to make an expenditure without an appropriation.

  3. The legislature finds that the skylight system is an invaluable architectural treasure that should be preserved and maintained in line with its original design. The legislature further finds that the skylight system both literally and symbolically contributes to more open and transparent legislative proceedings. Therefore, with this funding, the legislature intends to restore each chamber to its original amber-tinted glow and reveal to the public the beautiful design and superb craftsmanship of the skylight systems of the state legislative building.

Section 1050

FOR THE DEPARTMENT OF ENTERPRISE SERVICES

Section 1051

FOR THE DEPARTMENT OF ENTERPRISE SERVICES

Section 1052

FOR THE DEPARTMENT OF ENTERPRISE SERVICES

The appropriations in this section are subject to the following conditions and limitations:

  1. The reappropriations are subject to the provisions of section 1059, chapter 296, Laws of 2022.

  2. The department must consult with the senate facilities and operations committee or its designees and the house of representatives' executive rules committee or its designees at least every other month.

  3. All appropriations must be coded and tracked as separate discrete subprojects in the agency financial reporting system.

  4. If the department receives information that projected costs for any of the subprojects in subsections (5), (6), (7), or (8) of this section will exceed the amount provided in the respective subsections, including projected costs in future biennia, the department must timely notify and provide that information in writing to the project executive team. Prior to proceeding with design or construction, the department must:

    1. Provide at least three options to reduce the subproject costs to stay within the amount provided for that subproject and the project schedule;

    2. Consult with the project executive team on the options offered, prior to proceeding with a reduced cost option; and

    3. Receive majority consensus from the project executive team to either adopt and move forward with reduced cost options that bring the subproject costs within amounts appropriated or adopt a tentative modified budget for the subproject. If a tentative modified budget is adopted, the department must seek additional funding in the next agency budget submittal.

  5. $83,837,000 of the amount provided in this section is provided solely for the Irv Newhouse building replacement design and construction subproject on opportunity site six west. The department must:

    1. Start Newhouse building construction by July 1, 2023;

    2. Complete Newhouse building construction by October 31, 2024; and

    3. Consult with the leadership of the senate, or their designees, at least every month, beginning July 1, 2023.

  6. $66,373,000 of the amount provided in this section is provided solely for the Pritchard building rehabilitation, design, and construction subproject. The department must:

    1. Start design by July 1, 2023;

    2. Start construction by December 31, 2024; and

    3. Stabilize the hillside adjacent to the Pritchard building as part of this subproject.

  7. $6,861,000 of the amount provided in this section is provided solely for the partial renovation of the John L. O'Brien building on floors 3 and 4. The department must:

    1. Start design by July 1, 2023; and

    2. Start construction by April 1, 2024.

  8. $16,450,000 of the amount provided in this section is provided solely for the legislative campus modernization global subproject that includes, but is not limited to, the visitor lot (opportunity site six east), Columbia street site work, the legislative modular building, and Water street site work.

  9. The legislature intends to provide funds in the amount of $110,864,000 over the course of the 2023-2025 and the 2025-2027 fiscal biennia for rehabilitation and construction of the Pritchard building subproject. Pursuant to RCW 43.88.130, the department is authorized to enter into a multibiennium contract for the rehabilitation and construction of the Pritchard building subproject. Nothing in this section authorizes the agency to make an expenditure without an appropriation.

Section 1053

FOR THE DEPARTMENT OF ENTERPRISE SERVICES

Section 1054

FOR THE DEPARTMENT OF ENTERPRISE SERVICES

The appropriation in this section is subject to the following conditions and limitations:

  1. The appropriation in this section is provided solely for the state building code council to study and report the cost and benefits for public and private construction projects of transitioning to a six-year building code cycle.

  2. By October 1, 2023, the state building code council must contract with an independent consulting firm selected by the majority vote of an 11-member selection committee.

    1. The selection committee must include nine representatives who do not currently serve on the state building code council, from each from the largest Washington trade associations representing:

      1. Commercial construction;

      2. Residential construction;

      3. Building trades;

      4. Architects;

    2. Engineers;

    1. Manufacturers of building materials;

    2. Realtors;

    3. Cities; and

     ix. Counties.
    
    1. The chair and vice chair of the state building code council shall serve on the selection committee as cochairs.
  3. The selected independent consulting company must provide a report to the appropriate committees of the legislature by July 1, 2024. At a minimum, the report must include:

    1. An analysis of potential cost savings to the state's omnibus operating, transportation, and capital budgets achievable through the transition to a six-year building code cycle.

    2. An analysis of the upfront, lifecycle, and energy costs of building code updates for each three-year building code cycle dating back to 2006.

    3. Potential cost savings to private single-family and multifamily residential projects.

    4. An analysis of SBCC staffing needs utilizing a three-year code cycle versus a six-year code cycle and provide recommendations for dealing with staffing level increases or decreases.

    5. Recommendations to transition to a six-year code cycle, including, but not limited to, the state building code council's ability to initiate rulemaking activities.

    6. An analysis of cost savings that would be realized by stakeholders from moving from a three-year code cycle to a six-year code cycle, including costs of training stakeholder employees.

Section 1055

FOR THE MILITARY DEPARTMENT

Section 1056

FOR THE MILITARY DEPARTMENT

The appropriations in this section are subject to the following conditions and limitations: The reappropriation is subject to the provisions of section 1093, chapter 413, Laws of 2019.

Section 1057

FOR THE MILITARY DEPARTMENT

Section 1058

FOR THE MILITARY DEPARTMENT

Section 1059

FOR THE MILITARY DEPARTMENT

Section 1060

FOR THE MILITARY DEPARTMENT

Section 1061

FOR THE MILITARY DEPARTMENT

Section 1062

FOR THE MILITARY DEPARTMENT

Section 1063

FOR THE MILITARY DEPARTMENT

Section 1064

FOR THE MILITARY DEPARTMENT

Section 1065

FOR THE MILITARY DEPARTMENT

Section 1066

FOR THE MILITARY DEPARTMENT

Section 1067

FOR THE MILITARY DEPARTMENT

Section 1068

FOR THE MILITARY DEPARTMENT

Section 1069

FOR THE MILITARY DEPARTMENT

Section 1070

FOR THE MILITARY DEPARTMENT

Section 1071

FOR THE MILITARY DEPARTMENT

Section 1072

FOR THE MILITARY DEPARTMENT

Section 1073

FOR THE MILITARY DEPARTMENT

Section 1074

FOR THE DEPARTMENT OF ARCHAEOLOGY AND HISTORIC PRESERVATION

The appropriation in this section is subject to the following conditions and limitations: The appropriation is provided solely for the following list of projects:

Douglas County Courthouse$400,000

Grant County Courthouse$250,000

Grays Harbor County Courthouse$225,000

Klickitat County Courthouse$585,000

Lewis County Courthouse$120,000

Okanogan County Courthouse$670,000

San Juan County Courthouse$1,000,000

Snohomish County Courthouse$600,000

Stevens County Courthouse$97,000

Yakima County Courthouse$815,000

Section 1075

FOR THE DEPARTMENT OF ARCHAEOLOGY AND HISTORIC PRESERVATION

Section 1076

FOR THE DEPARTMENT OF ARCHAEOLOGY AND HISTORIC PRESERVATION

The appropriation in this section is subject to the following conditions and limitations: The appropriation provided in this section is intended to fund activities that preserve the historic character of theaters and not maintenance and upkeep.

Section 1077

FOR THE DEPARTMENT OF ARCHAEOLOGY AND HISTORIC PRESERVATION

Section 2001

FOR THE CRIMINAL JUSTICE TRAINING COMMISSION

Section 2002

FOR THE CRIMINAL JUSTICE TRAINING COMMISSION

The appropriation in this section is subject to the following conditions and limitations: The appropriation in this section is provided solely to fund a predesign for renovation of the Burien campus.

  1. The commission must work with the department of enterprise services to complete a predesign no later than June 30, 2024, that:

    1. Assesses the current condition of each building on campus, including an evaluation of major mechanical systems, building envelope, roofing, and energy upgrades.

    2. Assesses the viability of renovating each building on campus to meet the training needs of the commission and recommends whether each building should be renovated, demolished, or rebuilt.

    3. Recommends the placement and construction of any new buildings or structures on campus, which may include repurposing of the track, to meet the demands of the commission.

    4. Prioritizes each of the recommendations in subsections (b) and (c) of this section including a justification, estimated time of construction, and cost for each.

    5. Recommends a phased construction schedule over the next two or three biennia with a target total budget of $100,000,000.

    6. Recommends mechanisms that will enable the commission to maintain training capacity during the course of construction. In addition to phased construction, recommendations may include the use of temporary modular buildings on the Burien campus or the use of leased space.

  2. As part of the predesign process, the commission shall address the extent to which regional training centers will be used as a long-term delivery mechanism to deliver trainings around the state. The commission must include information regarding the current or proposed training location; facilities available or proposed to be provided at the regional location; type and target number of classes and students; and the cost or anticipated cost of the facilities.

Section 2003

FOR THE CRIMINAL JUSTICE TRAINING COMMISSION

The appropriation in this section is subject to the following conditions and limitations: The appropriation in this section is provided solely for the following list of projects:

NW Regional Training Academy - Firing Range$360,000

Spokane Academy Expansion$1,400,000

SW Regional Training Academy$1,000,000

Section 2004

FOR THE DEPARTMENT OF LABOR AND INDUSTRIES

Section 2005

FOR THE DEPARTMENT OF SOCIAL AND HEALTH SERVICES

Section 2006

FOR THE DEPARTMENT OF SOCIAL AND HEALTH SERVICES

Section 2007

FOR THE DEPARTMENT OF SOCIAL AND HEALTH SERVICES

Section 2008

FOR THE DEPARTMENT OF SOCIAL AND HEALTH SERVICES

Section 2009

FOR THE DEPARTMENT OF SOCIAL AND HEALTH SERVICES

Section 2010

FOR THE DEPARTMENT OF SOCIAL AND HEALTH SERVICES

Section 2011

FOR THE DEPARTMENT OF SOCIAL AND HEALTH SERVICES

Section 2012

FOR THE DEPARTMENT OF SOCIAL AND HEALTH SERVICES

Section 2013

FOR THE DEPARTMENT OF SOCIAL AND HEALTH SERVICES

Section 2014

FOR THE DEPARTMENT OF SOCIAL AND HEALTH SERVICES

Section 2015

FOR THE DEPARTMENT OF SOCIAL AND HEALTH SERVICES

Section 2016

FOR THE DEPARTMENT OF SOCIAL AND HEALTH SERVICES

Section 2017

FOR THE DEPARTMENT OF SOCIAL AND HEALTH SERVICES

Section 2018

FOR THE DEPARTMENT OF SOCIAL AND HEALTH SERVICES

Section 2019

FOR THE DEPARTMENT OF SOCIAL AND HEALTH SERVICES

Section 2020

FOR THE DEPARTMENT OF SOCIAL AND HEALTH SERVICES

Section 2021

FOR THE DEPARTMENT OF SOCIAL AND HEALTH SERVICES

Section 2022

FOR THE DEPARTMENT OF SOCIAL AND HEALTH SERVICES

Section 2023

FOR THE DEPARTMENT OF SOCIAL AND HEALTH SERVICES

Section 2024

FOR THE DEPARTMENT OF SOCIAL AND HEALTH SERVICES

The appropriation in this section is subject to the following conditions and limitations: As part of its assessment, the department must conduct a long-term cost-benefit analysis of transitioning the water system to the City of Lakewood and any cost mitigation strategies available to the state.

Section 2025

FOR THE DEPARTMENT OF SOCIAL AND HEALTH SERVICES

Section 2026

FOR THE DEPARTMENT OF SOCIAL AND HEALTH SERVICES

The appropriations in this section are subject to the following

conditions and limitations: $500,000 of the state building construction account—state appropriation is provided solely for a planning study to develop options for behavioral health diversion and treatment facilities for individuals with mental illnesses involved in or at risk of becoming involved in the criminal justice system.

Section 2027

FOR THE DEPARTMENT OF SOCIAL AND HEALTH SERVICES

The appropriations in this section are subject to the following conditions and limitations:

  1. The reappropriation is subject to the provisions of section 2037, chapter 332, Laws of 2021.

  2. The legislature intends to provide funds in the amount of $895,000,000 over the course of the 2023-2025 and 2025-2027 biennia for construction of the new forensic hospital on the Western State behavioral health campus. Pursuant to RCW 43.88.130, the department is authorized to enter into a multibiennium contract for the construction of the hospital. Nothing in this section authorizes the agency to make an expenditure without an appropriation.

Section 2028

FOR THE DEPARTMENT OF SOCIAL AND HEALTH SERVICES

The reappropriation in this section is subject to the following conditions and limitations: The reappropriation is subject to the provisions of section 2054, chapter 413, Laws of 2019.

Section 2029

FOR THE DEPARTMENT OF SOCIAL AND HEALTH SERVICES

Section 2030

FOR THE DEPARTMENT OF HEALTH

Section 2031

FOR THE DEPARTMENT OF HEALTH

Section 2032

FOR THE DEPARTMENT OF HEALTH

Section 2033

FOR THE DEPARTMENT OF HEALTH

Section 2034

FOR THE DEPARTMENT OF HEALTH

Section 2035

FOR THE DEPARTMENT OF HEALTH

The appropriation in this section is subject to the following conditions and limitations: $2,000,000 of the state building construction account—state appropriation is provided solely for the department to facilitate a water supply agreement between the City of North Bend and the Sallal Water System. Funds must be distributed equally between the two parties and funding is conditional on a signed water supply agreement that ensures a minimum of 100 acre feet per year of permanent mitigation water supply for the city.

Section 2036

FOR THE DEPARTMENT OF HEALTH

The appropriation in this section is subject to the following conditions and limitations:

  1. For projects involving repair, replacement, or improvement of a clean water infrastructure facility or other public works facility for which an investment grade efficiency audit is reasonably obtainable, the department shall require as a contract condition that the project sponsor undertake an investment grade efficiency audit. The project sponsor may finance the costs of the audit as part of its drinking water state revolving fund program loan.

  2. The department must encourage local government use of federally funded drinking water infrastructure programs operated by the United States department of agriculture rural development agency.

Section 2037

FOR THE DEPARTMENT OF HEALTH

The appropriation in this section is subject to the following conditions and limitations:

  1. For projects involving repair, replacement, or improvement of a clean water infrastructure facility or other public works facility for which an investment grade efficiency audit is reasonably obtainable, the department must require as a contract condition that the project sponsor undertake an investment grade efficiency audit. The project sponsor may finance the costs of the audit as part of its drinking water state revolving fund program loan.

  2. The department must encourage local government use of federally funded drinking water infrastructure programs operated by the United States department of agriculture rural development agency.

Section 2038

FOR THE DEPARTMENT OF HEALTH

The appropriation in this section is subject to the following conditions and limitations: The appropriation in this section is provided solely for the department to develop and conduct a grant program to improve health outcomes for overburdened communities highly impacted by air pollution. In developing the grant program, the department shall focus on mechanisms to improve health disparities for persons living in overburdened communities. The department must work with the environmental justice council to identify grant criteria that targets appropriate communities, provides measurable beneficial health outcomes, and monitors outcomes for identification of strategies for future investment. The department may use no more than 3 percent of the appropriation for administrative expenses.

Section 2039

FOR THE DEPARTMENT OF VETERANS AFFAIRS

Section 2040

FOR THE DEPARTMENT OF VETERANS AFFAIRS

Section 2041

FOR THE DEPARTMENT OF VETERANS AFFAIRS

Section 2042

FOR THE DEPARTMENT OF VETERANS AFFAIRS

Section 2043

FOR THE DEPARTMENT OF VETERANS AFFAIRS

Section 2044

FOR THE DEPARTMENT OF VETERANS AFFAIRS

Section 2045

FOR THE DEPARTMENT OF VETERANS AFFAIRS

Section 2046

FOR THE DEPARTMENT OF VETERANS AFFAIRS

The appropriations in this section are subject to the following conditions and limitations: The appropriations are provided solely for the WVH HVAC Retrofit Project (40000006) in the nursing facility at the Washington veterans' home. The department anticipates the receipt of federal competitive grant funding from the American rescue plan act. Any amount of state funds that exceed the level of funding needed due to the receipt of federal funding must be placed in unallotted status.

Section 2047

FOR THE DEPARTMENT OF VETERANS AFFAIRS

Section 2048

FOR THE DEPARTMENT OF CHILDREN, YOUTH, AND FAMILIES

Section 2049

FOR THE DEPARTMENT OF CHILDREN, YOUTH, AND FAMILIES

The appropriation in this section is subject to the following conditions and limitations: The department must assess the environmental considerations of installing an above ground storage tank versus an underground storage tank, with preference given to an above ground storage tank.

Section 2050

FOR THE DEPARTMENT OF CHILDREN, YOUTH, AND FAMILIES

Section 2051

FOR THE DEPARTMENT OF CHILDREN, YOUTH, AND FAMILIES

Section 2052

FOR THE DEPARTMENT OF CORRECTIONS

The appropriations in this section are subject to the following conditions and limitations: $600,000 of the model toxics control capital account—state appropriation is provided for the lead abatement activities associated with this project.

Section 2053

FOR THE DEPARTMENT OF CORRECTIONS

Section 2054

FOR THE DEPARTMENT OF CORRECTIONS

Section 2055

FOR THE DEPARTMENT OF CORRECTIONS

Section 2056

FOR THE DEPARTMENT OF CORRECTIONS

Section 2057

FOR THE DEPARTMENT OF CORRECTIONS

The appropriations in this section are subject to the following conditions and limitations: The reappropriation is subject to the provisions of section 2026, chapter 356, Laws of 2020.

Section 2058

FOR THE DEPARTMENT OF CORRECTIONS

Section 2059

FOR THE DEPARTMENT OF CORRECTIONS

Section 2060

FOR THE DEPARTMENT OF CORRECTIONS

Section 2061

FOR THE DEPARTMENT OF CORRECTIONS

Section 2062

FOR THE DEPARTMENT OF CORRECTIONS

Section 2063

FOR THE DEPARTMENT OF CORRECTIONS

Section 2064

FOR THE DEPARTMENT OF CORRECTIONS

Section 2065

FOR THE DEPARTMENT OF CORRECTIONS

Section 3001

FOR THE DEPARTMENT OF ECOLOGY

Section 3002

FOR THE DEPARTMENT OF ECOLOGY

Section 3003

FOR THE DEPARTMENT OF ECOLOGY

The appropriation in this section is subject to the following conditions and limitations:

  1. $30,448,000 of the appropriation in this section is provided solely for board-approved projects to protect and restore aquatic species habitat, including: Construction and property acquisition; preconstruction and acquisition planning and project development, feasibility, design, environmental review, and permitting; postconstruction and acquisition monitoring and adaptive management; and engagement of state agencies, tribes, conservation partners, landowners, and other parties.

  2. $30,448,000 of the appropriation in this section is provided solely for board-approved projects to reduce flood damage, including: Construction and property acquisition; preconstruction and acquisition project planning and development, feasibility, design, environmental review, and permitting; completion of environmental review and endangered species act consultation on the proposed flood protection facility; refinement and evaluation of the local action non-dam alternative; and engagement of state agencies, tribes, project sponsors, landowners, and other parties.

  3. $5,204,000 of the appropriation in this section is provided solely for board-approved integrated projects that advance both the habitat restoration and the flood damage reduction goals of the Chehalis Basin strategy using a multibenefit approach, including: Community outreach and education; construction and property acquisition; preconstruction and acquisition planning and project development, feasibility, design, environmental review, and permitting; post construction and acquisition monitoring and adaptive management; and engagement of federal, state, and local agencies, tribes, conservation partners, landowners, and other parties.

  4. $3,900,000 of the appropriation in this section is provided solely for the operations of the office of Chehalis Basin and Chehalis Basin board to oversee the development, implementation, and amendment of the Chehalis Basin strategy, and this is the maximum amount the board may expend for this purpose. Oversight operations include, but are not limited to: Providing financial accountability, project management, and board meeting administration and facilitation.

  5. Specific projects must be approved by at least six of the seven voting members of the Chehalis Basin board. The Chehalis Basin board has the discretion to reallocate the funding between subsections (1), (2), (3), and (4) of this section if needed to meet the objectives of this appropriation and approved by at least six of the seven voting members of the board. However, $3,900,000 is the maximum amount the department may expend for the purposes of subsection (4) of this section.

  6. Up to 1.5 percent of the appropriation in this section may be used by the recreation and conservation office to administer contracts associated with the subprojects funded through this section. Contract administration includes, but is not limited to: Drafting and amending contracts, reviewing and approving invoices, tracking expenditures, and performing field inspections to assess project status when conducting similar assessments related to other agency contracts in the same geographic area.

Section 3004

FOR THE DEPARTMENT OF ECOLOGY

Section 3005

FOR THE DEPARTMENT OF ECOLOGY

Section 3006

FOR THE DEPARTMENT OF ECOLOGY

The appropriation in this section is subject to the following conditions and limitations:

  1. $4,044,000 of the model toxics control capital account—state appropriation is provided solely for the replacement of uncertified heating devices to reduce toxic air pollution. Whenever possible and most cost effective, the agency and local air agency partners must select home heating devices that are certified by the United States environmental protection agency or that do not use natural gas to replace noncompliant devices.

  2. $100,000 of the model toxics control capital account—state appropriation is provided solely for air agencies to offer the opportunity to replace a noncompliant woodstove with a compliant woodstove under this program.

Section 3007

FOR THE DEPARTMENT OF ECOLOGY

Section 3008

FOR THE DEPARTMENT OF ECOLOGY

Section 3009

FOR THE DEPARTMENT OF ECOLOGY

Section 3010

FOR THE DEPARTMENT OF ECOLOGY

Section 3011

FOR THE DEPARTMENT OF ECOLOGY

Section 3012

FOR THE DEPARTMENT OF ECOLOGY

Section 3013

FOR THE DEPARTMENT OF ECOLOGY

The appropriations in this section are subject to the following conditions and limitations:

  1. $1,500,000 of the state building construction account—state appropriation is provided solely for the investigation of PFAS contaminated drinking water in the Lower Issaquah Valley.

  2. $7,857,000 of the model toxics control capital account—state appropriation is provided solely as state grant assistance to the Sammamish Plateau Water and Sewer District for a municipal water treatment plant. State grant assistance is provided as matching funds, not to exceed 50 percent of the estimated total capital cost or actual cost of the project, whichever is less.

Section 3014

FOR THE DEPARTMENT OF ECOLOGY

Section 3015

FOR THE DEPARTMENT OF ECOLOGY

Section 3016

FOR THE DEPARTMENT OF ECOLOGY

Section 3017

FOR THE DEPARTMENT OF ECOLOGY

Section 3018

FOR THE DEPARTMENT OF ECOLOGY

Section 3019

FOR THE DEPARTMENT OF ECOLOGY

Section 3020

FOR THE DEPARTMENT OF ECOLOGY

Section 3021

FOR THE DEPARTMENT OF ECOLOGY

Section 3022

FOR THE DEPARTMENT OF ECOLOGY

Section 3023

FOR THE DEPARTMENT OF ECOLOGY

Section 3024

FOR THE DEPARTMENT OF ECOLOGY

Section 3025

FOR THE DEPARTMENT OF ECOLOGY

Section 3026

FOR THE DEPARTMENT OF ECOLOGY

Section 3027

FOR THE DEPARTMENT OF ECOLOGY

Section 3028

FOR THE DEPARTMENT OF ECOLOGY

The appropriations in this section are subject to the following conditions and limitations:

  1. $32,800,000 of the appropriation in this section is provided solely for planning, designing, engineering, development, coordination, and construction of the Odessa groundwater replacement project, sufficient to irrigate the acres located within the Odessa Subarea Special Study and facilities modifications necessary to accommodate capacity demands resulting from the individual public delivery systems within the Odessa groundwater replacement program.

    1. To be eligible for a grant under this subsection (1), a project must have at least 30 percent of its design work completed by July 1, 2023.

    2. The east Columbia basin irrigation district may only be allowed to make any administrative charges sufficient to administer the state grants, not to exceed one percent of amounts provided to them within this appropriation, with the requirement to report administrative expenditures to the office of Columbia river annually.

  2. $850,000 of the appropriation in this section is provided solely for the department to enter into an agreement with the United States bureau of reclamation to reimburse the bureau for costs related to the design and review activities necessary to complete the transfer of the groundwater replacement delivery system title to the United States by the east Columbia basin irrigation district and to secure project reserved power for public delivery systems.

Section 3029

FOR THE DEPARTMENT OF ECOLOGY

Section 3030

FOR THE DEPARTMENT OF ECOLOGY

Section 3031

FOR THE DEPARTMENT OF ECOLOGY

Section 3032

FOR THE DEPARTMENT OF ECOLOGY

The appropriation in this section is subject to the following conditions and limitations: The appropriation is provided solely as state grant assistance to the cities of Aberdeen and Hoquiam to match federal funding for the Aberdeen-Hoquiam flood protection project, north shore levee and north shore levee-west segments. The legislature intends to provide funds in the amount of $35,500,000 over the course of the 2023-2025 and 2025-2027 fiscal biennia in grant funds for construction of the north shore levee project.

Section 3033

FOR THE DEPARTMENT OF ECOLOGY

The appropriation in this section is subject to the following conditions and limitations: The appropriation is provided solely for projects that include drought mitigation measures, water rights acquisition, or long-term leasing of water rights.

Section 3034

FOR THE DEPARTMENT OF ECOLOGY

Section 3035

FOR THE POLLUTION LIABILITY INSURANCE PROGRAM

Section 3036

FOR THE POLLUTION LIABILITY INSURANCE PROGRAM

Section 3037

FOR THE STATE PARKS AND RECREATION COMMISSION

Section 3038

FOR THE STATE PARKS AND RECREATION COMMISSION

Section 3039

FOR THE STATE PARKS AND RECREATION COMMISSION

Section 3040

FOR THE STATE PARKS AND RECREATION COMMISSION

Section 3041

FOR THE STATE PARKS AND RECREATION COMMISSION

Section 3042

FOR THE STATE PARKS AND RECREATION COMMISSION

Section 3043

FOR THE STATE PARKS AND RECREATION COMMISSION

Section 3044

FOR THE STATE PARKS AND RECREATION COMMISSION

Section 3045

FOR THE STATE PARKS AND RECREATION COMMISSION

Section 3046

FOR THE STATE PARKS AND RECREATION COMMISSION

Section 3047

FOR THE STATE PARKS AND RECREATION COMMISSION

Section 3048

FOR THE STATE PARKS AND RECREATION COMMISSION

The appropriation in this section is subject to the following conditions and limitations:

  1. $500,000 of the state building construction account—state appropriation is provided solely for conducting a needs assessment of recreational marine pump out facilities in Puget Sound with the goal of identifying areas underserviced by the current infrastructure and new projects that will help meet the Puget Sound no discharge zone and prevent vessels from discharging sewage directly into Puget Sound.

  2. $500,000 of the state building construction account—state appropriation is provided solely to assist facilities that might otherwise experience hardship paying the federal matching requirements for projects funded under the United States fish and wildlife service clean vessel act program.

Section 3049

FOR THE STATE PARKS AND RECREATION COMMISSION

The appropriation in this section is subject to the following conditions and limitations:

  1. The appropriation in this section is provided solely for a pool of eligible projects owned by the state parks and recreation commission.

  2. The following projects are the only projects eligible for funding provided in this section:

Larrabee Water System Replacement

Cape Disappointment - Welcome Center and Entrance

Blake Island Marine Facilities Improvements

Wallace Falls Water System Replacement

Cape Disappointment: Campground Access Road Culverts

Statewide - Facility & Infrastructure Backlog Reduction 2023-25

Statewide - ADA Compliance 2023-25

Sun Lakes Replace Primary Lift Station

Fort Worden PDA Fire Alarm System Modifications and Upgrades

Statewide - Code/Regulatory Compliance 2023-25

Statewide - Fish Barrier Removal

Statewide Electric, Water and Sewer Infrastructure Preservation 23-25

Statewide Marine Facility Rehabilitation 2023-25

Palouse to Cascade Trail - Kittitas Depot Historic Preservation

Lake Sylvia Culvert Replacement

Statewide Restroom Renovations

Millersylvania Replace Original 1940's Water System

NW Region Wide Culvert Replacements.

  1. The statewide restroom renovations project in subsection (2) of this section must include the Fort Ebey replace campground restroom project.

  2. The commission shall report to the governor and the appropriate committees of the legislature the list of projects with funding levels, allotments, and schedules for the projects in this section by January 1, 2024.

Section 3050

FOR THE RECREATION AND CONSERVATION FUNDING BOARD

The appropriations in this section are subject to the following conditions and limitations: The appropriations in this section are provided solely for the list of projects approved by the legislature, as identified in LEAP capital document No. RCO-1-SB-2023, developed March 20, 2023.

Section 3051

FOR THE RECREATION AND CONSERVATION FUNDING BOARD

The appropriations in this section are subject to the following conditions and limitations:

  1. $2,400,000 of the state building construction account—state appropriation is provided solely to maintain the lead entity program as described in chapter 77.85 RCW.

  2. $640,000 of the state building construction account—state appropriation is provided solely for regional fisheries enhancement groups created in RCW 77.95.060.

Section 3052

FOR THE RECREATION AND CONSERVATION FUNDING BOARD

Section 3053

FOR THE RECREATION AND CONSERVATION FUNDING BOARD

Section 3054

FOR THE RECREATION AND CONSERVATION FUNDING BOARD

Section 3055

FOR THE RECREATION AND CONSERVATION FUNDING BOARD

The appropriation in this section is subject to the following conditions and limitations: The appropriation in this section is provided solely for the list of projects approved by the legislature, as identified in LEAP capital document No. RCO-3-SB-2023, developed March 20, 2023.

Section 3056

FOR THE RECREATION AND CONSERVATION FUNDING BOARD

The appropriations in this section are subject to the following conditions and limitations: The appropriations in this section are provided solely for the list of projects approved by the legislature, as identified in LEAP capital document No. RCO-4-SB-2023, developed March 20, 2023.

Section 3057

FOR THE RECREATION AND CONSERVATION FUNDING BOARD

The appropriation in this section is subject to the following conditions and limitations: The appropriation in this section is provided solely for the list of projects approved by the legislature, as identified in LEAP capital document No. RCO-5-SB-2023, developed March 20, 2023.

Section 3058

FOR THE RECREATION AND CONSERVATION FUNDING BOARD

The appropriation in this section is subject to the following conditions and limitations: The appropriation in this section is provided solely for the list of projects approved by the legislature, as identified in LEAP capital document No. RCO-2-SB-2023, developed March 20, 2023.

Section 3059

FOR THE RECREATION AND CONSERVATION FUNDING BOARD

The appropriation in this section is subject to the following conditions and limitations: The appropriation in this section is provided solely for the list of projects approved by the legislature, as identified in LEAP capital document No. RCO-7-SB-2023, developed March 20, 2023.

Section 3060

FOR THE RECREATION AND CONSERVATION FUNDING BOARD

The appropriation in this section is subject to the following conditions and limitations:

  1. The appropriation in this section is provided solely for the list of projects approved by the legislature, as identified in LEAP capital document No. RCO-8-SB-2023, developed March 20, 2023.

  2. The recreation and conservation funding board may retain a portion of the funds appropriated in this section for the administration of the grants. The portion of the funds retained for administration may not exceed 4.12 percent of the appropriation.

Section 3061

FOR THE RECREATION AND CONSERVATION FUNDING BOARD

The appropriations in this section are subject to the following conditions and limitations:

  1. The appropriations in this section are provided solely for the list of projects approved by the legislature, as identified in LEAP capital document No. RCO-6-SB-2023, developed March 20, 2023.

  2. The recreation and conservation funding board may retain a portion of the funds appropriated in this section for the administration of the grants. The portion of the funds retained for administration may not exceed three percent of the appropriation.

  3. The department of fish and wildlife may retain a portion of the funds appropriated in this section for the Brian Abbott fish barrier removal board for technical assistance in developing projects for consideration. The portion of the funds retained for technical assistance may not exceed 4.12 percent of the appropriation.

Section 3062

FOR THE RECREATION AND CONSERVATION FUNDING BOARD

Section 3063

FOR THE RECREATION AND CONSERVATION FUNDING BOARD

Section 3064

FOR THE RECREATION AND CONSERVATION FUNDING BOARD

Section 3065

FOR THE RECREATION AND CONSERVATION FUNDING BOARD

Section 3066

FOR THE RECREATION AND CONSERVATION FUNDING BOARD

Section 3067

FOR THE RECREATION AND CONSERVATION FUNDING BOARD

Section 3068

FOR THE RECREATION AND CONSERVATION FUNDING BOARD

The appropriations in this section are subject to the following conditions and limitations:

  1. Except as provided under subsection (4) of this section, the appropriations in this section are provided solely for a grant from the agency to the trust for public land for the acquisition, disposition, and property management costs of real property in upper Kittitas county known as springwood ranch.

  2. The recreation and conservation office shall enter into a grant agreement with the trust for public land that allows for the disbursement of the funding described in subsection (1) of this section to the trust for public land for the following purposes:

    1. To convey a portion of the springwood ranch property to Kittitas county for its ownership and management, including maintenance of existing agricultural uses and future uses allowed under current zoning or that provide a public use or benefit.

    2. To convey a portion of the springwood ranch property to the department of fish and wildlife for its ownership and management.

    3. To convey a portion of the springwood ranch property to the Yakama Nation for its ownership and management.

    4. To convey a portion of the springwood ranch property to the Kittitas reclamation district, which shall hold the property until a transfer, without compensation and not subject to RCW 87.03.136, to the United States bureau of reclamation for the purposes of construction of a water supply reservoir in accordance with the Yakima basin integrated plan, or until such purpose is declared by the bureau of reclamation no longer feasible.

    5. To assist in achieving the goals of the Yakima basin integrated plan.

  3. If the bureau of reclamation determines that the construction of a water supply reservoir is not feasible as described in subsection (2)(d) of this section, the Kittitas reclamation district shall work with Kittitas county, the Yakama Nation, the department of fish and wildlife, and other interested stakeholders to identify the appropriate public owner and manager and convey, without compensation and not subject to RCW 87.03.136, the Kittitas reclamation district's portion of springwood ranch to that entity.

  4. The recreation and conservation office may use up to one percent of the appropriations in this section, if necessary, for its administrative costs.

Section 3069

FOR THE RECREATION AND CONSERVATION FUNDING BOARD

The appropriation in this section is subject to the following conditions and limitations:

  1. $5,600,000 of the youth athletic facility account—state appropriation is provided solely for a competitive grant program that improves equitable access to community outdoor athletic facilities.

  2. $1,000,000 of the youth athletic facility account—state appropriation is provided solely for the sentinel gap community park project.

  3. Up to 2.0 percent of the appropriation in this section may be used by the recreation and conservation office for the costs of administration.

Section 3070

FOR THE RECREATION AND CONSERVATION FUNDING BOARD

Section 3071

FOR THE STATE CONSERVATION COMMISSION

Section 3072

FOR THE STATE CONSERVATION COMMISSION

Section 3073

FOR THE STATE CONSERVATION COMMISSION

Section 3074

FOR THE STATE CONSERVATION COMMISSION

Section 3075

FOR THE STATE CONSERVATION COMMISSION

The appropriation in this section is subject to the following conditions and limitations:

  1. The appropriation in this section is provided solely for technical assistance and grants to conservation districts for the purpose of implementing water conservation measures and irrigation efficiencies. The state conservation commission shall give preference to projects located in the 16 fish critical basins, other water-short or drought impacted basins, and basins with significant water resource and instream flow issues. Projects that are not within the basins described in this subsection are also eligible to receive funding.

  2. Conservation districts statewide are eligible for grants under subsection (1) of this section. A conservation district receiving funds shall manage each grant to ensure that a portion of the water saved by the water conservation measure or irrigation efficiency is available for other instream and out-of-stream uses and users. The proportion of saved water made available for other uses and users must be equal to the percentage of the public investment in the conservation measure or irrigation efficiency.

Section 3076

FOR THE STATE CONSERVATION COMMISSION

Section 3077

FOR THE STATE CONSERVATION COMMISSION

Section 3078

FOR THE STATE CONSERVATION COMMISSION

Section 3079

FOR THE STATE CONSERVATION COMMISSION

Section 3080

FOR THE STATE CONSERVATION COMMISSION

Section 3081

FOR THE DEPARTMENT OF FISH AND WILDLIFE

The reappropriation in this section is subject to the following conditions and limitations: The reappropriation is subject to the provisions of section 3205, chapter 19, Laws of 2013 2nd sp. sess.

Section 3082

FOR THE DEPARTMENT OF FISH AND WILDLIFE

Section 3083

FOR THE DEPARTMENT OF FISH AND WILDLIFE

Section 3084

FOR THE DEPARTMENT OF FISH AND WILDLIFE

Section 3085

FOR THE DEPARTMENT OF FISH AND WILDLIFE

Section 3086

FOR THE DEPARTMENT OF FISH AND WILDLIFE

Section 3087

FOR THE DEPARTMENT OF FISH AND WILDLIFE

The appropriations in this section are subject to the following conditions and limitations: The reappropriation is subject to the provisions of section 3243, chapter 413, Laws of 2019.

Section 3088

FOR THE DEPARTMENT OF FISH AND WILDLIFE

Section 3089

FOR THE DEPARTMENT OF FISH AND WILDLIFE

Section 3090

FOR THE DEPARTMENT OF FISH AND WILDLIFE

Section 3091

FOR THE DEPARTMENT OF FISH AND WILDLIFE

Section 3092

FOR THE DEPARTMENT OF FISH AND WILDLIFE

The appropriations in this section are subject to the following conditions and limitations: The reappropriation is subject to the provisions of section 3058, chapter 296, Laws of 2022.

Section 3093

FOR THE DEPARTMENT OF FISH AND WILDLIFE

Section 3094

FOR THE DEPARTMENT OF FISH AND WILDLIFE

Section 3095

FOR THE DEPARTMENT OF FISH AND WILDLIFE

The appropriations in this section are subject to the following conditions and limitations: $14,000,000 of the state building construction account—state appropriation is provided solely to fund construction of the Duckabush estuary habitat restoration project. The legislature intends to provide funds in the amount of $39,380,000 over the course of the 2023-2025 and 2025-2027 fiscal biennia for this project.

Section 3096

FOR THE DEPARTMENT OF FISH AND WILDLIFE

Section 3097

FOR THE DEPARTMENT OF FISH AND WILDLIFE

Section 3098

FOR THE DEPARTMENT OF FISH AND WILDLIFE

Section 3099

FOR THE DEPARTMENT OF FISH AND WILDLIFE

Section 3100

FOR THE DEPARTMENT OF NATURAL RESOURCES

Section 3101

FOR THE DEPARTMENT OF NATURAL RESOURCES

Section 3102

FOR THE DEPARTMENT OF NATURAL RESOURCES

Section 3103

FOR THE DEPARTMENT OF NATURAL RESOURCES

Section 3104

FOR THE DEPARTMENT OF NATURAL RESOURCES

Section 3105

FOR THE DEPARTMENT OF NATURAL RESOURCES

Section 3106

FOR THE DEPARTMENT OF NATURAL RESOURCES

Section 3107

FOR THE DEPARTMENT OF NATURAL RESOURCES

2023-25 State Forest Land Replacement - Encumbered Lands (40000146)

Section 3108

FOR THE DEPARTMENT OF NATURAL RESOURCES

Removal of Aquatic Derelict Structures (40000147)

The appropriation in this section is subject to the following conditions and limitations: The appropriation in this section is provided solely for the following list of projects:

Dickman Mill $3,500,000

Former High Tides Seafood Pier $3,000,000

Ray's Boathouse Pier $650,000

Triton-America Pier $2,500,000

Section 3109

FOR THE DEPARTMENT OF NATURAL RESOURCES

Section 3110

FOR THE DEPARTMENT OF NATURAL RESOURCES

Section 3111

FOR THE DEPARTMENT OF NATURAL RESOURCES

Section 3112

FOR THE DEPARTMENT OF NATURAL RESOURCES

Section 3113

FOR THE DEPARTMENT OF NATURAL RESOURCES

The appropriation in this section is subject to the following conditions and limitations: The appropriation in this section is provided solely for the following list of projects:

Eglon$7,300,000

Upper Dry Gulch$3,075,000

Section 3114

FOR THE DEPARTMENT OF NATURAL RESOURCES

Section 3115

FOR THE DEPARTMENT OF NATURAL RESOURCES

Section 3116

FOR THE DEPARTMENT OF NATURAL RESOURCES

Section 3117

FOR THE DEPARTMENT OF NATURAL RESOURCES

Section 3118

FOR THE DEPARTMENT OF NATURAL RESOURCES

Section 3119

FOR THE DEPARTMENT OF NATURAL RESOURCES

Section 3120

FOR THE DEPARTMENT OF NATURAL RESOURCES

Section 3121

FOR THE DEPARTMENT OF NATURAL RESOURCES

Section 3122

FOR THE DEPARTMENT OF NATURAL RESOURCES

The appropriation in this section is subject to the following conditions and limitations: By November 1, 2023, the department must provide the legislature with a strategic plan for future carbon sequestration investments on state lands. The strategic plan must include, but is not limited to, a description of proposed carbon sequestration projects in order of priority, a timeline for project implementation, and a financial analysis of the impact of each project on trust beneficiaries. The analysis must compare the difference in net present value and cash flow between carbon sequestration and planned timber sales pursuant to decadal sustainable harvest calculations under chapter 79.10 RCW and describe the economic impacts from any proposed carbon sequestration project on the forest products industry.

Section 3123

FOR THE DEPARTMENT OF NATURAL RESOURCES

Land Appraisals (92000057)

The appropriation in this section is subject to the following conditions and limitations: The appropriation in this section is provided solely for the department to conduct land appraisals of parcel number 55161.9025 located in the City of Liberty Lake in Spokane county and the Geiger field property operated by the national guard and located at the Spokane international airport. The department shall complete the land appraisals and provide the legislature with findings by December 1, 2023.

Section 3124

FOR THE DEPARTMENT OF AGRICULTURE

2023-25 WA State Fairs Health and Safety Grants (92000006)

Section 4001

FOR THE WASHINGTON STATE PATROL

Section 4002

FOR THE WASHINGTON STATE PATROL

Section 4003

FOR THE WASHINGTON STATE PATROL

Section 4004

FOR THE WASHINGTON STATE PATROL

Section 4005

FOR THE WASHINGTON STATE PATROL

Section 4006

FOR THE WASHINGTON STATE PATROL

Section 4007

FOR THE DEPARTMENT OF TRANSPORTATION

The appropriation in this section is subject to the following conditions and limitations: The appropriation in this section must be deposited in the public use general aviation airport loan revolving account.

Section 5001

FOR THE SUPERINTENDENT OF PUBLIC INSTRUCTION

The appropriations in this section are subject to the following conditions and limitations: The reappropriation is subject to the provisions of section 5003, chapter 269, Laws of 2022.

Section 5002

FOR THE SUPERINTENDENT OF PUBLIC INSTRUCTION

The appropriation in this section is subject to the following conditions and limitations:

  1. $583,141,000 of the appropriation in this section is provided solely for school construction assistance grants for qualifying public school construction projects.

  2. $3,684,000 of the appropriation in this section is provided solely for study and survey grants and for completing inventory and building condition assessments for public school districts every six years.

Section 5003

FOR THE SUPERINTENDENT OF PUBLIC INSTRUCTION

The appropriations in this section are subject to the following conditions and limitations:

  1. $46,608,000 of the common school construction account—state appropriation, $31,783,000 of the state building construction account—state appropriation, and $3,000,000 of the common school construction fund—federal appropriation in this section are provided solely for modernization grants for small school districts authorized under RCW 28A.525.159.

  2. $1,307,000 of the common school construction account—state appropriation and $189,000 of the state building construction account—state appropriation in this section are provided solely for planning grants for small school districts authorized under RCW 28A.525.159. Planning grants may not exceed $50,000 per district. Planning grants may only be awarded to school districts with an estimated total project cost of $5,000,000 or less.

  3. $17,145,000 of the state building construction account—state appropriation in this section is provided solely for planning grants and modernization grants to state-tribal compact schools. The superintendent of public instruction may prioritize planning grants for state-tribal compact schools with the most serious building deficiencies and the most limited financial capacity.

  4. The superintendent of public instruction shall submit a list of small school district modernization projects, as prioritized by the advisory committee under RCW 28A.525.159, to the legislature and the governor by September 15, 2024. The list must include: (a) A description of the project; (b) the proposed state funding level, not to exceed $5,000,000; (c) estimated total project costs; and (d) local funding resources.

  5. The appropriations in this section may be awarded only to projects approved by the legislature, as identified in LEAP capital document No. OSPI-1-SB-2023, developed March 20, 2023.

Section 5004

FOR THE SUPERINTENDENT OF PUBLIC INSTRUCTION

Section 5005

FOR THE SUPERINTENDENT OF PUBLIC INSTRUCTION

The appropriation in this section is subject to the following conditions and limitations:

  1. $4,000,000 of the state building construction account—state appropriation in this section is provided solely for emergency repair grants to address unexpected and imminent health and safety hazards at K-12 public schools, including skill centers, that will impact the day-to-day operations of the school facility, and this is the maximum amount that may be spent for this purpose. For emergency repair grants only, an emergency declaration must be signed by the school district board of directors and submitted to the superintendent of public instruction for consideration. The emergency declaration must include a description of the imminent health and safety hazard, the possible cause, the proposed scope of emergency repair work and related cost estimate, and identification of local funding to be applied to the project. Grants of emergency repair moneys must be conditioned upon the written commitment and plan of the school district board of directors to repay the grant with any insurance payments or other judgments that may be awarded, if applicable.

  2. $11,600,000 of the state building construction account—state appropriation in this section is provided solely for urgent repair grants to address nonreccurring urgent small repair projects at K-12 public schools, excluding skill centers, that could impact the health and safety of students and staff if not completed, and this is the maximum amount that may be spent for this purpose. The office of the superintendent of public instruction, after consulting with maintenance and operations administrators of school districts, shall develop criteria and assurances for providing funding for specific projects through a competitive grant program. The criteria and assurances must include, but are not limited to, the following: (a) Limiting school districts to one grant, not to exceed $500,000, per three-year period; (b) prioritizing applications based on limited school district financial resources for the project; and (c) requiring any district receiving funding provided in this section to demonstrate a consistent commitment to addressing school facility needs. The grant applications must include a comprehensive description of the health and safety issues to be addressed, a detailed description of the remedy, including a detailed cost estimate of the repair or replacement work to be performed, and identification of local funding, if any, which will be applied to the project. Grants may be used for, but are not limited to: Repair or replacement of failing building systems, abatement of potentially hazardous materials, and safety-related structural improvements.

  3. $3,600,000 of the state building construction account—state appropriation in this section is provided solely for equal access grants for facility repairs and alterations at K-12 public schools, including skills centers, to improve compliance with the Americans with disabilities act and individuals with disabilities education act, and this is the maximum amount that may be spent for this purpose. The office of the superintendent of public instruction shall develop criteria and assurances for providing funding for specific projects through a competitive grant program. The criteria and assurances must include, but are not limited to, the following: (a) Limiting districts to one grant, not to exceed $100,000, per three-year period; (b) prioritizing applications based on limited school district financial resources for the project; and (c) requiring recipient districts to demonstrate a consistent commitment to addressing school facility needs. The grant applications must include a description of the Americans with disabilities act or individuals with disabilities education act compliance deficiency, a comprehensive description of the facility accessibility issues to be addressed, a detailed description of the remedy including a detailed cost estimate of the repair or replacement work to be performed, and identification of local funding, if any, which will be applied to the project. Priority for grant funding must be given to school districts that demonstrate a lack of capital resources to address the compliance deficiencies outlined in the grant application.

  4. The superintendent of public instruction must notify the office of financial management, the legislative evaluation and accountability program committee, the house capital budget committee, and the senate ways and means committee as projects described in subsection (1) of this section are approved for funding.

Section 5006

FOR THE SUPERINTENDENT OF PUBLIC INSTRUCTION

The appropriation in this section is subject to the following conditions and limitations:

  1. [Empty]

    1. $10,000,000 of the appropriation in this section is provided solely for healthy kids and healthy schools grants for projects that are consistent with the healthiest next generation priorities.

    2. The appropriation in this subsection (1) is provided solely for grant funding to school districts for the purchase of equipment or to make repairs to existing equipment that is related to improving: (i) Children's physical health, and may include, but is not limited to, fitness playground equipment, covered play areas, and physical education equipment or related structures or renovation; and (ii) children's nutrition, and may include, but is not limited to, garden related structures and greenhouses to provide students access to fresh produce, and kitchen equipment or upgrades.

    3. The office of the superintendent of public instruction shall develop criteria for grant funding under this subsection (1) that include, but are not limited to, the following requirements: (i) Districts may apply for grants, but no single district may receive more than $200,000 of the appropriation for grants awarded under this section; (ii) any district receiving funding provided in this section must demonstrate a consistent commitment to addressing school facilities' needs; and (iii) applicants with a high percentage of students who are eligible and enrolled in the free and reduced-price meals program may be prioritized.

  2. $3,000,000 of the model toxics control capital account—state appropriation in this section is provided solely for grants to school districts for the replacement of lead-contaminated pipes, drinking water fixtures, and the purchase of water filters, including the labor costs of remediation design, installation, and construction.

Section 5007

FOR THE SUPERINTENDENT OF PUBLIC INSTRUCTION

The appropriation in this section is subject to the following conditions and limitations:

  1. The appropriation in this section is provided solely for the superintendent of public instruction to provide competitive grants to school districts to purchase and install career and technical education equipment that expands career connected learning and work-integrated learning opportunities.

  2. The office of the superintendent of public instruction, after consulting with school districts, Career Connect Washington, and the workforce training and education coordinating board, shall develop criteria and assurances for providing funding and outcomes for specific projects through a competitive grant program to stay within the appropriation level provided in this section consistent with the following priorities. The criteria must include, but are not limited to, the following:

    1. Districts or schools must demonstrate that the request provides necessary equipment to deliver career and technical education; and

    2. Applicants with a high percentage of students who are eligible and enrolled in the free and reduced-price meals program must be prioritized.

  3. No single district may receive more than $150,000 of the appropriation.

Section 5008

FOR THE SUPERINTENDENT OF PUBLIC INSTRUCTION

The appropriations in this section are subject to the following conditions and limitations: In addition to the conditions and limitations specified in section 8017 of this act, no skill center shall receive funding for more than two minor works projects within the 2023-2025 fiscal biennium.

Section 5009

FOR THE SUPERINTENDENT OF PUBLIC INSTRUCTION

Section 5010

FOR THE SUPERINTENDENT OF PUBLIC INSTRUCTION

Section 5011

FOR THE SUPERINTENDENT OF PUBLIC INSTRUCTION

The appropriation in this section is subject to the following conditions and limitations:

  1. The appropriation in this section is provided solely for a contract with a statewide community-based organization with experience planning and developing green stormwater infrastructure and related educational programs on public school properties. The organization awarded funding under this section must use this funding solely for green stormwater infrastructure projects on public school properties.

  2. The organization selected under subsection (1) of this section must use geographic analysis to identify green stormwater infrastructure project locations based on the opportunity to reduce stormwater runoff.

  3. To qualify for a project under this section, schools must be eligible for financial assistance under Title I of the elementary and secondary education act, as amended by the every student succeeds act (P.L. 114-95). The organization selected under subsection (1) of this section must prioritize schools with high percentages of students eligible for the free and reduced-price meals program that also serve diverse student populations.

  4. Stormwater infrastructure projects under this section should aim to: (a) Provide equity of opportunity in high-need communities; and (b) engage students in conjunction with K-12 STEM education programs aligned with the Washington state science and learning standards.

Section 5012

FOR THE SUPERINTENDENT OF PUBLIC INSTRUCTION

The appropriation in this section is subject to the following conditions and limitations: The appropriation is provided solely for the following list of projects:

Cascadia Technical Academy (Vancouver)$250,000

Crescent Elementary (Oak Harbor)$13,600,000

Ingraham High School Construction Trades Skills

Center (Seattle)$527,000

Maritime 253: South Puget Sound Maritime Skills

Center (Tacoma)$6,000,000

Rainier Beach High School Campus Skills Center$9,915,000

Seattle Skills Center (Seattle)$2,200,000

Stevenson-Carson High School (Stevenson)$750,000

Washington Middle School (Seattle)$98,000

Section 5013

FOR THE SUPERINTENDENT OF PUBLIC INSTRUCTION

Section 5014

FOR THE STATE SCHOOL FOR THE BLIND

Section 5015

CENTER FOR DEAF AND HARD OF HEARING YOUTH

Section 5016

CENTER FOR DEAF AND HARD OF HEARING YOUTH

Section 5017

CENTER FOR DEAF AND HARD OF HEARING YOUTH

Section 5018

FOR THE UNIVERSITY OF WASHINGTON

Section 5019

FOR THE UNIVERSITY OF WASHINGTON

Section 5020

FOR THE UNIVERSITY OF WASHINGTON

Section 5021

FOR THE UNIVERSITY OF WASHINGTON

Section 5022

FOR THE UNIVERSITY OF WASHINGTON

Section 5023

FOR THE UNIVERSITY OF WASHINGTON

Section 5024

FOR THE UNIVERSITY OF WASHINGTON

Section 5025

FOR THE UNIVERSITY OF WASHINGTON

Section 5026

FOR THE UNIVERSITY OF WASHINGTON

Section 5027

FOR THE UNIVERSITY OF WASHINGTON

Section 5028

FOR THE UNIVERSITY OF WASHINGTON

Section 5029

FOR THE UNIVERSITY OF WASHINGTON

The appropriations in this section are subject to the following conditions and limitations: The reappropriation is subject to the provisions of section 5055, chapter 332, Laws of 2021.

Section 5030

FOR THE UNIVERSITY OF WASHINGTON

Section 5031

FOR WASHINGTON STATE UNIVERSITY

Section 5032

FOR WASHINGTON STATE UNIVERSITY

Section 5033

FOR WASHINGTON STATE UNIVERSITY

Section 5034

FOR WASHINGTON STATE UNIVERSITY

Section 5035

FOR WASHINGTON STATE UNIVERSITY

Section 5036

FOR WASHINGTON STATE UNIVERSITY

Section 5037

FOR WASHINGTON STATE UNIVERSITY

Section 5038

FOR WASHINGTON STATE UNIVERSITY

Section 5039

FOR EASTERN WASHINGTON UNIVERSITY

Section 5040

FOR EASTERN WASHINGTON UNIVERSITY

Section 5041

FOR EASTERN WASHINGTON UNIVERSITY

Section 5042

FOR EASTERN WASHINGTON UNIVERSITY

Section 5043

FOR EASTERN WASHINGTON UNIVERSITY

Section 5044

FOR CENTRAL WASHINGTON UNIVERSITY

Section 5045

FOR CENTRAL WASHINGTON UNIVERSITY

Section 5046

FOR CENTRAL WASHINGTON UNIVERSITY

Section 5047

FOR CENTRAL WASHINGTON UNIVERSITY

Section 5048

FOR CENTRAL WASHINGTON UNIVERSITY

Section 5049

FOR THE EVERGREEN STATE COLLEGE

Section 5050

FOR THE EVERGREEN STATE COLLEGE

Section 5051

FOR THE EVERGREEN STATE COLLEGE

Section 5052

FOR WESTERN WASHINGTON UNIVERSITY

Section 5053

FOR WESTERN WASHINGTON UNIVERSITY

Section 5054

FOR WESTERN WASHINGTON UNIVERSITY

Section 5055

FOR WESTERN WASHINGTON UNIVERSITY

Section 5056

FOR WESTERN WASHINGTON UNIVERSITY

Section 5057

FOR WESTERN WASHINGTON UNIVERSITY

Section 5058

FOR WESTERN WASHINGTON UNIVERSITY

Section 5059

FOR THE WASHINGTON STATE ARTS COMMISSION

Section 5060

FOR THE WASHINGTON STATE HISTORICAL SOCIETY

Section 5061

FOR THE WASHINGTON STATE HISTORICAL SOCIETY

Section 5062

FOR THE WASHINGTON STATE HISTORICAL SOCIETY

Section 5063

FOR THE WASHINGTON STATE HISTORICAL SOCIETY

Section 5064

FOR THE EASTERN WASHINGTON STATE HISTORICAL SOCIETY

Section 5065

FOR THE COMMUNITY AND TECHNICAL COLLEGE SYSTEM

Section 5066

FOR THE COMMUNITY AND TECHNICAL COLLEGE SYSTEM

Section 5067

FOR THE COMMUNITY AND TECHNICAL COLLEGE SYSTEM

Section 5068

FOR THE COMMUNITY AND TECHNICAL COLLEGE SYSTEM

Section 5069

FOR THE COMMUNITY AND TECHNICAL COLLEGE SYSTEM

Section 5070

FOR THE COMMUNITY AND TECHNICAL COLLEGE SYSTEM

Section 5071

FOR THE COMMUNITY AND TECHNICAL COLLEGE SYSTEM

Section 5072

FOR THE COMMUNITY AND TECHNICAL COLLEGE SYSTEM

Section 5073

FOR THE COMMUNITY AND TECHNICAL COLLEGE SYSTEM

Section 5074

FOR THE COMMUNITY AND TECHNICAL COLLEGE SYSTEM

Section 5075

FOR THE COMMUNITY AND TECHNICAL COLLEGE SYSTEM

Section 5076

FOR THE COMMUNITY AND TECHNICAL COLLEGE SYSTEM

Section 5077

FOR THE COMMUNITY AND TECHNICAL COLLEGE SYSTEM

Section 5078

FOR THE COMMUNITY AND TECHNICAL COLLEGE SYSTEM

The appropriation in this section is subject to the following conditions and limitations:

  1. This appropriation is provided solely for the state board for community and technical colleges to provide competitive grants to community and technical colleges to purchase and install equipment that expands career-connected learning opportunities.

  2. The state board for community and technical colleges shall develop common criteria for providing competitive grant funding and outcomes for specific projects.

Section 6001

FOR THE OFFICE OF THE SECRETARY OF STATE

Section 6002

FOR THE DEPARTMENT OF COMMERCE

Section 6003

FOR THE DEPARTMENT OF COMMERCE

The reappropriation in this section is subject to the following conditions and limitations: The reappropriation is subject to the provisions of section 1016, chapter 2, Laws of 2012 2nd sp. sess.

Section 6004

FOR THE DEPARTMENT OF COMMERCE

The reappropriations in this section are subject to the following conditions and limitations: The reappropriations are subject to the provisions of section 6003, chapter 4, Laws of 2017 3rd sp. sess.

Section 6005

FOR THE DEPARTMENT OF COMMERCE

The reappropriation in this section is subject to the following conditions and limitations:

  1. The reappropriation is subject to the provisions of section 6004, chapter 4, Laws of 2017 3rd sp. sess.

  2. The reappropriation for any project for which the department has not executed a contract by December 31, 2023, shall lapse. The department shall provide a list of lapsed projects to the legislative fiscal committees no later than January 15, 2024.

Section 6006

FOR THE DEPARTMENT OF COMMERCE

The reappropriations in this section are subject to the following conditions and limitations: The reappropriations are subject to the provisions of section 1004, chapter 296, Laws of 2022.

Section 6007

FOR THE DEPARTMENT OF COMMERCE

Section 6008

FOR THE DEPARTMENT OF COMMERCE

The reappropriation in this section is subject to the following conditions and limitations: The reappropriation is subject to the provisions of section 1019, chapter 413, Laws of 2019.

Section 6009

FOR THE DEPARTMENT OF COMMERCE

The reappropriation in this section is subject to the following conditions and limitations: The reappropriation is subject to the provisions of section 1014, chapter 298, Laws of 2018.

Section 6010

FOR THE DEPARTMENT OF COMMERCE

The reappropriations in this section are subject to the following conditions and limitations: The reappropriations are subject to the provisions of section 1007, chapter 296, Laws of 2022.

Section 6011

FOR THE DEPARTMENT OF COMMERCE

The reappropriations in this section are subject to the following conditions and limitations: The reappropriations are subject to the provisions of section 6007, chapter 413, Laws of 2019.

Section 6012

FOR THE DEPARTMENT OF COMMERCE

The reappropriation in this section is subject to the following conditions and limitations:

  1. The reappropriation is subject to the provisions of section 1052, chapter 296, Laws of 2022.

  2. The reappropriation for any project for which the department has not executed a contract by December 31, 2024, shall lapse. The department shall provide a list of lapsed projects to the legislative fiscal committees no later than January 15, 2025.

Section 6013

FOR THE DEPARTMENT OF COMMERCE

The reappropriations in this section are subject to the following conditions and limitations: The reappropriations are subject to the provisions of section 1005, chapter 298, Laws of 2018.

Section 6014

FOR THE DEPARTMENT OF COMMERCE

The reappropriation in this section is subject to the following conditions and limitations: The reappropriation is subject to the provisions of section 1002, chapter 356, Laws of 2020.

Section 6015

FOR THE DEPARTMENT OF COMMERCE

The reappropriation in this section is subject to the following conditions and limitations: The reappropriation is subject to the provisions of section 1027, chapter 413, Laws of 2019.

Section 6016

FOR THE DEPARTMENT OF COMMERCE

The reappropriation in this section is subject to the following conditions and limitations: The reappropriation is subject to the provisions of section 6004, chapter 413, Laws of 2019.

Section 6017

FOR THE DEPARTMENT OF COMMERCE

The reappropriations in this section are subject to the following conditions and limitations: The reappropriations are subject to the provisions of section 6005, chapter 332, Laws of 2021.

Section 6018

FOR THE DEPARTMENT OF COMMERCE

The reappropriation in this section is subject to the following conditions and limitations: The reappropriation is subject to the provisions of section 1020, chapter 356, Laws of 2020.

Section 6019

FOR THE DEPARTMENT OF COMMERCE

The reappropriation in this section is subject to the following conditions and limitations: The reappropriation is subject to the provisions of section 6011, chapter 332, Laws of 2021.

Section 6020

FOR THE DEPARTMENT OF COMMERCE

Section 6021

FOR THE DEPARTMENT OF COMMERCE

The reappropriation in this section is subject to the following conditions and limitations: The reappropriation is subject to the provisions of section 1034, chapter 413, Laws of 2019.

Section 6022

FOR THE DEPARTMENT OF COMMERCE

The reappropriations in this section are subject to the following conditions and limitations: The reappropriations are subject to the provisions of section 1005, chapter 356, Laws of 2020.

Section 6023

FOR THE DEPARTMENT OF COMMERCE

The reappropriation in this section is subject to the following conditions and limitations: The reappropriation is subject to the provisions of section 1036, chapter 413, Laws of 2019.

Section 6024

FOR THE DEPARTMENT OF COMMERCE

The reappropriations in this section are subject to the following conditions and limitations: The reappropriations are subject to the provisions of section 1006, chapter 356, Laws of 2020.

Section 6025

FOR THE DEPARTMENT OF COMMERCE

The reappropriation in this section is subject to the following conditions and limitations: The reappropriation is subject to the provisions of section 1038, chapter 413, Laws of 2019.

Section 6026

FOR THE DEPARTMENT OF COMMERCE

The reappropriation in this section is subject to the following conditions and limitations: The reappropriation is subject to the provisions of section 1023, chapter 356, Laws of 2020.

Section 6027

FOR THE DEPARTMENT OF COMMERCE

Section 6028

FOR THE DEPARTMENT OF COMMERCE

The reappropriation in this section is subject to the following conditions and limitations: The reappropriation is subject to the provisions of section 1010, chapter 356, Laws of 2020.

Section 6029

FOR THE DEPARTMENT OF COMMERCE

The reappropriation in this section is subject to the following conditions and limitations: The reappropriation is subject to the provisions of section 6007, chapter 332, Laws of 2021.

Section 6030

FOR THE DEPARTMENT OF COMMERCE

The reappropriation in this section is subject to the following conditions and limitations: The reappropriation is subject to the provisions of section 1012, chapter 356, Laws of 2020.

Section 6031

FOR THE DEPARTMENT OF COMMERCE

The reappropriation in this section is subject to the following conditions and limitations: The reappropriation is subject to the provisions of section 1044, chapter 413, Laws of 2019.

Section 6032

FOR THE DEPARTMENT OF COMMERCE

The reappropriation in this section is subject to the following conditions and limitations: The reappropriation is subject to the provisions of section 6008, chapter 332, Laws of 2021.

Section 6033

FOR THE DEPARTMENT OF COMMERCE

The reappropriations in this section are subject to the following conditions and limitations: The reappropriations are subject to the provisions of section 1009, chapter 356, Laws of 2020.

Section 6034

FOR THE DEPARTMENT OF COMMERCE

The reappropriation in this section is subject to the following conditions and limitations: The reappropriation is subject to the provisions of section 1056, chapter 332, Laws of 2021.

Section 6035

FOR THE DEPARTMENT OF COMMERCE

The reappropriation in this section is subject to the following conditions and limitations: The reappropriation is subject to the provisions of section 1057, chapter 332, Laws of 2021.

Section 6036

FOR THE DEPARTMENT OF COMMERCE

Section 6037

FOR THE DEPARTMENT OF COMMERCE

The reappropriation in this section is subject to the following conditions and limitations: The reappropriation is subject to the provisions of section 1059, chapter 332, Laws of 2021.

Section 6038

FOR THE DEPARTMENT OF COMMERCE

The reappropriation in this section is subject to the following conditions and limitations: The reappropriation is subject to the provisions of section 1060, chapter 332, Laws of 2021.

Section 6039

FOR THE DEPARTMENT OF COMMERCE

Section 6040

FOR THE DEPARTMENT OF COMMERCE

The reappropriation in this section is subject to the following conditions and limitations: The reappropriation is subject to the provisions of section 1017, chapter 296, Laws of 2022.

Section 6041

FOR THE DEPARTMENT OF COMMERCE

The reappropriations in this section are subject to the following conditions and limitations: The reappropriations are subject to the provisions of section 7001 of this act.

Section 6042

FOR THE DEPARTMENT OF COMMERCE

The reappropriation in this section is subject to the following conditions and limitations: The reappropriation is subject to the provisions of section 1065, chapter 332, Laws of 2021.

Section 6043

FOR THE DEPARTMENT OF COMMERCE

The reappropriations in this section are subject to the following conditions and limitations: The reappropriations are subject to the provisions of section 1019, chapter 296, Laws of 2022.

Section 6044

FOR THE DEPARTMENT OF COMMERCE

The reappropriations in this section are subject to the following conditions and limitations: The reappropriations are subject to the provisions of section 1067, chapter 332, Laws of 2021.

Section 6045

FOR THE DEPARTMENT OF COMMERCE

The reappropriations in this section are subject to the following conditions and limitations: The reappropriations are subject to the provisions of section 1020, chapter 296, Laws of 2022.

Section 6046

FOR THE DEPARTMENT OF COMMERCE

The reappropriations in this section are subject to the following conditions and limitations: The reappropriations are subject to the provisions of section 1039, chapter 296, Laws of 2022.

Section 6047

FOR THE DEPARTMENT OF COMMERCE

The reappropriation in this section is subject to the following conditions and limitations: The reappropriation is subject to the provisions of section 1070, chapter 332, Laws of 2021.

Section 6048

FOR THE DEPARTMENT OF COMMERCE

The reappropriations in this section are subject to the following conditions and limitations: The reappropriations are subject to the provisions of section 1021, chapter 296, Laws of 2022.

Section 6049

FOR THE DEPARTMENT OF COMMERCE

Section 6050

FOR THE DEPARTMENT OF COMMERCE

The reappropriation in this section is subject to the following conditions and limitations: The reappropriation is subject to the provisions of section 1022, chapter 296, Laws of 2022.

Section 6051

FOR THE DEPARTMENT OF COMMERCE

Section 6052

FOR THE DEPARTMENT OF COMMERCE

The reappropriation in this section is subject to the following conditions and limitations: The reappropriation is subject to the provisions of section 1012, chapter 296, Laws of 2022.

Section 6053

FOR THE DEPARTMENT OF COMMERCE

The reappropriation in this section is subject to the following conditions and limitations: The reappropriation is subject to the provisions of section 1013, chapter 296, Laws of 2022.

Section 6054

FOR THE DEPARTMENT OF COMMERCE

The reappropriations in this section are subject to the following conditions and limitations: The reappropriations are subject to the provisions of section 1024, chapter 296, Laws of 2022.

Section 6055

FOR THE DEPARTMENT OF COMMERCE

The reappropriation in this section is subject to the following conditions and limitations: The reappropriation is subject to the provisions of section 1026, chapter 296, Laws of 2022.

Section 6056

FOR THE DEPARTMENT OF COMMERCE

The reappropriation in this section is subject to the following conditions and limitations: The reappropriation is subject to the provisions of section 1027, chapter 296, Laws of 2022.

Section 6057

FOR THE DEPARTMENT OF COMMERCE

The reappropriations in this section are subject to the following conditions and limitations: The reappropriations are subject to the provisions of section 1011, chapter 296, Laws of 2022.

Section 6058

FOR THE DEPARTMENT OF COMMERCE

The reappropriation in this section is subject to the following conditions and limitations: The reappropriation is subject to the provisions of section 1017, chapter 356, Laws of 2020.

Section 6059

FOR THE DEPARTMENT OF COMMERCE

The reappropriation in this section is subject to the following conditions and limitations: The reappropriation is subject to the provisions of section 1053, chapter 413, Laws of 2019.

Section 6060

FOR THE DEPARTMENT OF COMMERCE

The reappropriation in this section is subject to the following conditions and limitations: The reappropriation is subject to the provisions of section 1018, chapter 356, Laws of 2020.

Section 6061

FOR THE DEPARTMENT OF COMMERCE

The reappropriation in this section is subject to the following conditions and limitations: The reappropriation is subject to the provisions of section 6012, chapter 332, Laws of 2021.

Section 6062

FOR THE DEPARTMENT OF COMMERCE

The reappropriation in this section is subject to the following conditions and limitations: The reappropriation is subject to the provisions of section 1072, chapter 332, Laws of 2021.

Section 6063

FOR THE DEPARTMENT OF COMMERCE

The reappropriation in this section is subject to the following conditions and limitations: The reappropriation is subject to the provisions of section 1043, chapter 296, Laws of 2022.

Section 6064

FOR THE DEPARTMENT OF COMMERCE

The reappropriation in this section is subject to the following conditions and limitations: The reappropriation is subject to the provisions of section 1031, chapter 296, Laws of 2022.

Section 6065

FOR THE DEPARTMENT OF COMMERCE

The reappropriations in this section are subject to the following conditions and limitations: The reappropriations are subject to the provisions of section 1037, chapter 296, Laws of 2022.

Section 6066

FOR THE DEPARTMENT OF COMMERCE

The reappropriation in this section is subject to the following conditions and limitations: The reappropriation is subject to the provisions of section 1047, chapter 296, Laws of 2022.

Section 6067

FOR THE DEPARTMENT OF COMMERCE

The reappropriations in this section are subject to the following conditions and limitations: The reappropriations are subject to the provisions of section 1032, chapter 296, Laws of 2022.

Section 6068

FOR THE DEPARTMENT OF COMMERCE

The reappropriation in this section is subject to the following conditions and limitations: The reappropriation is subject to the provisions of section 1046, chapter 296, Laws of 2022.

Section 6069

FOR THE DEPARTMENT OF COMMERCE

The reappropriations in this section are subject to the following conditions and limitations: The reappropriations are subject to the provisions of section 1033, chapter 296, Laws of 2022.

Section 6070

FOR THE DEPARTMENT OF COMMERCE

The reappropriation in this section is subject to the following conditions and limitations: The reappropriation is subject to the provisions of section 1093, chapter 332, Laws of 2021.

Section 6071

FOR THE DEPARTMENT OF COMMERCE

The reappropriation in this section is subject to the following conditions and limitations: The reappropriation is subject to the provisions of section 1034, chapter 296, Laws of 2022.

Section 6072

FOR THE DEPARTMENT OF COMMERCE

The reappropriation in this section is subject to the following conditions and limitations: The reappropriation is subject to the provisions of section 1048, chapter 296, Laws of 2022.

Section 6073

FOR THE DEPARTMENT OF COMMERCE

The reappropriation in this section is subject to the following conditions and limitations: The reappropriation is subject to the provisions of section 1035, chapter 296, Laws of 2022.

Section 6074

FOR THE DEPARTMENT OF COMMERCE

The reappropriation in this section is subject to the following conditions and limitations: The reappropriation is subject to the provisions of section 1050, chapter 296, Laws of 2022.

Section 6075

FOR THE DEPARTMENT OF COMMERCE

The reappropriations in this section are subject to the following conditions and limitations: The reappropriations are subject to the provisions of section 6013, chapter 332, Laws of 2021.

Section 6076

FOR THE DEPARTMENT OF COMMERCE

The reappropriation in this section is subject to the following conditions and limitations:

  1. The reappropriation is subject to the provisions of section 6006, chapter 3, Laws of 2015 3rd sp. sess.

  2. The reappropriation for any project for which the department has not executed a contract by December 31, 2023, shall lapse. The department shall provide a list of lapsed projects to the legislative fiscal committees no later than January 15, 2024.

Section 6077

FOR THE DEPARTMENT OF COMMERCE

The reappropriation in this section is subject to the following conditions and limitations:

  1. The reappropriation is subject to the provisions of section 1030, chapter 296, Laws of 2022.

  2. The reappropriation for any project for which the department has not executed a contract by December 31, 2023, shall lapse. The department shall provide a list of lapsed projects to the legislative fiscal committees no later than January 15, 2024.

Section 6078

FOR THE DEPARTMENT OF COMMERCE

The reappropriation in this section is subject to the following conditions and limitations: The reappropriation is subject to the provisions of section 1036, chapter 296, Laws of 2022.

Section 6079

FOR THE DEPARTMENT OF COMMERCE

The reappropriations in this section are subject to the following conditions and limitations: The reappropriations are subject to the provisions of section 1041, chapter 296, Laws of 2022.

Section 6080

FOR THE DEPARTMENT OF COMMERCE

The reappropriations in this section are subject to the following conditions and limitations: The reappropriations are subject to the provisions of section 1044, chapter 296, Laws of 2022.

Section 6081

FOR THE DEPARTMENT OF COMMERCE

The reappropriation in this section is subject to the following conditions and limitations: The reappropriation is subject to the provisions of section 1088, chapter 332, Laws of 2021.

Section 6082

FOR THE DEPARTMENT OF COMMERCE

The reappropriation in this section is subject to the following conditions and limitations: The reappropriation is subject to the provisions of section 1045, chapter 296, Laws of 2022.

Section 6083

FOR THE DEPARTMENT OF COMMERCE

The reappropriation in this section is subject to the following conditions and limitations: The reappropriation is subject to the provisions of section 1090, chapter 332, Laws of 2021.

Section 6084

FOR THE DEPARTMENT OF COMMERCE

The reappropriation in this section is subject to the following conditions and limitations: The reappropriation is subject to the provisions of section 1049, chapter 296, Laws of 2022.

Section 6085

FOR THE DEPARTMENT OF COMMERCE

The reappropriation in this section is subject to the following conditions and limitations: The reappropriation is subject to the provisions of section 1042, chapter 296, Laws of 2022.

Section 6086

FOR THE DEPARTMENT OF COMMERCE

The reappropriation in this section is subject to the following conditions and limitations: The reappropriation is subject to the provisions of section 1051, chapter 296, Laws of 2022.

Section 6087

FOR THE DEPARTMENT OF COMMERCE

The reappropriation in this section is subject to the following conditions and limitations: The reappropriation is subject to the provisions of section 1025, chapter 296, Laws of 2022.

Section 6088

FOR THE OFFICE OF FINANCIAL MANAGEMENT

The reappropriation in this section is subject to the following conditions and limitations: The reappropriation is subject to the provisions of section 1053, chapter 296, Laws of 2022.

Section 6089

FOR THE OFFICE OF FINANCIAL MANAGEMENT

The reappropriation in this section is subject to the following conditions and limitations: The reappropriation is subject to the provisions of section 1099, chapter 332, Laws of 2021.

Section 6090

FOR THE OFFICE OF FINANCIAL MANAGEMENT

The reappropriation in this section is subject to the following conditions and limitations: The reappropriation is subject to the provisions of section 1100, chapter 332, Laws of 2021.

Section 6091

FOR THE OFFICE OF FINANCIAL MANAGEMENT

The reappropriation in this section is subject to the following conditions and limitations: The reappropriation is subject to the provisions of section 1056, chapter 296, Laws of 2022.

Section 6092

FOR THE DEPARTMENT OF ENTERPRISE SERVICES

Section 6093

FOR THE DEPARTMENT OF ENTERPRISE SERVICES

Section 6094

FOR THE WASHINGTON STATE PATROL

Section 6095

FOR THE WASHINGTON STATE PATROL

Section 6096

FOR THE CRIMINAL JUSTICE TRAINING COMMISSION

Section 6097

FOR THE DEPARTMENT OF LABOR AND INDUSTRIES

The reappropriations in this section are subject to the following conditions and limitations: The reappropriations are subject to the provisions of section 2005, chapter 413, Laws of 2019.

Section 6098

FOR THE DEPARTMENT OF LABOR AND INDUSTRIES

Section 6099

FOR THE MILITARY DEPARTMENT

The reappropriation in this section is subject to the following conditions and limitations: The reappropriation is subject to the provisions of section 1027, chapter 35, Laws of 2016 sp. sess.

Section 6100

FOR THE MILITARY DEPARTMENT

The reappropriations in this section are subject to the following conditions and limitations: The reappropriations are subject to the provisions of section 1100, chapter 413, Laws of 2019.

Section 6101

FOR THE MILITARY DEPARTMENT

Section 6102

FOR THE MILITARY DEPARTMENT

Section 6103

FOR THE MILITARY DEPARTMENT

Section 6104

FOR THE MILITARY DEPARTMENT

Section 6105

FOR THE MILITARY DEPARTMENT

Section 6106

FOR THE MILITARY DEPARTMENT

Section 6107

FOR THE DEPARTMENT OF SOCIAL AND HEALTH SERVICES

The reappropriation in this section is subject to the following conditions and limitations: The reappropriation is subject to the provisions of section 2003, chapter 2, Laws of 2018.

Section 6108

FOR THE DEPARTMENT OF SOCIAL AND HEALTH SERVICES

The reappropriation in this section is subject to the following conditions and limitations: The reappropriation is subject to the provisions of section 2005, chapter 3, Laws of 2015 3rd sp. sess.

Section 6109

FOR THE DEPARTMENT OF SOCIAL AND HEALTH SERVICES

Section 6110

FOR THE DEPARTMENT OF SOCIAL AND HEALTH SERVICES

Section 6111

FOR THE DEPARTMENT OF SOCIAL AND HEALTH SERVICES

The reappropriation in this section is subject to the following conditions and limitations: The reappropriation is subject to the provisions of section 2005, chapter 356, Laws of 2020.

Section 6112

FOR THE DEPARTMENT OF SOCIAL AND HEALTH SERVICES

The reappropriation in this section is subject to the following conditions and limitations: The reappropriation is subject to the provisions of section 2004, chapter 296, Laws of 2022.

Section 6113

FOR THE DEPARTMENT OF SOCIAL AND HEALTH SERVICES

Section 6114

FOR THE DEPARTMENT OF SOCIAL AND HEALTH SERVICES

Section 6115

FOR THE DEPARTMENT OF SOCIAL AND HEALTH SERVICES

Section 6116

FOR THE DEPARTMENT OF SOCIAL AND HEALTH SERVICES

Section 6117

FOR THE DEPARTMENT OF SOCIAL AND HEALTH SERVICES

Section 6118

FOR THE DEPARTMENT OF SOCIAL AND HEALTH SERVICES

The reappropriation in this section is subject to the following conditions and limitations: The reappropriation is subject to the provisions of section 2015, chapter 2, Laws of 2018.

Section 6119

FOR THE DEPARTMENT OF SOCIAL AND HEALTH SERVICES

The reappropriation in this section is subject to the following conditions and limitations: The reappropriation is subject to the provisions of section 2016, chapter 2, Laws of 2018.

Section 6120

FOR THE DEPARTMENT OF SOCIAL AND HEALTH SERVICES

Section 6121

FOR THE DEPARTMENT OF SOCIAL AND HEALTH SERVICES

The reappropriations in this section are subject to the following conditions and limitations: The reappropriations are subject to the provisions of section 2023, chapter 332, Laws of 2021.

Section 6122

FOR THE DEPARTMENT OF SOCIAL AND HEALTH SERVICES

Section 6123

FOR THE DEPARTMENT OF SOCIAL AND HEALTH SERVICES

Section 6124

FOR THE DEPARTMENT OF SOCIAL AND HEALTH SERVICES

The reappropriations in this section are subject to the following conditions and limitations: The reappropriations are subject to the provisions of section 2007, chapter 296, Laws of 2022.

Section 6125

FOR THE DEPARTMENT OF SOCIAL AND HEALTH SERVICES

Section 6126

FOR THE DEPARTMENT OF SOCIAL AND HEALTH SERVICES

Section 6127

FOR THE DEPARTMENT OF SOCIAL AND HEALTH SERVICES

The reappropriation in this section is subject to the following conditions and limitations: The reappropriation is subject to the provisions of section 2033, chapter 413, Laws of 2019.

Section 6128

FOR THE DEPARTMENT OF SOCIAL AND HEALTH SERVICES

Section 6129

FOR THE DEPARTMENT OF SOCIAL AND HEALTH SERVICES

Section 6130

FOR THE DEPARTMENT OF SOCIAL AND HEALTH SERVICES

Section 6131

FOR THE DEPARTMENT OF SOCIAL AND HEALTH SERVICES

Section 6132

FOR THE DEPARTMENT OF SOCIAL AND HEALTH SERVICES

Section 6133

FOR THE DEPARTMENT OF SOCIAL AND HEALTH SERVICES

Section 6134

FOR THE DEPARTMENT OF SOCIAL AND HEALTH SERVICES

The reappropriation in this section is subject to the following conditions and limitations: The reappropriation is subject to the provisions of section 2046, chapter 332, Laws of 2021.

Section 6135

FOR THE DEPARTMENT OF SOCIAL AND HEALTH SERVICES

Section 6136

FOR THE DEPARTMENT OF SOCIAL AND HEALTH SERVICES

Section 6137

FOR THE DEPARTMENT OF SOCIAL AND HEALTH SERVICES

Section 6138

FOR THE DEPARTMENT OF SOCIAL AND HEALTH SERVICES

Section 6139

FOR THE DEPARTMENT OF SOCIAL AND HEALTH SERVICES

Section 6140

FOR THE DEPARTMENT OF SOCIAL AND HEALTH SERVICES

Section 6141

FOR THE DEPARTMENT OF SOCIAL AND HEALTH SERVICES

Section 6142

FOR THE DEPARTMENT OF SOCIAL AND HEALTH SERVICES

Section 6143

FOR THE DEPARTMENT OF SOCIAL AND HEALTH SERVICES

The reappropriation in this section is subject to the following conditions and limitations: The reappropriation is subject to the provisions of section 2036, chapter 332, Laws of 2021.

Section 6144

FOR THE DEPARTMENT OF SOCIAL AND HEALTH SERVICES

Section 6145

FOR THE DEPARTMENT OF SOCIAL AND HEALTH SERVICES

Section 6146

FOR THE DEPARTMENT OF SOCIAL AND HEALTH SERVICES

Section 6147

FOR THE DEPARTMENT OF SOCIAL AND HEALTH SERVICES

Section 6148

FOR THE DEPARTMENT OF SOCIAL AND HEALTH SERVICES

Section 6149

FOR THE DEPARTMENT OF SOCIAL AND HEALTH SERVICES

The reappropriation in this section is subject to the following conditions and limitations: The reappropriation is subject to the provisions of section 2060, chapter 332, Laws of 2021.

Section 6150

FOR THE DEPARTMENT OF HEALTH

Section 6151

FOR THE DEPARTMENT OF HEALTH

The reappropriation in this section is subject to the following conditions and limitations: The reappropriation is subject to the provisions of section 2064, chapter 332, Laws of 2021.

Section 6152

FOR THE DEPARTMENT OF HEALTH

The reappropriation in this section is subject to the following conditions and limitations: The reappropriation is subject to the provisions of section 2034, chapter 2, Laws of 2018.

Section 6153

FOR THE DEPARTMENT OF HEALTH

The reappropriation in this section is subject to the following conditions and limitations: The reappropriation is subject to the provisions of section 2035, chapter 2, Laws of 2018.

Section 6154

FOR THE DEPARTMENT OF HEALTH

Section 6155

FOR THE DEPARTMENT OF HEALTH

The reappropriation in this section is subject to the following conditions and limitations: The reappropriation is subject to the provisions of section 2068, chapter 413, Laws of 2019.

Section 6156

FOR THE DEPARTMENT OF HEALTH

The reappropriation in this section is subject to the following conditions and limitations: The reappropriation is subject to the provisions of section 2020, chapter 296, Laws of 2022.

Section 6157

FOR THE DEPARTMENT OF HEALTH

Section 6158

FOR THE DEPARTMENT OF HEALTH

The reappropriation in this section is subject to the following conditions and limitations: The reappropriation is subject to the provisions of section 2023, chapter 296, Laws of 2022.

Section 6159

FOR THE DEPARTMENT OF HEALTH

The reappropriation in this section is subject to the following conditions and limitations: The reappropriation is subject to the provisions of section 2024, chapter 296, Laws of 2022.

Section 6160

FOR THE DEPARTMENT OF HEALTH

Section 6161

FOR THE DEPARTMENT OF HEALTH

Section 6162

FOR THE DEPARTMENT OF HEALTH

Section 6163

FOR THE DEPARTMENT OF HEALTH

Section 6164

FOR THE DEPARTMENT OF VETERANS AFFAIRS

Section 6165

FOR THE DEPARTMENT OF VETERANS AFFAIRS

Section 6166

FOR THE DEPARTMENT OF VETERANS AFFAIRS

Section 6167

FOR THE DEPARTMENT OF VETERANS AFFAIRS

Section 6168

FOR THE DEPARTMENT OF CHILDREN, YOUTH, AND FAMILIES

The reappropriation in this section is subject to the following conditions and limitations: The reappropriation is subject to the provisions of section 2078, chapter 413, Laws of 2019.

Section 6169

FOR THE DEPARTMENT OF CHILDREN, YOUTH, AND FAMILIES

The reappropriation in this section is subject to the following conditions and limitations: The reappropriation is subject to the provisions of section 2013, chapter 356, Laws of 2020.

Section 6170

FOR THE DEPARTMENT OF CHILDREN, YOUTH, AND FAMILIES

Section 6171

FOR THE DEPARTMENT OF CHILDREN, YOUTH, AND FAMILIES

Section 6172

FOR THE DEPARTMENT OF CHILDREN, YOUTH, AND FAMILIES

Section 6173

FOR THE DEPARTMENT OF CORRECTIONS

Section 6174

FOR THE DEPARTMENT OF CORRECTIONS

Section 6175

FOR THE DEPARTMENT OF CORRECTIONS

Section 6176

FOR THE DEPARTMENT OF CORRECTIONS

Section 6177

FOR THE DEPARTMENT OF CORRECTIONS

Section 6178

FOR THE DEPARTMENT OF CORRECTIONS

Section 6179

FOR THE DEPARTMENT OF CORRECTIONS

Section 6180

FOR THE DEPARTMENT OF CORRECTIONS

Section 6181

FOR THE DEPARTMENT OF CORRECTIONS

Section 6182

FOR THE DEPARTMENT OF CORRECTIONS

Section 6183

FOR THE STATE SCHOOL FOR THE BLIND

Section 6184

FOR THE STATE SCHOOL FOR THE BLIND

Section 6185

FOR THE STATE SCHOOL FOR THE BLIND

Section 6186

FOR THE WASHINGTON STATE CENTER FOR CHILDHOOD DEAFNESS AND HEARING LOSS

Section 6187

FOR THE DEPARTMENT OF ARCHAEOLOGY AND HISTORIC PRESERVATION

The reappropriations in this section are subject to the following conditions and limitations: The reappropriations are subject to the provisions of section 1111, chapter 413, Laws of 2019.

Section 6188

FOR THE DEPARTMENT OF ARCHAEOLOGY AND HISTORIC PRESERVATION

The reappropriation in this section is subject to the following conditions and limitations: The reappropriation is subject to the provisions of section 1112, chapter 413, Laws of 2019.

Section 6189

FOR THE DEPARTMENT OF ARCHAEOLOGY AND HISTORIC PRESERVATION

Section 6190

FOR THE DEPARTMENT OF ARCHAEOLOGY AND HISTORIC PRESERVATION

The reappropriation in this section is subject to the following conditions and limitations: The reappropriation is subject to the provisions of section 1115, chapter 413, Laws of 2019.

Section 6191

FOR THE DEPARTMENT OF ARCHAEOLOGY AND HISTORIC PRESERVATION

Section 6192

FOR THE DEPARTMENT OF ARCHAEOLOGY AND HISTORIC PRESERVATION

The reappropriation in this section is subject to the following conditions and limitations: The reappropriation is subject to the provisions of section 1144, chapter 332, Laws of 2021.

Section 6193

FOR THE DEPARTMENT OF ARCHAEOLOGY AND HISTORIC PRESERVATION

Section 6194

FOR THE DEPARTMENT OF ARCHAEOLOGY AND HISTORIC PRESERVATION

The reappropriation in this section is subject to the following conditions and limitations: The reappropriation is subject to the provisions of section 1146, chapter 332, Laws of 2021.

Section 6195

FOR THE UNIVERSITY OF WASHINGTON

The reappropriation in this section is subject to the following conditions and limitations: The reappropriation is subject to the provisions of section 5037, chapter 413, Laws of 2019.

Section 6196

FOR THE UNIVERSITY OF WASHINGTON

Section 6197

FOR THE UNIVERSITY OF WASHINGTON

The reappropriations in this section are subject to the following conditions and limitations: The reappropriations are subject to the provisions of section 5014, chapter 296, Laws of 2022.

Section 6198

FOR THE UNIVERSITY OF WASHINGTON

Section 6199

FOR THE UNIVERSITY OF WASHINGTON

Section 6200

FOR THE UNIVERSITY OF WASHINGTON

Section 6201

FOR WASHINGTON STATE UNIVERSITY

Section 6202

FOR WASHINGTON STATE UNIVERSITY

Section 6203

FOR WASHINGTON STATE UNIVERSITY

Section 6204

FOR WASHINGTON STATE UNIVERSITY

Section 6205

FOR WASHINGTON STATE UNIVERSITY

Section 6206

FOR WASHINGTON STATE UNIVERSITY

Section 6207

FOR EASTERN WASHINGTON UNIVERSITY

Section 6208

FOR EASTERN WASHINGTON UNIVERSITY

Section 6209

FOR EASTERN WASHINGTON UNIVERSITY

Section 6210

FOR EASTERN WASHINGTON UNIVERSITY

Section 6211

FOR EASTERN WASHINGTON UNIVERSITY

Section 6212

FOR CENTRAL WASHINGTON UNIVERSITY

Section 6213

FOR CENTRAL WASHINGTON UNIVERSITY

Section 6214

FOR CENTRAL WASHINGTON UNIVERSITY

Section 6215

FOR CENTRAL WASHINGTON UNIVERSITY

Section 6216

FOR CENTRAL WASHINGTON UNIVERSITY

Section 6217

FOR CENTRAL WASHINGTON UNIVERSITY

Section 6218

FOR THE EVERGREEN STATE COLLEGE

Section 6219

FOR THE EVERGREEN STATE COLLEGE

Section 6220

FOR THE EVERGREEN STATE COLLEGE

Section 6221

FOR THE EVERGREEN STATE COLLEGE

Section 6222

FOR WESTERN WASHINGTON UNIVERSITY

The reappropriations in this section are subject to the following conditions and limitations: The reappropriations are subject to the provisions of section 5028, chapter 296, Laws of 2022.

Section 6223

FOR WESTERN WASHINGTON UNIVERSITY

Section 6224

FOR WESTERN WASHINGTON UNIVERSITY

The reappropriations in this section are subject to the following conditions and limitations: The reappropriations are subject to the provisions of section 5105, chapter 332, Laws of 2021.

Section 6225

FOR WESTERN WASHINGTON UNIVERSITY

Section 6226

FOR WESTERN WASHINGTON UNIVERSITY

Section 6227

FOR THE WASHINGTON STATE ARTS COMMISSION

Section 6228

FOR THE WASHINGTON STATE HISTORICAL SOCIETY

The reappropriation in this section is subject to the following conditions and limitations: The reappropriation is subject to the provisions of section 5054, chapter 2, Laws of 2018.

Section 6229

FOR THE WASHINGTON STATE HISTORICAL SOCIETY

The reappropriation in this section is subject to the following conditions and limitations: The reappropriation is subject to the provisions of section 5020, chapter 356, Laws of 2020.

Section 6230

FOR THE WASHINGTON STATE HISTORICAL SOCIETY

Section 6231

FOR THE WASHINGTON STATE HISTORICAL SOCIETY

Section 6232

FOR THE WASHINGTON STATE HISTORICAL SOCIETY

The reappropriation in this section is subject to the following conditions and limitations: The reappropriation is subject to the provisions of section 5022, chapter 356, Laws of 2020.

Section 6233

FOR THE EASTERN WASHINGTON STATE HISTORICAL SOCIETY

Section 6234

FOR THE EASTERN WASHINGTON STATE HISTORICAL SOCIETY

Section 6235

FOR THE EASTERN WASHINGTON STATE HISTORICAL SOCIETY

Section 6236

FOR THE EASTERN WASHINGTON STATE HISTORICAL SOCIETY

Section 6237

FOR THE DEPARTMENT OF ECOLOGY

Section 6238

FOR THE DEPARTMENT OF ECOLOGY

Section 6239

FOR THE DEPARTMENT OF ECOLOGY

Section 6240

FOR THE DEPARTMENT OF ECOLOGY

Section 6241

FOR THE DEPARTMENT OF ECOLOGY

The reappropriation in this section is subject to the following conditions and limitations: The reappropriation is subject to the provisions of section 3030, chapter 49, Laws of 2011 1st sp. sess.

Section 6242

FOR THE DEPARTMENT OF ECOLOGY

Section 6243

FOR THE DEPARTMENT OF ECOLOGY

Section 6244

FOR THE DEPARTMENT OF ECOLOGY

Section 6245

FOR THE DEPARTMENT OF ECOLOGY

Section 6246

FOR THE DEPARTMENT OF ECOLOGY

The reappropriation in this section is subject to the following conditions and limitations: The reappropriation is subject to the provisions of section 3082, chapter 19, Laws of 2013 2nd sp. sess.

Section 6247

FOR THE DEPARTMENT OF ECOLOGY

The reappropriation in this section is subject to the following conditions and limitations: The reappropriation is subject to the provisions of section 3001, chapter 296, Laws of 2022.

Section 6248

FOR THE DEPARTMENT OF ECOLOGY

Section 6249

FOR THE DEPARTMENT OF ECOLOGY

Section 6250

FOR THE DEPARTMENT OF ECOLOGY

The reappropriation in this section is subject to the following conditions and limitations: The reappropriation is subject to the provisions of section 3011, chapter 35, Laws of 2016 sp. sess.

Section 6251

FOR THE DEPARTMENT OF ECOLOGY

Section 6252

FOR THE DEPARTMENT OF ECOLOGY

Section 6253

FOR THE DEPARTMENT OF ECOLOGY

The reappropriation in this section is subject to the following conditions and limitations: The reappropriation is subject to the provisions of section 3013, chapter 35, Laws of 2016 sp. sess.

Section 6254

FOR THE DEPARTMENT OF ECOLOGY

The reappropriation in this section is subject to the following conditions and limitations: The reappropriation is subject to the provisions of section 3068, chapter 3, Laws of 2015 3rd sp. sess.

Section 6255

FOR THE DEPARTMENT OF ECOLOGY

Section 6256

FOR THE DEPARTMENT OF ECOLOGY

The reappropriation in this section is subject to the following conditions and limitations: The reappropriation is subject to the provisions of section 3031, chapter 332, Laws of 2021.

Section 6257

FOR THE DEPARTMENT OF ECOLOGY

Section 6258

FOR THE DEPARTMENT OF ECOLOGY

Section 6259

FOR THE DEPARTMENT OF ECOLOGY

Section 6260

FOR THE DEPARTMENT OF ECOLOGY

Section 6261

FOR THE DEPARTMENT OF ECOLOGY

The reappropriation in this section is subject to the following conditions and limitations: The reappropriation is subject to the provisions of section 3009, chapter 2, Laws of 2018.

Section 6262

FOR THE DEPARTMENT OF ECOLOGY

The reappropriation in this section is subject to the following conditions and limitations: The reappropriation is subject to the provisions of section 3001, chapter 298, Laws of 2018.

Section 6263

FOR THE DEPARTMENT OF ECOLOGY

Section 6264

FOR THE DEPARTMENT OF ECOLOGY

The reappropriation in this section is subject to the following conditions and limitations: The reappropriation is subject to the provisions of section 3040, chapter 332, Laws of 2021.

Section 6265

FOR THE DEPARTMENT OF ECOLOGY

The reappropriations in this section are subject to the following conditions and limitations: The reappropriations are subject to the provisions of section 3006, chapter 298, Laws of 2018.

Section 6266

FOR THE DEPARTMENT OF ECOLOGY

The reappropriation in this section is subject to the following conditions and limitations: The reappropriation is subject to the provisions of section 3017, chapter 2, Laws of 2018.

Section 6267

FOR THE DEPARTMENT OF ECOLOGY

The reappropriation in this section is subject to the following conditions and limitations: The reappropriation is subject to the provisions of section 3007, chapter 298, Laws of 2018.

Section 6268

FOR THE DEPARTMENT OF ECOLOGY

Section 6269

FOR THE DEPARTMENT OF ECOLOGY

Section 6270

FOR THE DEPARTMENT OF ECOLOGY

The reappropriations in this section are subject to the following conditions and limitations: The reappropriations are subject to the provisions of section 3049, chapter 332, Laws of 2021.

Section 6271

FOR THE DEPARTMENT OF ECOLOGY

Section 6272

FOR THE DEPARTMENT OF ECOLOGY

The reappropriation in this section is subject to the following conditions and limitations: The reappropriation is subject to the provisions of section 3008, chapter 298, Laws of 2018.

Section 6273

FOR THE DEPARTMENT OF ECOLOGY

The reappropriation in this section is subject to the following conditions and limitations: The reappropriation is subject to the provisions of section 3019, chapter 356, Laws of 2020.

Section 6274

FOR THE DEPARTMENT OF ECOLOGY

The reappropriation in this section is subject to the following conditions and limitations: The reappropriation is subject to the provisions of section 3074, chapter 413, Laws of 2019.

Section 6275

FOR THE DEPARTMENT OF ECOLOGY

Section 6276

FOR THE DEPARTMENT OF ECOLOGY

Section 6277

FOR THE DEPARTMENT OF ECOLOGY

Section 6278

FOR THE DEPARTMENT OF ECOLOGY

The reappropriation in this section is subject to the following conditions and limitations: The reappropriation is subject to the provisions of section 3074, chapter 413, Laws of 2019.

Section 6279

FOR THE DEPARTMENT OF ECOLOGY

Section 6280

FOR THE DEPARTMENT OF ECOLOGY

Section 6281

FOR THE DEPARTMENT OF ECOLOGY

Section 6282

FOR THE DEPARTMENT OF ECOLOGY

The reappropriation in this section is subject to the following conditions and limitations: The reappropriation is subject to the provisions of section 3080, chapter 413, Laws of 2019.

Section 6283

FOR THE DEPARTMENT OF ECOLOGY

The reappropriation in this section is subject to the following conditions and limitations: The reappropriation is subject to the provisions of section 3020, chapter 356, Laws of 2020.

Section 6284

FOR THE DEPARTMENT OF ECOLOGY

Section 6285

FOR THE DEPARTMENT OF ECOLOGY

The reappropriation in this section is subject to the following conditions and limitations: The reappropriation is subject to the provisions of section 3085, chapter 413, Laws of 2019.

Section 6286

FOR THE DEPARTMENT OF ECOLOGY

The reappropriations in this section are subject to the following conditions and limitations: The reappropriations are subject to the provisions of section 3087, chapter 413, Laws of 2019.

Section 6287

FOR THE DEPARTMENT OF ECOLOGY

Section 6288

FOR THE DEPARTMENT OF ECOLOGY

The reappropriation in this section is subject to the following conditions and limitations: The reappropriation is subject to the provisions of section 3072, chapter 332, Laws of 2021.

Section 6289

FOR THE DEPARTMENT OF ECOLOGY

Section 6290

FOR THE DEPARTMENT OF ECOLOGY

The reappropriation in this section is subject to the following conditions and limitations: The reappropriation is subject to the provisions of section 6032, chapter 332, Laws of 2021.

Section 6291

FOR THE DEPARTMENT OF ECOLOGY

The reappropriation in this section is subject to the following conditions and limitations: The reappropriation is subject to the provisions of section 3023, chapter 356, Laws of 2020.

Section 6292

FOR THE DEPARTMENT OF ECOLOGY

Section 6293

FOR THE DEPARTMENT OF ECOLOGY

Section 6294

FOR THE DEPARTMENT OF ECOLOGY

Section 6295

FOR THE DEPARTMENT OF ECOLOGY

Section 6296

FOR THE DEPARTMENT OF ECOLOGY

Section 6297

FOR THE DEPARTMENT OF ECOLOGY

The reappropriation in this section is subject to the following conditions and limitations: The reappropriation is subject to the provisions of section 3082, chapter 332, Laws of 2021.

Section 6298

FOR THE DEPARTMENT OF ECOLOGY

Section 6299

FOR THE DEPARTMENT OF ECOLOGY

The reappropriations in this section are subject to the following conditions and limitations: The reappropriations are subject to the provisions of section 3003, chapter 296, Laws of 2022.

Section 6300

FOR THE DEPARTMENT OF ECOLOGY

Section 6301

FOR THE DEPARTMENT OF ECOLOGY

Section 6302

FOR THE DEPARTMENT OF ECOLOGY

Section 6303

FOR THE DEPARTMENT OF ECOLOGY

The reappropriation in this section is subject to the following conditions and limitations: The reappropriation is subject to the provisions of section 3089, chapter 332, Laws of 2021.

Section 6304

FOR THE DEPARTMENT OF ECOLOGY

Section 6305

FOR THE DEPARTMENT OF ECOLOGY

The reappropriation in this section is subject to the following conditions and limitations: The reappropriation is subject to the provisions of section 3091, chapter 332, Laws of 2021.

Section 6306

FOR THE DEPARTMENT OF ECOLOGY

Section 6307

FOR THE DEPARTMENT OF ECOLOGY

Section 6308

FOR THE DEPARTMENT OF ECOLOGY

The reappropriation in this section is subject to the following conditions and limitations: The reappropriation is subject to the provisions of section 3094, chapter 332, Laws of 2021.

Section 6309

FOR THE DEPARTMENT OF ECOLOGY

Section 6310

FOR THE DEPARTMENT OF ECOLOGY

The reappropriation in this section is subject to the following conditions and limitations: The reappropriation is subject to the provisions of section 3096, chapter 332, Laws of 2021.

Section 6311

FOR THE DEPARTMENT OF ECOLOGY

Section 6312

FOR THE DEPARTMENT OF ECOLOGY

Section 6313

FOR THE DEPARTMENT OF ECOLOGY

Section 6314

FOR THE DEPARTMENT OF ECOLOGY

Section 6315

FOR THE DEPARTMENT OF ECOLOGY

The reappropriation in this section is subject to the following conditions and limitations: The reappropriation is subject to the provisions of section 3101, chapter 332, Laws of 2021.

Section 6316

FOR THE DEPARTMENT OF ECOLOGY

Section 6317

FOR THE DEPARTMENT OF ECOLOGY

The reappropriations in this section are subject to the following conditions and limitations: The reappropriations are subject to the provisions of section 3103, chapter 332, Laws of 2021.

Section 6318

FOR THE DEPARTMENT OF ECOLOGY

Section 6319

FOR THE DEPARTMENT OF ECOLOGY

Section 6320

FOR THE DEPARTMENT OF ECOLOGY

Section 6321

FOR THE DEPARTMENT OF ECOLOGY

Section 6322

FOR THE DEPARTMENT OF ECOLOGY

The reappropriation in this section is subject to the following conditions and limitations: The reappropriation is subject to the provisions of section 3008, chapter 296, Laws of 2022.

Section 6323

FOR THE DEPARTMENT OF ECOLOGY

Section 6324

FOR THE DEPARTMENT OF ECOLOGY

The reappropriation in this section is subject to the following conditions and limitations: The reappropriation is subject to the provisions of section 3012, chapter 298, Laws of 2018.

Section 6325

FOR THE DEPARTMENT OF ECOLOGY

The reappropriation in this section is subject to the following conditions and limitations: The reappropriation is subject to the provisions of section 3108, chapter 332, Laws of 2021.

Section 6326

FOR THE DEPARTMENT OF ECOLOGY

The reappropriations in this section are subject to the following conditions and limitations: The reappropriations are subject to the provisions of section 7041 of this act.

Section 6327

FOR THE DEPARTMENT OF ECOLOGY

The reappropriation in this section is subject to the following conditions and limitations: The reappropriation is subject to the provisions of section 3028, chapter 2, Laws of 2018.

Section 6328

FOR THE DEPARTMENT OF ECOLOGY

Section 6329

FOR THE DEPARTMENT OF ECOLOGY

Section 6330

FOR THE DEPARTMENT OF ECOLOGY

The reappropriation in this section is subject to the following conditions and limitations: The reappropriation is subject to the provisions of section 3011, chapter 296, Laws of 2022.

Section 6331

FOR THE POLLUTION LIABILITY INSURANCE PROGRAM

The reappropriation in this section is subject to the following conditions and limitations: The reappropriation is subject to the provisions of section 3085, chapter 3, Laws of 2015 3rd sp. sess.

Section 6332

FOR THE POLLUTION LIABILITY INSURANCE PROGRAM

Section 6333

FOR THE POLLUTION LIABILITY INSURANCE PROGRAM

Section 6334

FOR THE POLLUTION LIABILITY INSURANCE PROGRAM

Section 6335

FOR THE POLLUTION LIABILITY INSURANCE PROGRAM

Section 6336

FOR THE POLLUTION LIABILITY INSURANCE PROGRAM

Section 6337

FOR THE STATE PARKS AND RECREATION COMMISSION

Section 6338

FOR THE STATE PARKS AND RECREATION COMMISSION

Section 6339

FOR THE STATE PARKS AND RECREATION COMMISSION

Section 6340

FOR THE STATE PARKS AND RECREATION COMMISSION

Section 6341

FOR THE STATE PARKS AND RECREATION COMMISSION

Section 6342

FOR THE STATE PARKS AND RECREATION COMMISSION

The reappropriation in this section is subject to the following conditions and limitations: The reappropriation is subject to the provisions of section 3047, chapter 2, Laws of 2018.

Section 6343

FOR THE STATE PARKS AND RECREATION COMMISSION

Section 6344

FOR THE STATE PARKS AND RECREATION COMMISSION

Section 6345

FOR THE STATE PARKS AND RECREATION COMMISSION

Section 6346

FOR THE STATE PARKS AND RECREATION COMMISSION

Section 6347

FOR THE STATE PARKS AND RECREATION COMMISSION

Section 6348

FOR THE STATE PARKS AND RECREATION COMMISSION

Section 6349

FOR THE STATE PARKS AND RECREATION COMMISSION

Section 6350

FOR THE STATE PARKS AND RECREATION COMMISSION

Section 6351

FOR THE STATE PARKS AND RECREATION COMMISSION

Section 6352

FOR THE STATE PARKS AND RECREATION COMMISSION

Section 6353

FOR THE STATE PARKS AND RECREATION COMMISSION

Section 6354

FOR THE STATE PARKS AND RECREATION COMMISSION

Section 6355

FOR THE STATE PARKS AND RECREATION COMMISSION

The reappropriation in this section is subject to the following conditions and limitations: The reappropriation is subject to the provisions of section 3023, chapter 296, Laws of 2022.

Section 6356

FOR THE STATE PARKS AND RECREATION COMMISSION

The reappropriation in this section is subject to the following conditions and limitations: The reappropriation is subject to the provisions of section 3162, chapter 413, Laws of 2019.

Section 6357

FOR THE STATE PARKS AND RECREATION COMMISSION

The reappropriation in this section is subject to the following conditions and limitations: The reappropriation is subject to the provisions of section 3025, chapter 296, Laws of 2022.

Section 6358

FOR THE RECREATION AND CONSERVATION FUNDING BOARD

The reappropriations in this section are subject to the following conditions and limitations: The reappropriations are subject to the provisions of section 3029, chapter 296, Laws of 2022.

Section 6359

FOR THE RECREATION AND CONSERVATION FUNDING BOARD

The reappropriation in this section is subject to the following conditions and limitations: The reappropriation is subject to the provisions of section 3164, chapter 3, Laws of 2015 3rd sp. sess.

Section 6360

FOR THE RECREATION AND CONSERVATION FUNDING BOARD

Section 6361

FOR THE RECREATION AND CONSERVATION FUNDING BOARD

Section 6362

FOR THE RECREATION AND CONSERVATION FUNDING BOARD

The reappropriations in this section are subject to the following conditions and limitations: The reappropriations are subject to the provisions of section 3070, chapter 2, Laws of 2018.

Section 6363

FOR THE RECREATION AND CONSERVATION FUNDING BOARD

The reappropriations in this section are subject to the following conditions and limitations: The reappropriations are subject to the provisions of section 3034, chapter 296, Laws of 2022.

Section 6364

FOR THE RECREATION AND CONSERVATION FUNDING BOARD

The reappropriation in this section is subject to the following conditions and limitations: The reappropriation is subject to the provisions of section 3072, chapter 2, Laws of 2018.

Section 6365

FOR THE RECREATION AND CONSERVATION FUNDING BOARD

Section 6366

FOR THE RECREATION AND CONSERVATION FUNDING BOARD

Section 6367

FOR THE RECREATION AND CONSERVATION FUNDING BOARD

The reappropriations in this section are subject to the following conditions and limitations: The reappropriations are subject to the provisions of section 3037, chapter 296, Laws of 2022.

Section 6368

FOR THE RECREATION AND CONSERVATION FUNDING BOARD

Section 6369

FOR THE RECREATION AND CONSERVATION FUNDING BOARD

Section 6370

FOR THE RECREATION AND CONSERVATION FUNDING BOARD

Section 6371

FOR THE RECREATION AND CONSERVATION FUNDING BOARD

The reappropriation in this section is subject to the following conditions and limitations: The reappropriation is subject to the provisions of section 3082, chapter 2, Laws of 2018.

Section 6372

FOR THE RECREATION AND CONSERVATION FUNDING BOARD

Section 6373

FOR THE RECREATION AND CONSERVATION FUNDING BOARD

The reappropriations in this section are subject to the following conditions and limitations: The reappropriations are subject to the provisions of section 3200, chapter 413, Laws of 2019.

Section 6374

FOR THE RECREATION AND CONSERVATION FUNDING BOARD

The reappropriations in this section are subject to the following conditions and limitations: The reappropriations are subject to the provisions of section 3201, chapter 413, Laws of 2019.

Section 6375

FOR THE RECREATION AND CONSERVATION FUNDING BOARD

Section 6376

FOR THE RECREATION AND CONSERVATION FUNDING BOARD

Section 6377

FOR THE RECREATION AND CONSERVATION FUNDING BOARD

The reappropriation in this section is subject to the following conditions and limitations: The reappropriation is subject to the provisions of section 3041, chapter 296, Laws of 2022.

Section 6378

FOR THE RECREATION AND CONSERVATION FUNDING BOARD

The reappropriation in this section is subject to the following conditions and limitations: The reappropriation is subject to the provisions of section 3202, chapter 332, Laws of 2021.

Section 6379

FOR THE RECREATION AND CONSERVATION FUNDING BOARD

Section 6380

FOR THE RECREATION AND CONSERVATION FUNDING BOARD

Section 6381

FOR THE RECREATION AND CONSERVATION FUNDING BOARD

The reappropriation in this section is subject to the following conditions and limitations: The reappropriation is subject to the provisions of section 3208, chapter 413, Laws of 2019.

Section 6382

FOR THE RECREATION AND CONSERVATION FUNDING BOARD

The reappropriation in this section is subject to the following conditions and limitations: The reappropriation is subject to the provisions of section 3209, chapter 413, Laws of 2019.

Section 6383

FOR THE RECREATION AND CONSERVATION FUNDING BOARD

Section 6384

FOR THE RECREATION AND CONSERVATION FUNDING BOARD

Section 6385

FOR THE RECREATION AND CONSERVATION FUNDING BOARD

Section 6386

FOR THE RECREATION AND CONSERVATION FUNDING BOARD

Section 6387

FOR THE RECREATION AND CONSERVATION FUNDING BOARD

Section 6388

FOR THE RECREATION AND CONSERVATION FUNDING BOARD

The reappropriations in this section are subject to the following conditions and limitations: The reappropriations are subject to the provisions of section 3213, chapter 332, Laws of 2021.

Section 6389

FOR THE RECREATION AND CONSERVATION FUNDING BOARD

The reappropriations in this section are subject to the following conditions and limitations: The reappropriations are subject to the provisions of section 3042, chapter 296, Laws of 2022.

Section 6390

FOR THE RECREATION AND CONSERVATION FUNDING BOARD

Section 6391

FOR THE RECREATION AND CONSERVATION FUNDING BOARD

Section 6392

FOR THE RECREATION AND CONSERVATION FUNDING BOARD

The reappropriation in this section is subject to the following conditions and limitations: The reappropriation is subject to the provisions of section 3217, chapter 332, Laws of 2021.

Section 6393

FOR THE RECREATION AND CONSERVATION FUNDING BOARD

The reappropriations in this section are subject to the following conditions and limitations: The reappropriations are subject to the provisions of section 3048, chapter 296, Laws of 2022.

Section 6394

FOR THE RECREATION AND CONSERVATION FUNDING BOARD

Section 6395

FOR THE RECREATION AND CONSERVATION FUNDING BOARD

The reappropriation in this section is subject to the following conditions and limitations: The reappropriation is subject to the provisions of section 3220, chapter 332, Laws of 2021.

Section 6396

FOR THE RECREATION AND CONSERVATION FUNDING BOARD

The reappropriation in this section is subject to the following conditions and limitations: The reappropriation is subject to the provisions of section 3043, chapter 296, Laws of 2022.

Section 6397

FOR THE RECREATION AND CONSERVATION FUNDING BOARD

Section 6398

FOR THE RECREATION AND CONSERVATION FUNDING BOARD

Section 6399

FOR THE RECREATION AND CONSERVATION FUNDING BOARD

Section 6400

FOR THE RECREATION AND CONSERVATION FUNDING BOARD

Section 6401

FOR THE RECREATION AND CONSERVATION FUNDING BOARD

The reappropriation in this section is subject to the following conditions and limitations: The reappropriation is subject to the provisions of section 3226, chapter 332, Laws of 2021.

Section 6402

FOR THE RECREATION AND CONSERVATION FUNDING BOARD

The reappropriation in this section is subject to the following conditions and limitations: The reappropriation is subject to the provisions of section 3227, chapter 332, Laws of 2021.

Section 6403

FOR THE RECREATION AND CONSERVATION FUNDING BOARD

The reappropriation in this section is subject to the following conditions and limitations: The reappropriation is subject to the provisions of section 3203, chapter 332, Laws of 2021.

Section 6404

FOR THE RECREATION AND CONSERVATION FUNDING BOARD

Section 6405

FOR THE RECREATION AND CONSERVATION FUNDING BOARD

Section 6406

FOR THE RECREATION AND CONSERVATION FUNDING BOARD

Section 6407

FOR THE RECREATION AND CONSERVATION FUNDING BOARD

Section 6408

FOR THE RECREATION AND CONSERVATION FUNDING BOARD

The reappropriation in this section is subject to the following conditions and limitations: The reappropriation is subject to the provisions of section 3177, chapter 3, Laws of 2015 3rd sp. sess.

Section 6409

FOR THE RECREATION AND CONSERVATION FUNDING BOARD

The reappropriation in this section is subject to the following conditions and limitations: The reappropriation is subject to the provisions of section 3046, chapter 296, Laws of 2022.

Section 6410

FOR THE RECREATION AND CONSERVATION FUNDING BOARD

The reappropriations in this section are subject to the following conditions and limitations: The reappropriations are subject to the provisions of section 3049, chapter 356, Laws of 2020.

Section 6411

FOR THE RECREATION AND CONSERVATION FUNDING BOARD

The reappropriation in this section is subject to the following conditions and limitations: The reappropriation is subject to the provisions of section 3234, chapter 332, Laws of 2021.

Section 6412

FOR THE STATE CONSERVATION COMMISSION

The reappropriation in this section is subject to the following conditions and limitations: The reappropriation is subject to the provisions of section 3033, chapter 35, Laws of 2016 sp. sess.

Section 6413

FOR THE STATE CONSERVATION COMMISSION

The reappropriation in this section is subject to the following conditions and limitations: The reappropriation is subject to the provisions of section 3051, chapter 356, Laws of 2020.

Section 6414

FOR THE STATE CONSERVATION COMMISSION

The reappropriation in this section is subject to the following conditions and limitations: The reappropriation is subject to the provisions of section 3224, chapter 413, Laws of 2019.

Section 6415

FOR THE STATE CONSERVATION COMMISSION

The reappropriation in this section is subject to the following conditions and limitations: The reappropriation is subject to the provisions of section 3241, chapter 332, Laws of 2021.

Section 6416

FOR THE STATE CONSERVATION COMMISSION

Section 6417

FOR THE STATE CONSERVATION COMMISSION

Section 6418

FOR THE STATE CONSERVATION COMMISSION

The reappropriation in this section is subject to the following conditions and limitations: The reappropriation is subject to the provisions of section 3244, chapter 332, Laws of 2021.

Section 6419

FOR THE STATE CONSERVATION COMMISSION

Section 6420

FOR THE STATE CONSERVATION COMMISSION

The reappropriation in this section is subject to the following conditions and limitations: The reappropriation is subject to the provisions of section 3246, chapter 332, Laws of 2021.

Section 6421

FOR THE STATE CONSERVATION COMMISSION

The reappropriation in this section is subject to the following conditions and limitations: The reappropriation is subject to the provisions of section 3050, chapter 296, Laws of 2022.

Section 6422

FOR THE STATE CONSERVATION COMMISSION

Section 6423

FOR THE STATE CONSERVATION COMMISSION

Section 6424

FOR THE STATE CONSERVATION COMMISSION

Section 6425

FOR THE STATE CONSERVATION COMMISSION

The reappropriation in this section is subject to the following conditions and limitations: The reappropriation is subject to the provisions of section 3090, chapter 2, Laws of 2018.

Section 6426

FOR THE STATE CONSERVATION COMMISSION

Section 6427

FOR THE DEPARTMENT OF FISH AND WILDLIFE

Section 6428

FOR THE DEPARTMENT OF FISH AND WILDLIFE

Section 6429

FOR THE DEPARTMENT OF FISH AND WILDLIFE

The reappropriations in this section are subject to the following conditions and limitations: The reappropriations are subject to the provisions of section 3196, chapter 3, Laws of 2015 3rd sp. sess.

Section 6430

FOR THE DEPARTMENT OF FISH AND WILDLIFE

Section 6431

FOR THE DEPARTMENT OF FISH AND WILDLIFE

The reappropriation in this section is subject to the following conditions and limitations: The reappropriation is subject to the provisions of section 3271, chapter 332, Laws of 2021.

Section 6432

FOR THE DEPARTMENT OF FISH AND WILDLIFE

Section 6433

FOR THE DEPARTMENT OF FISH AND WILDLIFE

Section 6434

FOR THE DEPARTMENT OF FISH AND WILDLIFE

Section 6435

FOR THE DEPARTMENT OF FISH AND WILDLIFE

Section 6436

FOR THE DEPARTMENT OF FISH AND WILDLIFE

Section 6437

FOR THE DEPARTMENT OF FISH AND WILDLIFE

Section 6438

FOR THE DEPARTMENT OF FISH AND WILDLIFE

Section 6439

FOR THE DEPARTMENT OF FISH AND WILDLIFE

Section 6440

FOR THE DEPARTMENT OF FISH AND WILDLIFE

Section 6441

FOR THE DEPARTMENT OF FISH AND WILDLIFE

Section 6442

FOR THE DEPARTMENT OF FISH AND WILDLIFE

Section 6443

FOR THE DEPARTMENT OF FISH AND WILDLIFE

Section 6444

FOR THE DEPARTMENT OF FISH AND WILDLIFE

Section 6445

FOR THE DEPARTMENT OF FISH AND WILDLIFE

Section 6446

FOR THE DEPARTMENT OF FISH AND WILDLIFE

Section 6447

FOR THE DEPARTMENT OF FISH AND WILDLIFE

Section 6448

FOR THE DEPARTMENT OF FISH AND WILDLIFE

Section 6449

FOR THE DEPARTMENT OF FISH AND WILDLIFE

Section 6450

FOR THE DEPARTMENT OF FISH AND WILDLIFE

The reappropriation in this section is subject to the following conditions and limitations: The reappropriation is subject to the provisions of section 3062, chapter 296, Laws of 2022.

Section 6451

FOR THE DEPARTMENT OF FISH AND WILDLIFE

The reappropriation in this section is subject to the following conditions and limitations: The reappropriation is subject to the provisions of section 3061, chapter 296, Laws of 2022.

Section 6452

FOR THE DEPARTMENT OF FISH AND WILDLIFE

Section 6453

FOR THE DEPARTMENT OF FISH AND WILDLIFE

The reappropriation in this section is subject to the following conditions and limitations: The reappropriation is subject to the provisions of section 3294, chapter 332, Laws of 2021.

Section 6454

FOR THE DEPARTMENT OF FISH AND WILDLIFE

The reappropriation in this section is subject to the following conditions and limitations: The reappropriation is subject to the provisions of section 3064, chapter 296, Laws of 2022.

Section 6455

FOR THE DEPARTMENT OF FISH AND WILDLIFE

Section 6456

FOR THE DEPARTMENT OF NATURAL RESOURCES

Section 6457

FOR THE DEPARTMENT OF NATURAL RESOURCES

Section 6458

FOR THE DEPARTMENT OF NATURAL RESOURCES

Section 6459

FOR THE DEPARTMENT OF NATURAL RESOURCES

The reappropriation in this section is subject to the following conditions and limitations: The reappropriation is subject to the provisions of section 3281, chapter 413, Laws of 2019.

Section 6460

FOR THE DEPARTMENT OF NATURAL RESOURCES

Section 6461

FOR THE DEPARTMENT OF NATURAL RESOURCES

Section 6462

FOR THE DEPARTMENT OF NATURAL RESOURCES

The reappropriation in this section is subject to the following conditions and limitations: The reappropriation is subject to the provisions of section 3292, chapter 413, Laws of 2019.

Section 6463

FOR THE DEPARTMENT OF NATURAL RESOURCES

Section 6464

FOR THE DEPARTMENT OF NATURAL RESOURCES

Section 6465

FOR THE DEPARTMENT OF NATURAL RESOURCES

The reappropriation in this section is subject to the following conditions and limitations: The reappropriation is subject to the provisions of section 3072, chapter 296, Laws of 2022.

Section 6466

FOR THE DEPARTMENT OF NATURAL RESOURCES

Section 6467

FOR THE DEPARTMENT OF NATURAL RESOURCES

The reappropriation in this section is subject to the following conditions and limitations: The reappropriation is subject to the provisions of section 3323, chapter 332, Laws of 2021.

Section 6468

FOR THE DEPARTMENT OF NATURAL RESOURCES

Section 6469

FOR THE DEPARTMENT OF NATURAL RESOURCES

The reappropriation in this section is subject to the following conditions and limitations: The reappropriation is subject to the provisions of section 3326, chapter 332, Laws of 2021.

Section 6470

FOR THE DEPARTMENT OF NATURAL RESOURCES

The reappropriation in this section is subject to the following conditions and limitations: The reappropriation is subject to the provisions of section 3327, chapter 332, Laws of 2021.

Section 6471

FOR THE DEPARTMENT OF NATURAL RESOURCES

The reappropriation in this section is subject to the following conditions and limitations: The reappropriation is subject to the provisions of section 3073, chapter 296, Laws of 2022.

Section 6472

FOR THE DEPARTMENT OF NATURAL RESOURCES

The reappropriation in this section is subject to the following conditions and limitations: The reappropriation is subject to the provisions of section 3066, chapter 296, Laws of 2022.

Section 6473

FOR THE DEPARTMENT OF NATURAL RESOURCES

The reappropriation in this section is subject to the following conditions and limitations: The reappropriation is subject to the provisions of section 3299, chapter 332, Laws of 2021.

Section 6474

FOR THE DEPARTMENT OF NATURAL RESOURCES

Section 6475

FOR THE DEPARTMENT OF NATURAL RESOURCES

Section 6476

FOR THE DEPARTMENT OF NATURAL RESOURCES

The reappropriation in this section is subject to the following conditions and limitations: The reappropriation is subject to the provisions of section 3303, chapter 332, Laws of 2021.

Section 6477

FOR THE DEPARTMENT OF NATURAL RESOURCES

The reappropriation in this section is subject to the following conditions and limitations: The reappropriation is subject to the provisions of section 3304, chapter 332, Laws of 2021.

Section 6478

FOR THE DEPARTMENT OF NATURAL RESOURCES

Section 6479

FOR THE DEPARTMENT OF NATURAL RESOURCES

Section 6480

FOR THE DEPARTMENT OF NATURAL RESOURCES

The reappropriation in this section is subject to the following conditions and limitations: The reappropriation is subject to the provisions of section 3075, chapter 296, Laws of 2022.

Section 6481

FOR THE DEPARTMENT OF AGRICULTURE

Section 6482

FOR THE COMMUNITY AND TECHNICAL COLLEGE SYSTEM

Section 6483

FOR THE COMMUNITY AND TECHNICAL COLLEGE SYSTEM

Section 6484

FOR THE COMMUNITY AND TECHNICAL COLLEGE SYSTEM

Section 6485

FOR THE COMMUNITY AND TECHNICAL COLLEGE SYSTEM

Section 6486

FOR THE COMMUNITY AND TECHNICAL COLLEGE SYSTEM

The reappropriation in this section is subject to the following conditions and limitations: The reappropriation is subject to the provisions of section 5025, chapter 298, Laws of 2018.

Section 6487

FOR THE COMMUNITY AND TECHNICAL COLLEGE SYSTEM

Section 6488

FOR THE COMMUNITY AND TECHNICAL COLLEGE SYSTEM

Section 6489

FOR THE COMMUNITY AND TECHNICAL COLLEGE SYSTEM

Section 6490

FOR THE COMMUNITY AND TECHNICAL COLLEGE SYSTEM

Section 6491

FOR THE COMMUNITY AND TECHNICAL COLLEGE SYSTEM

Section 6492

FOR THE COMMUNITY AND TECHNICAL COLLEGE SYSTEM

Section 6493

FOR THE COMMUNITY AND TECHNICAL COLLEGE SYSTEM

Section 6494

FOR THE COMMUNITY AND TECHNICAL COLLEGE SYSTEM

Section 6495

FOR THE COMMUNITY AND TECHNICAL COLLEGE SYSTEM

Section 6496

FOR THE COMMUNITY AND TECHNICAL COLLEGE SYSTEM

The reappropriation in this section is subject to the following conditions and limitations: The reappropriation is subject to the provisions of section 5140, chapter 332, Laws of 2021.

Section 6497

FOR THE COMMUNITY AND TECHNICAL COLLEGE SYSTEM

Section 6498

FOR THE COMMUNITY AND TECHNICAL COLLEGE SYSTEM

Section 6499

FOR THE COMMUNITY AND TECHNICAL COLLEGE SYSTEM

Section 6500

FOR THE COMMUNITY AND TECHNICAL COLLEGE SYSTEM

Section 6501

FOR THE COMMUNITY AND TECHNICAL COLLEGE SYSTEM

Section 6502

FOR THE COMMUNITY AND TECHNICAL COLLEGE SYSTEM

Section 6503

FOR THE COMMUNITY AND TECHNICAL COLLEGE SYSTEM

Section 6504

FOR THE COMMUNITY AND TECHNICAL COLLEGE SYSTEM

Section 6505

FOR THE COMMUNITY AND TECHNICAL COLLEGE SYSTEM

Section 6506

FOR THE COMMUNITY AND TECHNICAL COLLEGE SYSTEM

The reappropriation in this section is subject to the following conditions and limitations: The reappropriation is subject to the provisions of section 5037, chapter 296, Laws of 2022.

Section 6507

FOR THE COMMUNITY AND TECHNICAL COLLEGE SYSTEM

Section 6508

FOR THE SUPERINTENDENT OF PUBLIC INSTRUCTION

The reappropriation in this section is subject to the following conditions and limitations: The reappropriation is subject to the provisions of section 5001, chapter 35, Laws of 2016 sp. sess.

Section 6509

FOR THE SUPERINTENDENT OF PUBLIC INSTRUCTION

The reappropriation in this section is subject to the following conditions and limitations: The reappropriation is subject to the provisions of section 5013, chapter 3, Laws of 2015 3rd sp. sess.

Section 6510

FOR THE SUPERINTENDENT OF PUBLIC INSTRUCTION

The reappropriation in this section is subject to the following conditions and limitations: The reappropriation is subject to the provisions of section 5004, chapter 2, Laws of 2018.

Section 6511

FOR THE SUPERINTENDENT OF PUBLIC INSTRUCTION

The reappropriations in this section are subject to the following conditions and limitations: The reappropriations are subject to the provisions of section 5003, chapter 298, Laws of 2018.

Section 6512

FOR THE SUPERINTENDENT OF PUBLIC INSTRUCTION

The reappropriations in this section are subject to the following conditions and limitations: The reappropriations are subject to the provisions of section 6040, chapter 332, Laws of 2021.

Section 6513

FOR THE SUPERINTENDENT OF PUBLIC INSTRUCTION

The reappropriation in this section is subject to the following conditions and limitations: The reappropriation is subject to the provisions of section 5016, chapter 413, Laws of 2019.

Section 6514

FOR THE SUPERINTENDENT OF PUBLIC INSTRUCTION

Section 6515

FOR THE SUPERINTENDENT OF PUBLIC INSTRUCTION

The reappropriations in this section are subject to the following conditions and limitations: The reappropriations are subject to the provisions of section 5004, chapter 296, Laws of 2022.

Section 6516

FOR THE SUPERINTENDENT OF PUBLIC INSTRUCTION

The reappropriation in this section is subject to the following conditions and limitations: The reappropriation is subject to the provisions of section 5005, chapter 296, Laws of 2022.

Section 6517

FOR THE SUPERINTENDENT OF PUBLIC INSTRUCTION

The reappropriation in this section is subject to the following conditions and limitations: The reappropriation is subject to the provisions of section 5006, chapter 296, Laws of 2022.

Section 6518

FOR THE SUPERINTENDENT OF PUBLIC INSTRUCTION

Section 6519

FOR THE SUPERINTENDENT OF PUBLIC INSTRUCTION

Section 6520

FOR THE SUPERINTENDENT OF PUBLIC INSTRUCTION

Section 6521

FOR THE SUPERINTENDENT OF PUBLIC INSTRUCTION

The reappropriations in this section are subject to the following conditions and limitations: The reappropriations are subject to the provisions of section 5007, chapter 296, Laws of 2022.

Section 6522

FOR THE SUPERINTENDENT OF PUBLIC INSTRUCTION

The reappropriation in this section is subject to the following conditions and limitations: The reappropriation is subject to the provisions of section 5025, chapter 332, Laws of 2021.

Section 6523

FOR THE SUPERINTENDENT OF PUBLIC INSTRUCTION

The reappropriation in this section is subject to the following conditions and limitations: The reappropriation is subject to the provisions of section 5016, chapter 332, Laws of 2021.

Section 6524

FOR THE SUPERINTENDENT OF PUBLIC INSTRUCTION

The reappropriation in this section is subject to the following conditions and limitations: The reappropriation is subject to the provisions of section 5027, chapter 332, Laws of 2021.

Section 6525

FOR THE SUPERINTENDENT OF PUBLIC INSTRUCTION

The reappropriation in this section is subject to the following conditions and limitations: The reappropriation is subject to the provisions of section 5009, chapter 296, Laws of 2022.

Section 6526

FOR THE SUPERINTENDENT OF PUBLIC INSTRUCTION

The reappropriation in this section is subject to the following conditions and limitations: The reappropriation is subject to the provisions of section 5012, chapter 296, Laws of 2022.

Section 6527

FOR THE SUPERINTENDENT OF PUBLIC INSTRUCTION

The reappropriation in this section is subject to the following conditions and limitations: The reappropriation is subject to the provisions of section 5023, chapter 413, Laws of 2019.

Section 6528

FOR THE SUPERINTENDENT OF PUBLIC INSTRUCTION

The reappropriation in this section is subject to the following conditions and limitations: The reappropriation is subject to the provisions of section 5004, chapter 356, Laws of 2020.

Section 6529

FOR THE SUPERINTENDENT OF PUBLIC INSTRUCTION

The reappropriation in this section is subject to the following conditions and limitations: The reappropriation is subject to the provisions of section 5003, chapter 356, Laws of 2020.

Section 6530

FOR THE SUPERINTENDENT OF PUBLIC INSTRUCTION

The reappropriation in this section is subject to the following conditions and limitations: The reappropriation is subject to the provisions of section 5029, chapter 413, Laws of 2019.

Section 6531

FOR THE SUPERINTENDENT OF PUBLIC INSTRUCTION

The reappropriation in this section is subject to the following conditions and limitations: The reappropriation is subject to the provisions of section 5005, chapter 356, Laws of 2020.

Section 6532

FOR THE SUPERINTENDENT OF PUBLIC INSTRUCTION

The reappropriation in this section is subject to the following conditions and limitations: The reappropriation is subject to the provisions of section 5006, chapter 356, Laws of 2020.

Section 6533

FOR THE SUPERINTENDENT OF PUBLIC INSTRUCTION

The reappropriation in this section is subject to the following conditions and limitations: The reappropriation is subject to the provisions of section 5010, chapter 296, Laws of 2022.

Section 6534

FOR THE SUPERINTENDENT OF PUBLIC INSTRUCTION

The reappropriation in this section is subject to the following conditions and limitations: The reappropriation is subject to the provisions of section 5008, chapter 296, Laws of 2022.

Section 6535

FOR THE SUPERINTENDENT OF PUBLIC INSTRUCTION

The reappropriation in this section is subject to the following conditions and limitations: The reappropriation is subject to the provisions of section 5011, chapter 296, Laws of 2022.

Section 7001

FOR THE DEPARTMENT OF COMMERCE

Section 7002

FOR THE DEPARTMENT OF COMMERCE

Section 7003

FOR THE DEPARTMENT OF COMMERCE

Section 7004

FOR THE DEPARTMENT OF COMMERCE

Section 7005

FOR THE OFFICE OF FINANCIAL MANAGEMENT

Section 7006

FOR THE DEPARTMENT OF COMMERCE

Section 7007

FOR THE DEPARTMENT OF COMMERCE

Section 7008

FOR THE DEPARTMENT OF COMMERCE

Section 7009

FOR THE DEPARTMENT OF COMMERCE

Section 7010

FOR THE DEPARTMENT OF COMMERCE

Section 7011

FOR THE OFFICE OF FINANCIAL MANAGEMENT

Section 7012

FOR THE DEPARTMENT OF ENTERPRISE SERVICES

Section 7013

FOR THE DEPARTMENT OF ENTERPRISE SERVICES

Section 7014

FOR THE DEPARTMENT OF SOCIAL AND HEALTH SERVICES

Section 7015

FOR THE DEPARTMENT OF SOCIAL AND HEALTH SERVICES

Section 7016

FOR THE DEPARTMENT OF SOCIAL AND HEALTH SERVICES

Section 7017

FOR THE DEPARTMENT OF SOCIAL AND HEALTH SERVICES

Section 7018

FOR THE DEPARTMENT OF SOCIAL AND HEALTH SERVICES

Section 7019

FOR THE DEPARTMENT OF CORRECTIONS

Section 7020

FOR THE DEPARTMENT OF HEALTH

Section 7021

FOR THE DEPARTMENT OF ECOLOGY

Section 7022

FOR THE DEPARTMENT OF ECOLOGY

Section 7023

FOR THE DEPARTMENT OF ECOLOGY

Section 7024

FOR THE DEPARTMENT OF ECOLOGY

Section 7025

FOR THE DEPARTMENT OF ECOLOGY

Section 7026

FOR THE DEPARTMENT OF ECOLOGY

Section 7027

FOR THE DEPARTMENT OF ECOLOGY

Section 7028

FOR THE DEPARTMENT OF ECOLOGY

Section 7029

FOR THE DEPARTMENT OF ECOLOGY

Section 7030

FOR THE DEPARTMENT OF ECOLOGY

Section 7031

FOR THE DEPARTMENT OF ECOLOGY

Section 7032

FOR THE DEPARTMENT OF ECOLOGY

Section 7033

FOR THE DEPARTMENT OF ECOLOGY

Section 7034

FOR THE DEPARTMENT OF ECOLOGY

Section 7035

FOR THE DEPARTMENT OF ECOLOGY

Section 7036

FOR THE DEPARTMENT OF ECOLOGY

Section 7037

FOR THE DEPARTMENT OF ECOLOGY

Section 7038

FOR THE DEPARTMENT OF ECOLOGY

Section 7039

FOR THE DEPARTMENT OF ECOLOGY

Section 7040

FOR THE DEPARTMENT OF ECOLOGY

Section 7041

FOR THE DEPARTMENT OF ECOLOGY

Section 7042

FOR THE RECREATION AND CONSERVATION OFFICE

Section 7043

FOR THE RECREATION AND CONSERVATION OFFICE

Section 7044

FOR THE RECREATION AND CONSERVATION OFFICE

Section 7045

FOR THE STATE CONSERVATION COMMISSION

Section 7046

FOR THE STATE CONSERVATION COMMISSION

Section 7047

FOR THE DEPARTMENT OF FISH AND WILDLIFE

Section 7048

FOR THE DEPARTMENT OF FISH AND WILDLIFE

Section 7049

FOR THE DEPARTMENT OF NATURAL RESOURCES

Section 7050

FOR THE DEPARTMENT OF NATURAL RESOURCES

Section 7051

FOR THE SUPERINTENDENT OF PUBLIC INSTRUCTION

Section 7052

FOR WESTERN WASHINGTON UNIVERSITY

Section 7053

FOR THE DEPARTMENT OF SOCIAL AND HEALTH SERVICES

Maple Lane - Rapid BH Bed Capacity (92000046)

Section 7054

(1) The following agencies may enter into financial contracts, paid from any funds of an agency, appropriated or nonappropriated, for the purposes indicated and in not more than the principal amounts indicated, plus financing expenses and required reserves pursuant to chapter 39.94 RCW. When securing properties under this section, agencies shall use the most economical financial contract option available, including long-term leases, lease-purchase agreements, lease-development with option to purchase agreements or financial contracts using certificates of participation. Expenditures made by an agency for one of the indicated purposes before the issue date of the authorized financial contract and any certificates of participation therein are intended to be reimbursed from proceeds of the financial contract and any certificates of participation therein to the extent provided in the agency's financing plan approved by the state finance committee.

Section 7055

2021 c 332 s 3111 (uncodified) is repealed.

Section 8001

RCW 43.88.031 requires the disclosure of the estimated debt service costs associated with new capital bond appropriations. The estimated debt service costs for the appropriations contained in this act are $62,480,000 for the 2023-2025 biennium, $379,283,000 for the 2025-2027 biennium, and $529,187,000 for the 2027-2029 biennium.

Section 8002

  1. The following agencies may enter into financial contracts, paid from any funds of an agency, appropriated or nonappropriated, for the purposes indicated and in not more than the principal amounts indicated, plus financing expenses and required reserves pursuant to chapter 39.94 RCW. When securing properties under this section, agencies shall use the most economical financial contract option available, including long-term leases, lease-purchase agreements, lease-development with option to purchase agreements or financial contracts using certificates of participation. Expenditures made by an agency for one of the indicated purposes before the issue date of the authorized financial contract and any certificates of participation therein are intended to be reimbursed from proceeds of the financial contract and any certificates of participation therein to the extent provided in the agency's financing plan approved by the state finance committee.

  2. Those noninstructional facilities of higher education institutions authorized in this section to enter into financial contracts are not eligible for state funded maintenance and operations. Instructional space that is available for regularly scheduled classes for academic transfer, basic skills, and workforce training programs may be eligible for state funded maintenance and operations.

  3. Secretary of state: Enter into a financing contract for up to $119,000,000 plus financing expenses, required reserves, and capitalized interest pursuant to chapter 39.94 RCW to construct a new library-archives building.

  4. Department of social and health services: Enter into a financing contract for up to $146,038,000 plus costs and financing expenses, required reserves, and capitalized interest pursuant to chapter 39.94 RCW to construct a nursing facility on the fircrest residential habilitation center campus. The department may contract to lease develop or lease purchase the facility. Before entering into a contract, the department must consult with the office of financial management and the office of the state treasurer. Should the department of social and health services choose to use a financing contract that does not provide for the issuance of certificates of participation, the financing contract shall be subject to approval by the state finance committee as required by RCW 39.94.010. In approving a financing contract not providing for the use of certificates of participation, the state finance committee should be reasonably certain that the contract is excluded from the computation of indebtedness, particularly that the contract is not backed by the full faith and credit of the state and the legislature is expressly not obligated to appropriate funds to make payments. For purposes of this subsection, "financing contract" includes but is not limited to a certificate of participation and tax exempt financing similar to that authorized in RCW 47.79.140.

Section 8003

  1. To ensure that major construction projects are carried out in accordance with legislative and executive intent, agencies must complete a predesign for state construction projects with a total anticipated cost in excess of $10,000,000. For purposes of this section, "total anticipated cost" means the sum of the anticipated cost of the predesign, design, and construction phases of the project.

  2. Appropriations for design may not be expended or encumbered until the office of financial management has reviewed and approved the agency's predesign.

  3. The predesign must explore at least three project alternatives. These alternatives must be both distinctly different and viable solutions to the issue being addressed. The chosen alternative should be the most reasonable and cost-effective solution. The predesign document must include, but not be limited to, program, site, and cost analysis, and an analysis of the life-cycle costs of the alternatives explored, in accordance with the predesign manual adopted by the office of financial management.

  4. For projects exceeding the $10,000,000 predesign threshold established in this section, the office of financial management may make an exception to some or all of the predesign requirements in this section. The office of financial management shall report any exception to the fiscal committees of the legislature:

    1. A description of the major capital project for which the predesign waiver is made;

    2. An explanation of the reason for the waiver; and

    3. A rough order of magnitude cost estimate for the project's design and construction.

  5. In deliberations related to submitting an exception under this section, the office of financial management shall consider the following factors:

    1. Whether there is any determination to be made regarding the site of the project;

    2. Whether there is any determination to be made regarding whether the project will involve renovation, new construction, or both;

    3. Whether, within six years of submitting the request for funding, the agency has completed, or initiated the construction of, a substantially similar project;

    4. Whether there is any anticipated change to the project's program or the services to be delivered at the facility;

    5. Whether the requesting agency indicates that the project may not require some or all of the predesign requirements in this section due to a lack of complexity; and

    6. Whether any other factors related to project complexity or risk, as determined by the office of financial management, could reduce the need for, or scope of, a predesign.

  6. If under this section, some or all predesign requirements are waived, the office of financial management may instead propose a professional project cost estimate instead of a request for predesign funding.

Section 8004

  1. The legislature finds that use of life-cycle cost analysis will aid public entities, architects, engineers, and contractors in making design and construction decisions that positively impact both the initial construction cost and the ongoing operating and maintenance cost of a project. To ensure that the total cost of a project is accounted for and the most reasonable and cost efficient design is used, agencies shall develop life-cycle costs for any construction project over $10,000,000. The life-cycle costs must represent the present value sum of capital costs, installation costs, operating costs, and maintenance costs over the life expectancy of the project. The legislature further finds the most effective approach to the life-cycle cost analysis is to integrate it into the early part of the design process.

  2. Agencies must develop a minimum of three project alternatives for use in the life-cycle cost analysis. These alternatives must be both distinctly different and viable solutions to the issue being addressed. Agencies must choose the most reasonable and cost-effective solution, as supported by the life-cycle cost analysis. A brief description of each project alternative and why it was chosen must be included in the life-cycle cost analysis section of the predesign.

  3. The office of financial management shall: (a) Make available a life-cycle cost model to be used for analysis; (b) in consultation with the department of enterprise services, provide assistance in using the life-cycle cost model; and (c) update the life-cycle cost model annually including assumptions for inflation rates, discount rates, and energy rates.

  4. Agencies shall consider architectural and engineering firms' and general contractors' experience using life-cycle costs, operating costs, and energy efficiency measures when selecting an architectural and engineering firm, or when selecting contractors using alternative contracting methods.

Section 8005

Agencies administering construction projects with a total anticipated cost in excess of $10,000,000 must submit progress reports to the office of financial management and to the fiscal committees of the house of representatives and senate. "Total anticipated cost" means the sum of the anticipated cost of the predesign, design, and construction phases of the project. Reports must be submitted on July 1st and December 31st of each year in a format determined by the office of financial management. After the project is completed, agencies must also submit a closeout report that identifies the total project cost and any unspent appropriations.

Section 8006

  1. Allotments for appropriations in this act shall be provided in accordance with the capital project review requirements adopted by the office of financial management and in compliance with RCW 43.88.110. Projects that will be employing alternative public works construction procedures under chapter 39.10 RCW are subject to the allotment procedures defined in this section and RCW 43.88.110.

  2. Each project is defined as proposed in the legislative budget notes or in the governor's budget document.

Section 8007

  1. The office of financial management may authorize a transfer of appropriation authority provided for a capital project that is in excess of the amount required for the completion of such project to another capital project for which the appropriation is insufficient. No such transfer may be used to expand the capacity of any facility beyond that intended in making the appropriation. Such transfers may be effected only between capital appropriations to a specific department, commission, agency, or institution of higher education and only between capital projects that are funded from the same fund or account. No transfers may occur between projects to local government agencies except where the grants are provided within a single omnibus appropriation and where such transfers are specifically authorized by the implementing statutes that govern the grants.

  2. The office of financial management may find that an amount is in excess of the amount required for the completion of a project only if: (a) The project as defined in the notes to the budget document is substantially complete and there are funds remaining; or (b) bids have been let on a project and it appears to a substantial certainty that the project as defined in the notes to the budget document can be completed within the biennium for less than the amount appropriated in this act.

  3. For the purposes of this section, the intent is that each project be defined as proposed to the legislature in the governor's budget document, unless it clearly appears from the legislative history that the legislature intended to define the scope of a project in a different way.

  4. A report of any transfer effected under this section, except emergency projects or any transfer under $250,000, shall be filed with the fiscal committees of the legislature by the office of financial management at least 30 days before the date the transfer is effected. The office of financial management shall report all emergency or smaller transfers within 30 days from the date of transfer.

Section 8008

  1. It is expected that projects be ready to proceed in a timely manner depending on the type or phase of the project or program that is the subject of the appropriation in this act. Except for major projects that customarily may take more than two biennia to complete from predesign to the end of construction, or large infrastructure grant or loan programs supporting projects that often take more than two biennia to complete, the legislature generally does not intend to reappropriate funds more than once, particularly for smaller grant programs, local/community projects, and minor works.

  2. Agencies shall expedite the expenditure of reappropriations and appropriations in this act in order to: (a) Rehabilitate infrastructure resources; (b) accelerate environmental rehabilitation and restoration projects for the improvement of the state's natural environment; (c) reduce additional costs associated with acquisition and construction inflationary pressures; and (d) provide additional employment opportunities associated with capital expenditures.

  3. To the extent feasible, agencies are directed to accelerate expenditure rates at their current level of permanent employees and shall use contracted design and construction services wherever necessary to meet the goals of this section.

Section 8009

Any building project that receives over $10,000,000 in funding from the capital budget must be built to sustainable standards. "Sustainable building" means a building that integrates and optimizes all major high-performance building attributes, including energy efficiency, durability, life-cycle performance, and occupant productivity, and minimizes greenhouse gas emissions. The following design and construction attributes must be integrated into the building project:

  1. Employ integrated design principles: Use a collaborative, integrated planning and design process that initiates and maintains an integrated project team in all stages of a project's planning and delivery. Establish performance goals for siting, energy, water, materials, and indoor environmental quality along with other comprehensive design goals and ensures incorporation of these goals throughout the design and life-cycle of the building. Consider all stages of the building's life-cycle, including deconstruction.

  2. Commissioning: Employ commissioning practices tailored to the size and complexity of the building and its system components in order to verify performance of building components and systems and help ensure that design requirements are met. This should include an experienced commissioning provider, inclusion of commissioning requirements in construction documents, a commissioning plan, verification of the installation and performance of systems to be commissioned, and a commissioning report.

  3. Optimize energy performance: Establish a whole building performance target that takes into account the intended use, occupancy, operations, plug loads, other energy demands, and design to earn the ENERGY STAR targets for new construction and major renovation where applicable. For new construction target low energy use index. For major renovations, target reducing energy use by 50 percent below prerenovations baseline.

  4. On-site renewable energy: Implement renewable energy generation projects on agency property for agency use, when life-cycle cost effective.

  5. High-efficiency electric equipment: Use only high-efficiency electric equipment for water and space heating needs not met through on-site renewable energy, when life-cycle cost effective.

  6. Measurement and verification: For buildings over 50,000 square feet, install building level electricity meters in new major construction and renovation projects to track and continuously optimize performance. Include equivalent meters for natural gas and steam, where natural gas and steam are used. Where appropriate, install dashboards inside buildings to display and incentivize occupants on energy use.

  7. Benchmarking: Compare performance data from the first year of operation with the energy design target. Verify that the building performance meets or exceeds the design target. For other building and space types, use an equivalent benchmarking tool.

Section 8010

State agencies, including institutions of higher education, shall allot and report full-time equivalent staff for capital projects in a manner comparable to staff reporting for operating expenditures.

Section 8011

Executive Order No. 21-02, archaeological and cultural resources, was issued effective April 7, 2021. Agencies shall comply with the requirements set forth in this executive order and must consult with the department of archaeology and historic preservation and affected tribes on the potential effects of projects on cultural resources and historic properties proposed in state-funded construction or acquisition projects, including grant or pass-through funding that culminates in construction or land acquisitions. Consultation with the department of archaeology and historic preservation and affected tribes must be initiated early in the project planning process, prior to construction or taking title.

Section 8012

  1. One-half of one percent of moneys appropriated in this act for original construction of school plant facilities is provided solely for the purposes of RCW 28A.335.210.

  2. One-half of one percent of moneys appropriated in this act for original construction or any major renovation or remodel work exceeding $200,000 by colleges or universities is provided solely for the purposes of RCW 28B.10.027.

  3. One-half of one percent of moneys appropriated in this act for original construction of any public building by a state agency identified in RCW 43.17.200 is provided solely for the purposes of RCW 43.17.200.

  4. At least 75 percent of the moneys spent by the Washington state arts commission during the 2023-2025 fiscal biennium for the purposes of RCW 28A.335.210, 28B.10.027, and 43.17.200 must be expended solely for direct acquisition of works of art; 15 percent may be expended for program administration; and 10 percent may be expended to conserve or maintain existing pieces in the state art collection. Except for art allocations made under K-3 class size reduction grants under section 6527 of this act, art allocations not expended within the ensuing two biennia shall lapse.

Section 8013

To carry out the provisions of this act, the governor may assign responsibility for predesign, design, construction, and other related activities to any appropriate agency.

Section 8014

If any federal moneys appropriated by this act for capital projects are not received by the state, the department or agency to which the moneys were appropriated may replace the federal moneys with funds available from private or local sources. No replacement may occur under this section without the prior approval of the director of financial management in consultation with the senate ways and means committee and the house of representatives capital budget committee.

Section 8015

  1. Unless otherwise stated, for all appropriations under this act that require a match of nonstate money or in-kind contributions, the following requirement, consistent with RCW 43.88.150, shall apply: Expenditures of state money shall be timed so that the state share of project expenditures never exceeds the intended state share of total project costs.

  2. Provision of the full amount of required matching funds is not required to permit the expenditure of capital budget appropriations for phased projects if a proportional amount of the required matching funds is provided for each distinct, identifiable phase of the project.

Section 8016

Portions of the appropriation authority granted by this act from the state building construction account, or any other account receiving bond proceeds, may be transferred to the state taxable building construction account as deemed necessary by the state treasurer, on behalf of the state finance committee, to comply with the federal internal revenue service rules and regulations pertaining to the use of nontaxable bond proceeds. Portions of the general obligation bond proceeds authorized by chapter . . . (Senate Bill No. 5201), Laws of 2023 (state general obligation bonds and related accounts) for deposit into the state taxable building construction account that are in excess of amounts required to comply with the federal internal revenue service rules and regulations shall be deposited into the state building construction account. The state treasurer shall submit written notification to the director of financial management and the legislative evaluation and accountability program committee if it is determined that a shift of appropriation authority between the state building construction account, or any other account receiving bond proceeds, and the state taxable building construction account is necessary, or that a shift of appropriation authority from the state taxable building construction account to the state building construction account may be made.

Section 8017

  1. Minor works project lists are single line appropriations that include multiple projects of a similar nature and that are valued between $25,000 and $2,000,000 each. Funds appropriated in this act for minor works may not be initially allotted until agencies submit project lists to the office of financial management for review and approval.

  2. Revisions to the project lists, including the addition of projects and the transfer of funds between projects, are allowed but must be submitted to the office of financial management, the house of representatives capital budget committee, and the senate ways and means committee for review and comment, and must include an explanation of variances from prior approved lists. Any project list revisions must be approved by the office of financial management before funds may be expended from the minor works appropriation.

  3. [Empty]

    1. All minor works projects should be completed within two years of the appropriation with the funding provided.

    2. Agencies are prohibited from including projects on their minor works lists that are a phase of a larger project, and that if combined over a continuous period of time, would exceed $2,000,000.

    3. Minor works appropriations may not be used for the following: Studies, except for technical or engineering reviews or designs that lead directly to and support a project on the same minor works list; planning; design outside the scope of work on a minor works list; movable, temporary, and traditionally funded operating equipment not in compliance with the equipment criteria established by the office of financial management; software not dedicated to control of a specialized system; moving expenses; land or facility acquisition; rolling stock; computers; or to supplement funding for projects with funding shortfalls unless expressly authorized. The office of financial management may make an exception to the limitations described in this subsection (3)(c) for exigent circumstances after notifying the legislative fiscal committees and waiting 10 days for comments by the legislature regarding the proposed exception.

    4. Minor works preservation projects may include program improvements of no more than 25 percent of the individual minor works preservation project cost.

    5. Improvements for accessibility in compliance with the Americans with disabilities act may be included in any of the minor works categories.

Section 8018

To the extent that any appropriation authorizes expenditures of state funds from the state building construction account, or from any other capital project account in the state treasury, for a capital project or program that is specified to be funded with proceeds from the sale of bonds, the legislature declares that any such expenditures for that project or program made prior to the issue date of the applicable bonds are intended to be reimbursed from proceeds of those bonds in a maximum amount equal to the amount of such appropriation.

Section 8019

FOR THE STATE TREASURER—TRANSFERS

Section 8020

In order to accelerate the reduction of embodied carbon and improve the environmental performance of construction materials, agencies shall, whenever possible, review and consider embodied carbon reported in environmental product declarations when evaluating proposed structural materials for construction projects.

Section 8021

The department of natural resources, in coordination with the department of social and health services, shall enter into long-term, revenue-generating opportunities for under used portions of the Fircrest residential habilitation center bounded by 15th Ave NE and NE 150th Street to benefit the charitable, educational, penal, and reformatory institutions account. Long-term, revenue generating opportunities may include, but are not limited to, land leases, land sales, and land swaps. The department of social and health services and the department of natural resources must amend their lease under chapter 7, Laws of 1986 if necessary to conform with this section.

Section 8022

(1) The department must use moneys from the housing trust fund and other legislative appropriations to finance in whole or in part any loans or grant projects that will provide housing for persons and families with special housing needs and with incomes at or below fifty 50 percent of the median family income for the county or standard metropolitan statistical area where the project is located. At least thirty 30 percent of these moneys used in any given funding cycle must be for the benefit of projects located in rural areas of the state as defined by the department. If the department determines that it has not received an adequate number of suitable applications for rural projects during any given funding cycle, the department may allocate unused moneys for projects in nonrural areas of the state.

Section 8023

Section 8022 of this act takes effect if chapter . . . (Engrossed Substitute Senate Bill No. 5301), Laws of 2023 (concerning housing programs administered by the department of commerce), is not enacted by June 30, 2023.

Section 8024

The board is hereby empowered:

  1. To reserve the right to issue bonds later on a parity with any bonds being issued;

  2. To authorize the investing of moneys in the bond retirement fund and any reserve account therein;

  3. To authorize the transfer of money from the University of Washington building account to the bond retirement fund when necessary to prevent a default in the payments required to be made out of such fund;

  4. To create a reserve account or accounts in the bond retirement fund to secure the payment of the principal of and interest on any bonds;

  5. To authorize the transfer to the University of Washington building account of any money on deposit in the bond retirement fund in excess of debt service for a period of three years from the date of such transfer on all outstanding bonds payable out of such fund. However, during the 2021-2023 fiscal biennium, the legislature may transfer to the University of Washington building account moneys that are in excess of the debt service due within the 2021-2023 fiscal biennium from the date of such transfer on all outstanding bonds payable out of the bond retirement fund. However, during the 2023-2025 fiscal biennium, the legislature may transfer to the University of Washington building account moneys that are in excess of the debt service due within the 2023-2025 fiscal biennium from the date of such transfer on all outstanding bonds payable out of the bond retirement fund.

Section 8025

The board is hereby empowered:

  1. To reserve the right to issue bonds later on a parity with any bonds being issued;

  2. To authorize the investing of moneys in the bond retirement fund and any reserve account therein;

  3. To authorize the transfer of money from the Washington State University building account to the bond retirement fund when necessary to prevent a default in the payments required to be made out of such fund;

  4. To create a reserve account or accounts in the bond retirement fund to secure the payment of the principal of and interest on any bonds;

  5. To authorize the transfer to the Washington State University building account of any money on deposit in the bond retirement fund in excess of debt service for a period of three years from the date of such transfer on all outstanding bonds payable out of such fund. However, during the 2021-2023 fiscal biennium, the legislature may transfer to the Washington State University building account moneys that are in excess of the debt service due within the 2021-2023 fiscal biennium from the date of such transfer on all outstanding bonds payable out of the bond retirement fund. However, during the 2023-2025 fiscal biennium, the legislature may transfer to the University of Washington building account moneys that are in excess of the debt service due within the 2023-2025 fiscal biennium from the date of such transfer on all outstanding bonds payable out of the bond retirement fund.

Section 8026

  1. By October 1st of each even-numbered year, the office of financial management shall complete an objective analysis and scoring of all capital budget projects proposed by the public four-year institutions of higher education and submit the results of the scoring process to the legislative fiscal committees and the four-year institutions. Each project must be reviewed and scored within one of the following categories, according to the project's principal purpose. Each project may be scored in only one category. The categories are:

    1. Access‑related projects to accommodate enrollment growth at all campuses, at existing or new university centers, or through distance learning. Growth projects should provide significant additional student capacity. Proposed projects must demonstrate that they are based on solid enrollment demand projections, more cost‑effectively provide enrollment access than alternatives such as university centers and distance learning, and make cost‑effective use of existing and proposed new space;

    2. Projects that replace failing permanent buildings. Facilities that cannot be economically renovated are considered replacement projects. New space may be programmed for the same or a different use than the space being replaced and may include additions to improve access and enhance the relationship of program or support space;

    3. Projects that renovate facilities to restore building life and upgrade space to meet current program requirements. Renovation projects should represent a complete renovation of a total facility or an isolated wing of a facility. A reasonable renovation project should cost between sixty to eighty percent of current replacement value and restore the renovated area to at least twenty-five years of useful life. New space may be programmed for the same or a different use than the space being renovated and may include additions to improve access and enhance the relationship of program or support space;

    4. Major stand-alone campus infrastructure projects;

    5. Projects that promote economic growth and innovation through expanded research activity. The acquisition and installation of specialized equipment is authorized under this category; and

    6. Other project categories as determined by the office of financial management in consultation with the legislative fiscal committees.

  2. The office of financial management, in consultation with the legislative fiscal committees, shall establish a scoring system and process for each four-year project category that is based on the framework used in the community and technical college system of prioritization. Staff from the state board for community and technical colleges and the four-year institutions shall provide technical assistance on the development of a scoring system and process.

  3. The office of financial management shall consult with the legislative fiscal committees in the scoring of four-year institution project proposals, and may also solicit participation by independent experts.

    1. For each four-year project category, the scoring system must, at a minimum, include an evaluation of enrollment trends, reasonableness of cost, the ability of the project to enhance specific strategic master plan goals, age and condition of the facility if applicable, and impact on space utilization.

    2. Each four-year project category may include projects at the predesign, design, or construction funding phase.

    3. To the extent possible, the objective analysis and scoring system of all capital budget projects shall occur within the context of any and all performance agreements between the office of financial management and the governing board of a public, four-year institution of higher education that aligns goals, priorities, desired outcomes, flexibility, institutional mission, accountability, and levels of resources.

  4. In evaluating and scoring four-year institution projects, the office of financial management shall take into consideration project schedules that result in realistic, balanced, and predictable expenditure patterns over the ensuing three biennia.

  5. The office of financial management shall distribute common definitions, the scoring system, and other information required for the project proposal and scoring process as part of its biennial budget instructions. The office of financial management, in consultation with the legislative fiscal committees, shall develop common definitions that four-year institutions must use in developing their project proposals and lists under this section.

  6. In developing any scoring system for capital projects proposed by the four-year institutions, the office of financial management:

    1. Shall be provided with all required information by the four-year institutions as deemed necessary by the office of financial management;

    2. May utilize independent services to verify, sample, or evaluate information provided to the office of financial management by the four-year institutions; and

    3. Shall have full access to all data maintained by the joint legislative audit and review committee concerning the condition of higher education facilities.

  7. By August 1st of each even-numbered year each public four-year higher education institution shall prepare and submit prioritized lists of the individual projects proposed by the institution for the ensuing six-year period in each category. The lists must be submitted to the office of financial management and the legislative fiscal committees. The four-year institutions may aggregate minor works project proposals by primary purpose for ranking purposes. Proposed minor works projects must be prioritized within the aggregated proposal, and supporting documentation, including project descriptions and cost estimates, must be provided to the office of financial management and the legislative fiscal committees.

  8. For the 2021-2023 fiscal biennium, pursuant to subsection (1) of this section, by November 1, 2022, the office of financial management must score higher education capital project criteria with a rating scale that assesses how well a particular project satisfies those criteria. The office of financial management may not use a rating scale that weighs the importance of those criteria.

  9. For the 2021-2023 fiscal biennium, pursuant to subsection (6)(a) of this section and in lieu of the requirements of subsection (7) of this section, by August 15, 2022, the institutions of higher education shall prepare and submit or resubmit to the office of financial management and the legislative fiscal committees:

    1. Individual project proposals developed pursuant to subsection (1) of this section;

    2. Individual project proposals scored in prior biennia pursuant to subsection (1) of this section; and

    3. A prioritized list of up to five project proposals submitted pursuant to (a) and (b) of this subsection.

  10. The requirements of this section are suspended during the 2023-2025 fiscal biennium.

Section 8027

  1. All major facility projects of public agencies receiving any funding in a state capital budget, or projects financed through a financing contract as defined in RCW 39.94.020, must be designed, constructed, and certified to at least the LEED silver standard. This subsection applies to major facility projects that have not entered the design phase prior to July 24, 2005, and to the extent appropriate LEED silver standards exist for that type of building or facility.

  2. All major facility projects of any entity other than a public agency or public school district receiving any funding in a state capital budget must be designed, constructed, and certified to at least the LEED silver standard. This subsection applies to major facility projects that have not entered the grant application process prior to July 24, 2005, and to the extent appropriate LEED silver standards exist for that type of building or facility.

  3. [Empty]

    1. Public agencies, under this section, shall monitor and document ongoing operating savings resulting from major facility projects designed, constructed, and certified as required under this section.

    2. Public agencies, under this section, shall report annually to the department on major facility projects and operating savings.

  4. The department shall consolidate the reports required in subsection (3) of this section into one report and report to the governor and legislature by September 1st of each even-numbered year beginning in 2006 and ending in 2016. In its report, the department shall also report on the implementation of this chapter, including reasons why the LEED standard was not used as required by RCW 39.35D.020(5)(b). The department shall make recommendations regarding the ongoing implementation of this chapter, including a discussion of incentives and disincentives related to implementing this chapter.

  5. For the purposes of determining compliance with the requirement for a project to be designed, constructed, and certified to at least the LEED silver standard, the department must credit one additional point for a project that uses wood products with a credible third-party sustainable forest certification or from forests regulated under chapter 76.09 RCW, the Washington forest practices act. For projects that qualify for this additional point, and for which an additional point would have resulted in formal certification under the LEED silver standard, the project must be deemed to meet the standard under this section.

  6. During the 2021-2023 and 2023-2025 fiscal biennia, an alternative high-performance building certification, as determined by the legislature, may be used instead of the LEED silver building design, construction, and certification standard required by this section.

Section 8028

The state drought preparedness and response account is created in the state treasury. All receipts from appropriated funds designated for the account and all cost recovery revenues collected under RCW 43.83B.410(5) must be deposited into the account. Expenditures from the account may be used for drought preparedness and response activities under this chapter, including grants issued under RCW 43.83B.415. During the 2021-2023 fiscal biennium, moneys in the account may be used for water banking pilot projects. Moneys in the account may be spent only after appropriation. During the 2021-2023 and 2023-2025 fiscal biennium biennia, the legislature may appropriate moneys from the account for activities related to water banking.

Section 8029

  1. The stadium and exhibition center account is created in the custody of the state treasurer. All receipts from the taxes imposed under RCW 82.14.0494 and distributions under RCW 67.70.240(1)(d) shall be deposited into the account. Only the director of the office of financial management or the director's designee may authorize expenditures from the account. The account is subject to allotment procedures under chapter 43.88 RCW. An appropriation is not required for expenditures from this account.

  2. Until bonds are issued under RCW 43.99N.020, up to $5,000,000 per year beginning January 1, 1999, shall be used for the purposes of subsection (3)(b) of this section, all remaining moneys in the account shall be transferred to the public stadium authority, created under RCW 36.102.020, to be used for public stadium authority operations and development of the stadium and exhibition center.

  3. After bonds are issued under RCW 43.99N.020, all moneys in the stadium and exhibition center account shall be used exclusively for the following purposes in the following priority:

    1. On or before June 30th of each year, the office of financial management shall accumulate in the stadium and exhibition center account an amount at least equal to the amount required in the next succeeding twelve months for the payment of principal of and interest on the bonds issued under RCW 43.99N.020;

    2. An additional reserve amount not in excess of the expected average annual principal and interest requirements of bonds issued under RCW 43.99N.020 shall be accumulated and maintained in the account, subject to withdrawal by the state treasurer at any time if necessary to meet the requirements of (a) of this subsection, and, following any withdrawal, reaccumulated from the first tax revenues and other amounts deposited in the account after meeting the requirements of (a) of this subsection; and

    3. The balance, if any, shall be transferred to the youth athletic facility account under subsection (4) of this section.

Any revenues derived from the taxes authorized by RCW 36.38.010(5) and 36.38.040 or other amounts that if used as provided under (a) and (b) of this subsection would cause the loss of any tax exemption under federal law for interest on bonds issued under RCW 43.99N.020 shall be deposited in and used exclusively for the purposes of the youth athletic facility account and shall not be used, directly or indirectly, as a source of payment of principal of or interest on bonds issued under RCW 43.99N.020, or to replace or reimburse other funds used for that purpose.

  1. Any moneys in the stadium and exhibition center account not required or permitted to be used for the purposes described in subsection (3)(a) and (b) of this section shall be deposited in the youth athletic facility account hereby created in the state treasury. Except as provided in subsection (5) of this section, expenditures from the account may be used only for purposes of grants or loans to cities, counties, and qualified nonprofit organizations for community outdoor athletic facilities. Only the director of the recreation and conservation office or the director's designee may authorize expenditures from the account. The account is subject to allotment procedures under chapter 43.88 RCW, but an appropriation is not required for expenditures. The athletic facility grants or loans may be used for acquiring, developing, equipping, maintaining, and improving community outdoor athletic facilities. Funds shall be divided equally between the development of new community outdoor athletic facilities, the improvement of existing community outdoor athletic facilities, and the maintenance of existing community outdoor athletic facilities. Cities, counties, and qualified nonprofit organizations must submit proposals for grants or loans from the account. To the extent that funds are available, cities, counties, and qualified nonprofit organizations must meet eligibility criteria as established by the director of the recreation and conservation office. The grants and loans shall be awarded on a competitive application process and the amount of the grant or loan shall be in proportion to the population of the city or county for where the community outdoor athletic facility is located. For the 2023-2025 fiscal biennium, park districts and federally recognized Indian tribes that have a demonstrated financial need may submit proposals and be awarded grants and loans in the competitive process. Grants or loans awarded in any one year need not be distributed in that year. Except for the 2023-2025 fiscal biennium, the director of the recreation and conservation office may expend up to one and one-half percent of the moneys deposited in the account created in this subsection for administrative purposes. During the 2021-2023 fiscal biennium, the legislature may appropriate moneys from the youth athletic facility account to support a task force to consider ways to improve equitable access to K-12 schools' fields and athletic facilities and local parks agency facilities with the goal of increasing physical activity for youth and families. A portion of the appropriation must be used to inventory K-12 school fields and athletic facilities and park agency facilities.

  2. During the 2023-2025 fiscal biennium, moneys may be used by the department of commerce and the recreation and conservation office for the public facility improvement fund, youth athletics facilities, the community outdoor athletic facilities program as provided in subsection (4) of this section, and the agencies' authorized administrative costs in administering these programs.

Section 8030

  1. The director of financial management shall provide all agencies with a complete set of instructions for submitting biennial budget requests to the director at least three months before agency budget documents are due into the office of financial management. The budget document or documents shall consist of the governor's budget message which shall be explanatory of the budget and shall contain an outline of the proposed financial policies of the state for the ensuing fiscal period, as well as an outline of the proposed six-year financial policies where applicable, and shall describe in connection therewith the important features of the budget. The biennial budget document or documents shall also describe performance indicators that demonstrate measurable progress towards priority results. The message shall set forth the reasons for salient changes from the previous fiscal period in expenditure and revenue items and shall explain any major changes in financial policy. Attached to the budget message shall be such supporting schedules, exhibits and other explanatory material in respect to both current operations and capital improvements as the governor shall deem to be useful to the legislature. The budget document or documents shall set forth a proposal for expenditures in the ensuing fiscal period, or six-year period where applicable, based upon the estimated revenues and caseloads as approved by the economic and revenue forecast council and caseload forecast council or upon the estimated revenues and caseloads of the office of financial management for those funds, accounts, sources, and programs for which the forecast councils do not prepare an official forecast. Revenues shall be estimated for such fiscal period from the source and at the rates existing by law at the time of submission of the budget document, including the supplemental budgets submitted in the even-numbered years of a biennium. However, the estimated revenues and caseloads for use in the governor's budget document may be adjusted to reflect budgetary revenue transfers and revenue and caseload estimates dependent upon budgetary assumptions of enrollments, workloads, and caseloads. All adjustments to the approved estimated revenues and caseloads must be set forth in the budget document. The governor may additionally submit, as an appendix to each supplemental, biennial, or six-year agency budget or to the budget document or documents, a proposal for expenditures in the ensuing fiscal period from revenue sources derived from proposed changes in existing statutes.

The budget document or documents shall also contain:

a. Revenues classified by fund and source for the immediately past fiscal period, those received or anticipated for the current fiscal period, and those anticipated for the ensuing biennium;

b. The undesignated fund balance or deficit, by fund;

c. Such additional information dealing with expenditures, revenues, workload, performance, and personnel as the legislature may direct by law or concurrent resolution;

d. Such additional information dealing with revenues and expenditures as the governor shall deem pertinent and useful to the legislature;

e. Tabulations showing expenditures classified by fund, function, and agency;

f. The expenditures that include nonbudgeted, nonappropriated accounts outside the state treasury;

g. Identification of all proposed direct expenditures to implement the Puget Sound water quality plan under chapter 90.71 RCW, shown by agency and in total; and

h. Tabulations showing each postretirement adjustment by retirement system established after fiscal year 1991, to include, but not be limited to, estimated total payments made to the end of the previous biennial period, estimated payments for the present biennium, and estimated payments for the ensuing biennium.
  1. The budget document or documents shall include detailed estimates of all anticipated revenues applicable to proposed operating or capital expenditures and shall also include all proposed operating or capital expenditures. The total of beginning undesignated fund balance and estimated revenues less working capital and other reserves shall equal or exceed the total of proposed applicable expenditures. The budget document or documents shall further include:

    1. Interest, amortization and redemption charges on the state debt;

    2. Payments of all reliefs, judgments, and claims;

    3. Other statutory expenditures;

    4. Expenditures incident to the operation for each agency;

    5. Revenues derived from agency operations;

    6. Expenditures and revenues shall be given in comparative form showing those incurred or received for the immediately past fiscal period and those anticipated for the current biennium and next ensuing biennium;

    7. A showing and explanation of amounts of general fund and other funds obligations for debt service and any transfers of moneys that otherwise would have been available for appropriation;

    8. Common school expenditures on a fiscal-year basis;

    9. A showing, by agency, of the value and purpose of financing contracts for the lease/purchase or acquisition of personal or real property for the current and ensuing fiscal periods; and

    10. A showing and explanation of anticipated amounts of general fund and other funds required to amortize the unfunded actuarial accrued liability of the retirement system specified under chapter 41.45 RCW, and the contributions to meet such amortization, stated in total dollars and as a level percentage of total compensation.

  2. The governor's operating budget document or documents shall reflect the statewide priorities as required by RCW 43.88.090.

  3. The governor's operating budget document or documents shall identify activities that are not addressing the statewide priorities.

  4. [Empty]

    1. Beginning in the 2021-2023 fiscal biennium, the governor's operating budget document or documents submitted to the legislature must leave, in total, a positive ending fund balance in the general fund and related funds.

    2. Beginning in the 2021-2023 fiscal biennium, the projected maintenance level of the governor's operating budget document or documents submitted to the legislature must not exceed the available fiscal resources for the next ensuing fiscal biennium.

    3. For purposes of this subsection:

      1. "Available fiscal resources" means the beginning general fund and related funds balances and any fiscal resources estimated for the general fund and related funds, adjusted for proposed revenue legislation, and with forecasted revenues adjusted to the greater of (A) the official general fund and related funds revenue forecast for the ensuing biennium, or (B) the official general fund and related funds forecast for the second fiscal year of the current fiscal biennium, increased by 4.5 percent for each fiscal year of the ensuing biennium.

      2. "Projected maintenance level" means estimated appropriations necessary to maintain the continuing costs of program and service levels either funded in the governor's budget document or documents submitted to the legislature or mandated by other state or federal law, adjusted by the estimated cost of proposed executive branch legislation, and the amount of any general fund moneys projected to be transferred to the budget stabilization account pursuant to Article VII, section 12 of the state Constitution. Proposed executive branch legislation does not include proposals by institutions of higher education, other separately elected officials, or other boards, commissions, and offices not under the authority of the governor that are not funded or assumed in the governor's budget document or documents submitted to the legislature.

      3. "Related funds" has the meaning defined in RCW 43.88.055.

    4. (b) of this subsection (5) does not apply:

      1. To any governor-proposed legislation submitted to the legislature that makes net reductions in general fund and related funds appropriations to prevent the governor from making across-the-board reductions in allotments for these particular funds as provided in RCW 43.88.110(10); or

      2. In a fiscal biennium for which the governor proposes appropriations from the budget stabilization account pursuant to Article VII, section 12(d)(ii) of the state Constitution.

  5. A separate capital budget document or schedule shall be submitted that will contain the following:

    1. A statement setting forth a long-range facilities plan for the state that identifies and includes the highest priority needs within affordable spending levels;

    2. A capital program consisting of proposed capital projects for the next biennium and the two biennia succeeding the next biennium consistent with the long-range facilities plan. Insomuch as is practical, and recognizing emergent needs, the capital program shall reflect the priorities, projects, and spending levels proposed in previously submitted capital budget documents in order to provide a reliable long-range planning tool for the legislature and state agencies;

    3. A capital plan consisting of proposed capital spending for at least four biennia succeeding the next biennium;

    4. A strategic plan for reducing backlogs of maintenance and repair projects. The plan shall include a prioritized list of specific facility deficiencies and capital projects to address the deficiencies for each agency, cost estimates for each project, a schedule for completing projects over a reasonable period of time, and identification of normal maintenance activities to reduce future backlogs;

    5. A statement of the reason or purpose for a project;

    6. Verification that a project is consistent with the provisions set forth in chapter 36.70A RCW;

    7. A statement about the proposed site, size, and estimated life of the project, if applicable;

    8. Estimated total project cost;

    9. For major projects valued over five million dollars, estimated costs for the following project components: Acquisition, consultant services, construction, equipment, project management, and other costs included as part of the project. Project component costs shall be displayed in a standard format defined by the office of financial management to allow comparisons between projects;

    10. Estimated total project cost for each phase of the project as defined by the office of financial management;

    11. Estimated ensuing biennium costs;

    12. Estimated costs beyond the ensuing biennium;

    13. Estimated construction start and completion dates;

    14. Source and type of funds proposed;

    15. Estimated ongoing operating budget costs or savings resulting from the project, including staffing and maintenance costs;

    16. For any capital appropriation requested for a state agency for the acquisition of land or the capital improvement of land in which the primary purpose of the acquisition or improvement is recreation or wildlife habitat conservation, the capital budget document, or an omnibus list of recreation and habitat acquisitions provided with the governor's budget document, shall identify the projected costs of operation and maintenance for at least the two biennia succeeding the next biennium. Omnibus lists of habitat and recreation land acquisitions shall include individual project cost estimates for operation and maintenance as well as a total for all state projects included in the list. The document shall identify the source of funds from which the operation and maintenance costs are proposed to be funded;

    17. For any capital budget request for funding in the 2023-2025 or 2025-2027 fiscal biennia by an institution of higher education to address a cost increase for any major project, a statement describing the unexpected project costs, ways the agency has mitigated or will mitigate the estimated project costs, and identification of other funding that may be applied to the project. For purposes of this subsection (6)(q):

      1. "Cost increases" means total project costs estimated above those listed in the prior agency budget request and for which the legislature relied in making a funding decision for design or construction, adjusted for C-100 inflation factors; and

      2. "Institution of higher education" has the meaning provided in RCW 28B.10.016;

    18. Such other information bearing upon capital projects as the governor deems to be useful;

    19. Standard terms, including a standard and uniform definition of normal maintenance, for all capital projects; and

    20. Such other information as the legislature may direct by law or concurrent resolution.

For purposes of this subsection (6), the term "capital project" shall be defined subsequent to the analysis, findings, and recommendations of a joint committee comprised of representatives from the house capital appropriations committee, senate ways and means committee, legislative evaluation and accountability program committee, and office of financial management.

  1. No change affecting the comparability of agency or program information relating to expenditures, revenues, workload, performance and personnel shall be made in the format of any budget document or report presented to the legislature under this section or RCW 43.88.160(1) relative to the format of the budget document or report which was presented to the previous regular session of the legislature during an odd-numbered year without prior legislative concurrence. Prior legislative concurrence shall consist of (a) a favorable majority vote on the proposal by the standing committees on ways and means of both houses if the legislature is in session or (b) a favorable majority vote on the proposal by members of the legislative evaluation and accountability program committee if the legislature is not in session.

Section 8031

(1) The public works assistance account is hereby established in the state treasury. Money may be placed in the public works assistance account from the proceeds of bonds when authorized by the legislature or from any other lawful source. Money in the public works assistance account shall be used to make loans and grants and to give financial guarantees to local governments for public works projects. Moneys in the account may also be appropriated or transferred to the water pollution control revolving fund and the drinking water assistance account to provide for state match requirements under federal law. Moneys in the account may be transferred to the move ahead WA account to provide support of public works projects funded in the move ahead WA program. Not more than 20 percent of the biennial capital budget appropriation to the public works board from this account may be expended or obligated for preconstruction loans and grants, emergency loans and grants, or loans and grants for capital facility planning under this chapter. Not more than 10 percent of the biennial capital budget appropriation to the public works board from this account may be expended or obligated as grants for preconstruction, emergency, capital facility planning, and construction projects. During the 2017-2019 and 2019-2021 fiscal biennia, the legislature may appropriate moneys from the account for activities related to rural economic development, the growth management act, the aviation revitalization loan program, the community economic revitalization board broadband program, and the voluntary stewardship program. During the 2021-2023 biennium and 2023-2025 fiscal biennia, the legislature may appropriate moneys from the account for activities related to the community aviation revitalization board. During the 2019-2021 fiscal biennia, the legislature may direct the state treasurer to make transfers of moneys in the public works assistance account to the education legacy trust account. During the 2019-2021 and 2021-2023 fiscal biennia, the legislature may direct the state treasurer to make transfers of moneys in the public works assistance account to the statewide broadband account. The legislature may appropriate moneys from the public works assistance account for activities related to the voluntary stewardship program, rural economic development, and the growth management act. During the 2021-2023 biennium, the legislature may appropriate moneys from the account for projects identified in section 1033, chapter 296, Laws of 2022.

Section 8032

The Washington state library-archives building account is created in the custody of the state treasurer. All moneys received under RCW 36.18.010(12), 36.22.175(3), and 43.07.370(3) must be deposited in the account. Expenditures from the account may be made only for the purposes of payment of the financing contract entered into by the secretary of state for the Washington state library-archives building. However, during the 2023-2025 fiscal biennium, up to $5,000,000 may be used for costs associated with the design, permitting, and conservation plan development of the library-archives building. Only the secretary of state or the secretary of state's designee may authorize expenditures from the account. An appropriation is not required for expenditures, but the account is subject to allotment procedures under chapter 43.88 RCW.

Section 8033

An irrigation district has the power to sell or lease real property owned by the district whenever its board of directors, by resolution: Determines that the property is not necessary or needed for the use of the district; and authorizes the sale or lease. Notice of the district's intention to sell or lease the property shall be made by publication at least twenty days before the transaction is executed regarding the property in a newspaper of general circulation in the county where the property or part of the property is located or, if there is no such newspaper in the county, in a newspaper of general circulation published in an adjoining county. The publication shall be made at least once a week during three consecutive weeks. The notice shall state whether the sale or lease will be negotiated by the district or will be awarded by bid.

The district may lease the property for a duration determined by the board, afford the lessee the option to purchase the property, sell the property on contract for deferred payments, sell the property pursuant to a promissory note secured by a mortgage or deed of trust, or sell the property for cash and conveyance by deed. The appropriate documents shall be executed by the president of the board and acknowledged by the secretary.

The resolution authorizing the sale or lease shall be entered in the minutes of the board and shall fix the price at which the lease, option, or sale may be made. The price shall be not less than the reasonable market value of the property; however, the board may, without consideration, dedicate, grant, or convey district land or easements in district land for highway or public utility purposes that convenience the inhabitants of the district if the board deems that the action will enhance the value of the remaining district land to an extent equal to or greater than the value of the land or easement dedicated, granted, or conveyed.

During the 2023-2025 fiscal biennium, the requirements of this section do not apply to a property transferred to the bureau of reclamation or to a public owner under section 3068, chapter . . ., Laws of 2023.

Section 8034

  1. The director of enterprise services shall have custody and control of the capitol buildings and grounds, supervise and direct proper care, heating, lighting and repairing thereof, and designate rooms in the capitol buildings to be occupied by various state officials.

  2. During the 2023-2025 fiscal biennium, the director may access and tour the top of the legislative dome and, upon request, shall provide access to any legislative member and the member's guest.

Section 8035

If any provision of this act or its application to any person or circumstance is held invalid, the remainder of the act or the application of the provision to other persons or circumstances is not affected.

Section 8036

Except for section 8022 of this act, this act is necessary for the immediate preservation of the public peace, health, or safety, or support of the state government and its existing public institutions, and takes effect immediately.


Created by @tannewt. Contribute on GitHub.